GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 819
ANSWERED ON 23RD JULY, 2026
COMPLETION OF WORK ON MUMBAI-GOA HIGHWAY
†819. SHRI NARAYAN TATU RANE:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the work under National Highway-66 (Mumbai-Goa
Highway) from Lanja to Chiplun in Ratnagiri district is still pending;
(b) if so, the details of current progress of the said pending work;
(c) the scheduled timeline set for the completion of this work; and
(d) the reasons for the delay in the execution of the work and the
steps taken by the Government to expedite its completion?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (d) Out of total 106 km length of National Highway (NH) – 66 from
Lanja to Chiplun, the works for upgradation to four-lanes has been
completed in 102 km. The balance works for construction of fly-overs in
Chiplun, Niwali, Pali and Lanja towns, finishing works on Sangameshwar
Bridge and hill cutting / road works at Kurdhunda, Kolambe, Wandri and
Kante villages covering a length of 4 km are under implementation and
targeted for completion in October, 2026. The development of NH-66 got
delayed due to delay in land acquisition and other pre-construction
activities as well as issues with some of the Contractors. All the pending
issues have been substantially resolved and these pending works on NH-
66 are targeted for completion within the revised timelines.
*****