GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO - 4243
ANSWERED ON – 01/04/2026
CONSTRUCTION AND MAINTENANCE OF NATIONAL HIGHWAYS
4243. SMT. PHULO DEVI NETAM:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) the year-wise and State-wise length of National Highways constructed during last five
years, along with total construction expenditure and the amount spent on their maintenance
and repair within five years of completion;
(b) the year-wise number of accidents and fatalities on National Highways since 2021 where
potholes, surface defects or incomplete construction were recorded as contributing factors;
and
(c) whether any contractor has been penalised or blacklisted due to premature road
deterioration or poor-quality construction and the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) The State/ Union Territory (UT)-wise and year-wise details of length of National
Highways (NHs) constructed and expenditure incurred towards development & maintenance
of NHs during each of the last five years is at Annexure-I and Annexure II respectively.
(b) The Government publishes report on “Road Accidents in India” based on data
received from States/ UTs. As per the report, total number of road accidents on National
Highways, since 2021 is given in the table below, which also includes data of road accidents
on NHs for various reasons including potholes, surface defects or incomplete construction: -
Year No. of Road Accidents on No. of Road fatalities on
National Highways National Highways
2021 1,28,825 56,007
2022 1,51,997 61,038
2023 1,50,177 63,112
2024 1,50,958 64,772
(c) The Government in the Ministry of Road Transport and Highways is primarily
responsible for development and maintenance of National Highways (NHs). As per
information provided by the executing agencies of the NHs, major deficiencies in NH
stretches during the last three years and the current year have been reported for 67 projects /
stretches. The State / UT wise details of major deficiencies in NH stretches during the lastthree years and the current year along with status of its rectification works and action taken
against contractors/ concessionaires’ consultants are at Annexure-III. Actions against
defaulting agencies are taken up as per the provisions of the Contract/ Concession agreement
in cases of deficiencies / damages, such as termination of contract agreement, levying of
penalties/ liquidated damages, debarment / blacklisting, declaring as non-performers etc.ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF RAJYA SABHA
UNSTARRED QUESTION NO. 4243 ANSWERED ON 01.04.2026 ASKED BY SMT.
PHULO DEVI NETAM REGARDING CONSTRUCTION OF NATIONAL HIGHWAYS
The State/UT wise details of length (km) of NHs constructed during each of the last five
years
Sr. No. State/UT 2020-21 2021-22 2022-23 2023-24 2024-25
1 Andhra Pradesh 515 347 438 799 757
2 Arunachal Pradesh 135 206 320 262 152
3 Assam 567 318 310 272 344
4 Bihar 691 576 488 497 465
5 Chhattisgarh 247 320 243 251 308
6 Goa 49 65 16 11 27
7 Gujarat 361 249 658 622 500
8 Haryana 406 290 358 300 287
9 Himachal Pradesh 89 146 139 251 166
10 Jharkhand 358 298 245 248 202
11 Karnataka 425 419 393 741 477
12 Kerala 344 76 171 282 193
13 Madhya Pradesh 877 871 667 792 894
14 Maharashtra 2,870 1,534 1,087 1,463 1,203
15 Manipur 224 221 269 202 216
16 Meghalaya 36 26 98 162 154
17 Mizoram 169 239 205 209 126
18 Nagaland 197 254 236 159 230
19 Odisha 683 544 410 357 330
20 Punjab 188 150 274 409 227
21 Rajasthan 825 722 715 868 794
22 Sikkim 39 45 49 78 58
23 Tamil Nadu 447 470 690 814 613
24 Telangana 227 236 172 513 416
25 Tripura 78 181 204 47 51
26 Uttar Pradesh 917 824 642 939 906
27 Uttarakhand 577 354 219 216 148
28 West Bengal 400 169 284 190 121
29 Andaman & Nicobar Islands 113 39 25 11 18
30 Chandigarh 0 0 0 0 0
31 Dadra & Nagar Haveli and Daman & Diu 3 0 0 0 0
32 Delhi 20 5 43 53 10
33 Jammu & Kashmir 234 263 217 243 214
34 Ladakh 7 0 51 81 50
35 Puducherry 7 0 0 11 0ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF RAJYA SABHA
UNSTARRED QUESTION NO. 4243 ANSWERED ON 01.04.2026 ASKED BY SMT.
PHULO DEVI NETAM REGARDING CONSTRUCTION OF NATIONAL HIGHWAYS
The State / UT - wise details of expenditure incurred towards development and maintenance
of NHs during each of the last five years
(Amount in ₹ Crore)
Sr.
State/UT 2020-21 2021-22 2022-23 2023-24 2024-25
No.
1 Andhra Pradesh 4,281 5,890 6,957 11,440 11,756
2 Arunachal Pradesh 2,512 2,718 3,140 2,649 3,599
3 Assam 3,753 3,150 4,557 9,137 7,207
4 Bihar 6,716 9,174 9,347 10,749 8,840
5 Chhattisgarh 2,224 1,936 2,468 4,255 2,280
6 Goa 734 615 673 620 651
7 Gujarat 7,533 10,710 9,831 10,900 8,091
8 Haryana 10,651 7,203 3,924 6,062 4,344
9 Himachal Pradesh 2,033 3,164 4,534 5,175 3,994
10 Jharkhand 2,627 2,853 3,127 4,599 5,169
11 Karnataka 5,838 7,681 6,763 12,695 10,819
12 Kerala 12,831 10,136 3,994 10,419 5,082
13 Madhya Pradesh 8,250 9,006 6,210 7,447 7,799
14 Maharashtra 20,844 18,655 18,355 19,867 18,512
15 Manipur 978 2,142 2,737 2,598 2,011
16 Meghalaya 861 819 684 1,803 1,697
17 Mizoram 1,238 2,054 3,218 2,189 2,091
18 Nagaland 2,382 1,943 1,666 1,414 1,600
19 Odisha 5,336 4,510 4,643 5,948 5,786
20 Punjab 3,301 7,179 10,093 12,419 7,898
21 Rajasthan 7,340 11,353 9,719 8,874 6,301
22 Sikkim 1,053 811 1,008 684 441
23 Tamil Nadu 4,868 4,305 8,230 9,925 9,068
24 Telangana 2,907 3,458 3,622 6,117 7,496
25 Tripura 1,026 1,085 1,156 1,546 767
26 Uttar Pradesh 18,768 13,944 21,453 28,114 20,665
27 Uttarakhand 2,800 2,112 3,219 4,545 3,835
28 West Bengal 2,658 3,642 3,053 3,543 2,240
29 Andaman & Nicobar Islands 349 246 143 96 204
30 Chandigarh 2 6 1 0 0
31 Dadra & Nagar Haveli and Daman & Diu 43 30 26 2 46
32 Delhi / Headquarters -1,482 3,961 7,164 3,223 2,840
33 Jammu & Kashmir 2,932 6,817 7,370 10,528 10,204
34 Ladakh 24 352 574 658 768
35 Puducherry 21 1 61 35 23
[Negative figure against State/UT during the year indicates transfer of project/expenditure from that State/UT to
other State/UT]ANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PART (c) OF RAJYA SABHA
UNSTARRED QUESTION NO. 4243 ANSWERED ON 01.04.2026 ASKED BY SMT.
PHULO DEVI NETAM REGARDING CONSTRUCTION OF NATIONAL HIGHWAYS
The State / Union Territory (UT) – wise details of major deficiencies in NH stretches in the
last three years and current year along with status of its rectification works and action taken
against contractors / concessionaires / consultants
Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Permanent solution to Slip
Zones on Papu – Yupia – Hoj
– Potin section of NH-713A &
NH-13 at Km 31.000 (Hoj Rectification of defective work
Arunachal Market), Km 38.300 (Yabi initiated by the Contractor.
1 2024 RE wall Collapsed
Pradesh Village), Km 39.000 Penalty of 5% of contract
(Waterfall), Km 39.700 (Appa value imposed on Contractor.
Crusher) and Km 40.300
(Crusher Point) in the state of
Arunachal Pradesh
Six-laning of Vijayawada
bypass from Chinna Autupalli
Concessionaire commenced
(Design Ch.0+000) to
the rectification work based
Gollapudi (Design Ch.
on recommendation
30+000) in Vijayawada – Defects in the construction
2 2024 /suggestion of RE wall Expert.
Gundugolanu Section of NH- of RE wall.
Rs.10,99,235/- was recovered
16 in the State of Andhra
as damages from
Pradesh under Bharatmala
Concessionaire.
Pariyojana on Hybrid Annuity
Mode
6 laning of existing 4-lane
Andhra road from Kalaparru (Design
Pradesh Km 1050.680) to Chinna
Avutupalli (Design Km
1076.480) of NH-5 including
Contractor rectified defects at
6-lane Hanuman Junction
his own cost.
Bypass from (Existing Km
Defects in the construction
3 1055.680 to Km 1060.800) 2025
of RE wall. Show-cause notices issued to
(Design Ch.0.000 to
Contractor as per Contractual
Ch.6.720) (Total Design
provisions.
Length: 27.40 Km) in the
State of Andhra Pradesh
under NHDP Phase-V under
Bharatmala Pariyojana on
EPC Mode (Package-2)
Four Laning of Simaria- Issues reported by CRRI
Bihar 4 2023 Repair works taken up by
Khagaria Section of NH-31 in quality of Concrete of
Contractor as recommended
from Km. 206.050 to Km. superstructure in bridge atYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
266.282 (Design Chainage) Km 264.946 in CRRI report
and (Existing Chainage Km.
209.945 to Km. 270.000 of
NH-31) in the State of Bihar
on EPC Mode
Varanasi - Mohania (GTRIP/5;
Package - IV A): 4L of existing
Major deficiencies in Damages of INR 25 Cr
5 2L section from km. 65 to km. 2023
structural elements imposed on Contractor
317 of NH-2 in UP and Bihar
on NH-2
Project Manager & Bridge
Engineer of the
Falling of concrete from
Chhapra-Hajipur Section of Concessionaire were
the deck slab of Major
6 NH-19 (New NH-31) 2023 Bridge at km 145+280 and suspended. Reconstruction
Falling of Concrete from completed by concessionaire
the Deck Slab of ROB at at their own cost.
Ch 157+860.
Umagaon-Saharsa PKG-IV
Chief Project Manager &
Engineer (Launching) of
(Kosi Bridge & approach
7 2024 A girder collapsed during Contractor suspended.
Road)
construction.
4-Laning of Simga-Sargaon
Section of NH-200 (New NH- Cracks in Cement Rectifications initiated at cost
8 2024
130) from Km 48+580 to Km Concrete Panels of EPC Contractor.
91+026
Rehabilitation & Upgradation
2-lane with paved shoulders
Chhattisgarh
configuration of Bilaspur
Urdawal section in km The work is in Defect Liability
Damage in slab of Minor
9 241.553 to 312.60 = 71.0476 2025 Period and taken up by
bridge
km (Masanialala to Rengapali) Contractor at his own cost.
on NH 200 (New NH 49)
(Package-III)(Borai river MNB
at km 217.358)
Some portion of deck slab
Arbitration notice issued to
fallen down with
Contractor for recovery of
Flyover and underpass at settlement of the
10 2024 damages. Process of
Hero Honda Chowk NH 48 bituminous surface
Rectification and repair works
Haryana (MCW-01) on RHS at Ch.
initiated.
36+350
Delhi-Vadodara Expressway Authority has imposed
11 2024 Rutting
Pkg. 2 damages amounting to
Rs.48,61,243/- on theYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
contractor for delayed
maintenance. Rectification of
rutting has been taken up by
Contractor and majority of the
rutted portion has been
rectified.
Authority has imposed
damages amounting to Rs.
42,95,049/- on the contractor
Delhi-Vadodara Expressway for delayed maintenance.
12 2024 Rutting
Pkg. 3 Rectification of rutting has
been taken up by Contractor
and majority of the rutted
portion has been rectified.
Penalty of ₹2.8 crore has
been imposed on the
Contractor along with a
Ruts, cracks and surface
recommendation for
deformation/ Distress was
debarment up to one year or
Sanchore-Santalpur Package- observed recently after
Gujarat 13 2025 until successful rectification,
4 rains in June month 2025,
whichever is later. Contractor
severe rutting at some
has taken up repair/
locations.
restoration works. The Project
Director of NHAI was
suspended.
Four Laning of Mahulia-
Baharagora-JH/WB Border
Section of NH- 33 (from
Km.277+ 500 to Km.333+500)
Cracked PQC panels, Rs. 1.55 Cr penalty imposed
Jharkhand 14 & NH-06 (from Km.199+200 to 2024
Potholes on Contractor.
Km.183+587) (Length of
71.61Km) in the State of
Jharkhand on EPC Pattern
under NHDP Phase –III.
Concessionaire has taken up
Two/Four Laning of BRT Tiger Km 337+670 to
repair/ restoration works as
15 Reserve Boundary to 2025 Km337+680 RE Block of
per recommendation of report
Karnataka
Bengalore Section of NH-948 length 10 mts collapsed
submitted by IISC Bangalore.
Four laning of Goa-Karnataka 2024
Incident of collapse of Contractor debarred for 1
16 Border to Kundapur section of
three spans of Kaali month on Aug 2024.
NH-66 (formerly NH-17) from
Bridge. Inadequate slope
Km. 93.700 to Km. 283.300 inYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
the State of Karnataka stability works.
Distress in pile foundation
NH Connectivity to ICTT at
was observed at Bridge Penalty of Rs. 30.74 Cr was
17 Vallarpdam from Kalamassery 2025
no. 07 & 08 Ch. 7+960 imposed on Contractor
to Vallarpadam NH 966A
and Ch. 9+067 (BHS)
Damages in the pile
foundation Ch. 398+400
and 398+989 (RHS)
Sub-standard work (Minor Concessionaire debarred for
Kodugallur to Edappally NH Bridge works, backfill 1 year. Rectification works
18 2025
66 material for RS Wall, Poor taken up at cost of
safety precautions, contractor.
delayed grouting of
girders, bulging of
bearing) or poor quality
(Defective RE Panels)
Authority has suspended the
Concessionaire and its
promoter from future bidding
Soil nailing collapsed
Chengala-Neeleshwaram for 01-month period.
Kerala 19 2025 incident occurred at Ch.
Section of NH-66 Debarment also issued to
58+035 to Ch. 58+100
Concessionaire. Senior
(RHS) on 16.06.2025 with
Bridge Engineer of AE
no casualties.
removed from site.
Unprotected soil slip in the Rectification work carried out
Neeleshwaram-
cut section with debris and traffic restored with
20 Thaliparambha Section of NH- 2025
deposition on precautionary barricading in
66
carriageways. median portion.
NHAI - Six laning from start of
Valanchery bypass to
Debarment of Contractor and
Kappirikkad section of NH –
Independent Engineering firm
66 (old NH-17) from Design
from participating in
Ch. 298+500 (Ex. km
21 RE wall collapsed ongoing/future bidding for 01
304.250) to Design Chainage
2025 month period or completion of
335+850 (Ex. km 349.260) in
investigation by the expert
the state of Kerala on Hybrid
Committee whichever is later.
Annuity Mode under
Bharatmala Pariyojana
Penalty of Rs. 15.35 Lakhs
Collapse of 4 PSC Girders imposed. Bridge Engineer &
22 Thuravoor-paravoor 2025
during constructions Team Leader of AE were
Terminated.Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Failure/Collapse of
Six Laning of Start of Kollam scaffolding of Minor
Penalty of Rs. 9.55 lakhs
23 Bypass to Kadambattukonam 2025 Bridge (under
imposed on Concessionaire
from Km.486+000 to construction) at Km.Ch.
Km.517+800 of NH-47 (New 497+370(RHS)
NH-66) in the State of Kerala
on Hybrid Annuity Mode under Failure of RE Wall Ch.
Rectification initiated by
24 BharatmalaPariyojna 2025 504+400 to
Concessionaire.
504+500(LHS)
Toppling of two PSC
girders at span P-202-P-
203
6L Elevated Corridor along
with development of existing 4 Contractor and AE debarred
25 lane road at ground level from 2025 Failure on part of AE to from future bidding for 1
Aroor to Thuravoor Thekku review efficacy of material month.
section of NH 66 being used in launching
and not ensuring
application of approved
launching scheme.
Soil nailing collapse At
Rectification initiated by
26 Azhiyur-Vengalam 2024 Km:191(LHS) and
Concessionaire.
Km:193(RHS
Rectification works initiated by
27 Ramanattukara-Valanchery 2025 Defects in RE wall
Contractor at his own cost.
Retaining wall sliding and Damaged portion dismantled
Thaliparamba-
28 2026 defects in ground and rectification works
Muzhapilangadu
improvement works. initiated by Concessionaire.
Penalty of Rs. 119 Cr
Madhya 4-laning of Bhopal-Bioara Premature failure of imposed on Contractor.
29 2025
Pradesh section of NH-46 pavement. Rectification work initiated at
the cost of Contractor.
Balance work for 4-laning of
Panel cracking, poor
Panvel to Indapur section Contractor has taken up
30 2024 riding quality, bumps, poor
from km.0.0 to km.42.3 of NH- rectification works.
diversions etc.
66 - EPC
The Performance BG of
Contractor is forfeited.
Maharashtra 31 Mehkar-Ajispur Road 2024 Cracked panels
Process initiated for
rectification of damages.
Contractor has initiated
32 Bhokar-Sarsam 2024 Cracked panels actions for rectification of
damages.Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Contractor has initiated
33 Sillod-Fardapur 2024 Cracked panels actions for rectification of
damages.
Rehabilitation and
upgradation & NH-66
(Erstwhile NH-17) form km
241+300 to 281+300 (Arawali Contractor has initiated
Depression & cracks in
34 to Kante Section) to four lane actions for rectification of
PQC
with paved shoulder in the 2025 damages.
state of Maharashtra under
NHDP-IV on Hybrid Annuity
Mode.
Rehabilitation & Upgradation
of NH-66 (Old NH17) from Km
281+300 to Km 332+200
PQC cracks and Contractor has replaced
35 (Kante to Waked section) to 2024
settlement. cracked panels.
four lanes in the state of
Maharashtra under NHDP-IV
on Hybrid Annuity Mode.
Rehabilitation and up-
gradation of NH-66 (Old NH-
17) form km 332/200 to km Contractor has initiated
Full depth Cracks in
36 367/200 (Watul to Talgaon 2024 actions for rectification of
PQC
Section) to four lanes in the damages.
State of Maharashtra under
NHDP-IV on EPC Mode.
Rehabilitatyion & up gradation
for Talere Gaganbawada
Kolhapur Road (NH-166G)
stretches start from Ch. 6/00
Km. to Ch. 11/00 Km. and Ch.
Contractor has initiated
19/300 Km. (Start of Karul
37 2025 Cracks in PQC actions for rectification of
Ghat) to 35/300 Km. (End of
damages.
Gaganbawada) of NH-166G
to 2 lane paved shoulder/2
lane configuration lane, length
21.00 Km. in the state of
Mahrashtra on EPC Mode.Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Rehabilitation and Up-
gradation to Two lanes with
Rectification of damages
paved shoulder from Karad to
38 2024 Cracked panels taken up at risk and cost of
Tasgaon NH 266 from Km.
Contractor.
0/00 to 58/830 in the State of
Maharashtra on EPC mode
Upgradation to two lane with
Post construction defects
paved shoulder
are observed in the Rigid IIT Bombay has been
from Salaikhurd to Tiroda
Pavement i.e. formation of appointed for Technical
Km 120/100 to 163/200
39 2024 Longitudinal & Lateral Investigation of defects and
(Design Km 44/00 to
cracks, Opening of suggestion of remedial
87/00) of NH 753 on EPC
Central Joints, Settlement measures.
Mode in the state of
of Panels etc.
Maharashtra
Penalty imposed on each
contractor amounting to Rs.
Delhi Vadodara Expressway 50 Lakhs for non-rectification
40 2024
NE-4 Pkg.06 of defects in the stipulated
time frame as per provision of
contract agreement.
Rutting, Raincuts,
Delhi Vadodara Expressway
41 2024 potholes & settlement
NE-4 Pkg.07
Delhi Vadodara Expressway
42 2024
NE-4 Pkg.08
Delhi Vadodara Expressway
43 2024
Rajasthan NE-4 Pkg.09
Construction of 6-lane access-
controlled Greenfield highway
from km 28+70 to Km. 53+0 of (i) Damage of Rs. 50.00
Sangariya (near Chautala)- Lakhs imposed upon the
Rasisar (near Bikaner) section Deficiencies in riding Contractor.
44 of NH-754K as a part of 2024 quality and settlement at (ii) Two key personnel of
Amritsar-Jamnagar Economic some locations observed Authority Engineer team were
Corridor in the State of terminated due to poor
Rajasthan under Bharatmala supervision.
Pariyojana -Phase-I (AJ/SR-
Package-2)
Construction of 6-lane access Failure of the nose Penalty of Rs. 1.00 Cr.
45 2024
controlled Greenfield highway structure while launching imposed and warning for
from km 53+000 to Km. of 83 mtr single span truss debarment action for anyYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
88+000 of Sangariya (near bridge future instances upon the
Chautala)-Rasisar (near Contractor was issued.
Bikaner) section of NH-754K
Debarment of fabrication
as a part of Amritsar-
team and Designer team
Jamnagar Economic Corridor
issued for the period of 02
in the State of Rajasthan
years in NHAI works.
under Bharatmala Pariyojana-
Phase-I (AJ/SR-Package-3) Penalty of Rs. 20 Lakhs and
warning for debarment action
for any future instances upon
the Authority Engineer.
Debarment of Senior bridge
Engineer deployed by the
Authority Engineer issued for
a period of 2 years in NHAI
works.
Damages amounting to Rs.
1.06 Cr. imposed for delayed
maintenance. Also, IIT
Delhi-Vadodara Expressway Rutting & settlement of
46 2024 Kharagpur has been engaged
Pkg. 4 approach
for detailed study for
permanent rectification of
defects.
Damages amounting to Rs.
88.32 lakhs imposed for
delayed maintenance. Bulging
of RE wall has been rectified
as per suggestions of CRRI.
Rutting, settlement of
Delhi-Vadodara Expressway Majority of the rutting has
47 2024 approach & bulging of RE
Pkg. 5 been rectified. Further, in
wall
addition to above, IIT
Kharagpur has been engaged
for detailed study for
permanent rectification of
defects.
Delhi-Vadodara Greenfield
Alignment (NH-148N) (Pkg- Stretch is operational
16) (Ch. 427.300 to w.e.f. 30.11.2023 and at
EPC Contractor has rectified
48 Ch.452.420) [Major bridge 2024 some locations the
damages. R
over Takli river near settlements observed in
Nayagaon Jageer village to approaches of structure
Rajasthan/MP Border]Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Construction of proposed 2-
Post-completion,
lane ROB and its approaches
structural defects have Contract has been
in lieu of existing level
been observed in the deck terminated. Debarment of
49 crossing no. C-64 at km. 2024
slab of the ROB due to contractor taken up. Bid for
172.990 on Jodhpur–Ajmer
honeycombing caused by rectification works invited.
Road on NH-65 in District
poor workmanship.
Nagaur Rajasthan
The RE wall blocks
4-laning of Sethiyathope -
portion of the A2
50 Cholpauram section from Km 2025 (Thanjavur) side approach The rectification work
65.960 to Km 116.440 (LHS side) have been completed by the
disconnected from the geo Concessionaire at their own
grid and fallen down. cost.
The RE wall panel portion
of the A1 (Thanjavur) side
4-laning of Thanjavur - Trichy Based on report of Expert
approach (LHS side) have
51 section from Km 80.000 to Km 2023 Committee,
been disconnected from
136.490 restoration work using soil
the geo grid and fallen
nailing completed by
down.
Contractor.
Construction of 4 lane green
The project is under
field highway from km 35.00 Cracks observed over
construction, the repair and
to 49.155 of NH-731A with DBM due to percolation of
52 2025 rectification work taken up by
paved shoulder on Hybrid rain water in some
the concessionaire at its own
Annuity Mode in the State of stretches.
Uttar Pradesh cost.
Uttar Pradesh.
Contractor has initiated
Cracks in PQC Panel in
53 Lucknow Ring Road Pkg-3A 2024 process for rectification of
length of 2.886 Km.
damages.
Contractor has initiated
Uttar Pradesh 4L of Haridwar-Nagina section
54 2023 PQC panel cracks process for rectification of
& Uttarakhand of NH-74
damages.
Construction, Operation and
Maintenance of 2-Lane Bi- Rectification measures taken
Directional Silkyara Bend up by the EPC contractors at
Barkot Tunnel with escape its own cost.
Collapse at cavity in under
passage including approaches
Uttarakhand 55 2023 construction Silkyara
on Dharasu–Yamunotri
Tunnel.
section between Ch. 25.400 Actions as per the
Km and Ch. 51.000 Km falling Investigation Committee
along NH-134 (OLD NH-94) in Report initiated.
the state of UttarakhandYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
i) Rectification works initiated
Construction of 4-Laning of by Contractor. Amount of Rs.
Puruliya Bypass Section from 20.00 Lakh withheld from
Cracks have developed in
Km. 84.030 to Km. 94.345 of Contractor's bill.
56 2025 the newly constructed
NH-32 (length 10.315 Km) in
PQC.
the State of West Bengal on ii) Key personal of AE has
EPC Mode been debarred for a period of
one year.
Four laning with paved
shoulders of NH-6 from
Chichra to Kharagpur Km
185.150 to Km 134.400 Rectification works completed
57 2023 Cracks in PQC panels
including rehabilitation of at cost of EPC Contractor.
existing four lane from Km
134.400 to Km 129.600 in the
state of West Bengal
Failure of membrane pad
of Pot – PTFE bearing on
P2 of Ahiron Bridge (Ch.
257+440 LHS MJB-truss).
Also, a level difference up
Four laning of Berhampore – Rs. 26.19 lacs penalty
to 90mm had been
West Bengal
58 Farakka Section of NH-12 (old 2024 imposed on Concessionaire.
observed between
NH-34) Rectification work completed.
expansion joint of deck-I
and deck-II along with
missing of some
anchoring bolts of
connecting gusset plates.
Crack at the bottom of the
deck slab at km 325+060
of the Mahananda Bridge
(LHS). The crack was
located under the fast lane
Four laning of Farakka – between span P1 & P2
Raiganj Section of NH-12 (old (PSC Girder).
NH-34) Rectification work initiated by
59 2024 At RHS Pier 4 of MJB at
Concessionaire.
325+223, piles are
exposed and heavy
reinforcement were
exposed. Exposed
reinforcement were
corroded.Year of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Rectification initiated by
Four laning of Berhampore –
60 2025 Rutting, Potholes, Cracks Concessionaire at his own
Farakka Section of NH-12 (old
cost.
NH-34)
Six Laning of National
Corridor NH-19 from Palsit to
Dankuni (up to NH-6
Toll has been suspended. 2
Connector) from km 588.870
61 2026 Collapse of RE Wall key personnel of IE and
to km 652.700 in the state of
Concessionaire suspended.
West Bengal under
Bharatmala Pariyojana to be
executed on BOT (Toll) basis.
1. For Faulty Design at Km
96+326, penalty imposed of
1. Faulty Design in Bridge
Rs.30 Lakhs on the
at km. 96+326:
Concessionaire and Rs.5
Lakhs on the Independent
Engineer. Team Leader of IE
2. Bridge at km. 79+614: and Key Personnel of
Concessionaire suspended.
The span A1-P1 had
dislodged from the pier P2
due to breaking of the
2. For Bridge at km. 79+614:
cantilever
Penalty of Rs.5 crore imposed
Chandikhole-Bhadrak Section Portion of the pier cap and
Odisha 62 2023 on the Contractor and Penalty
of NH-16 had fallen on the ground.
of Rs.20 lakh imposed on the
Supervision Consultant.
Appearance of wide
cracks (up to 3-4mm) in
Debarment of DPR
the pier cap on grid “P2”.
Consultant for 1 year.
Damages of deck slab
The cost of entire remedial
and girders of the
measures / reconstruction
dislodged span.
recovered from the
Concessionaire.
Construction of 6-lane
Standalone Flyovers at
Falling of one PSC Girder
Bongaigaon, Chapaguri, Penalty imposed on
at Baihata Flyover (Span
Assam 63 Pathsala, Simlaguri Chowk 2024 Contractor. Contractor
P1-P2), resulting in the
and Baihata Junctions on debarred for 4 months.
death of one person.
stretches of NH-31 & NH-31C
[new NH-27 (EW)] in the State
of Assam under BharatmalaYear of Details of Major
State/ UT S. Name of the Project Action Taken
incident damages / defects
No.
Pariyojana on EPC basis
Two Lane with paved
shoulders configuration in
Jowai-Meghalaya Assam
Penalty of Rs. 20,00,000/-
Border Section of NH - 44 Slippage of Bituminous
imposed on Contractor and
Meghalaya 64 from Km 69.200 to Km 2025 concrete for a length of
rectification work carried out
173.200 (design Ch 171.455 ) approximate 10-15 mtrs
by Contractor at his own cost.
in the state of Meghalaya
Construction of Dwarka
Expressway Package-1, from
Shiv Murti Intersection at Km P8-P9 of flyover part of
20 of NH-8 till road under Shiv Murti interchange on Remedial measures
Delhi 65 2023
Bridge (RUB) near Dwarka Dwarka Expressway completed by Contractor.
Sector-21(From Km -0.600 to toppled.
5.300) in the state of Delhi on
EPC mode
Rehabilitation of km 181.00 to
Km 206.00 section in
Andaman Trunk Road of NH-4
Distress, sinking of
to Intermediate Lane with hard Rectification works
66 2024 pavement at various
shoulder in the union Territory completed.
locations.
of Andaman & Nicobar islands
(Total length 25.00 km) on
EPC Mode” (Package-VII)
Andaman &
Nicobar
Construction of 4 Nos. of
Islands
Minor Bridges at Km 21.717, The EPC contractor has
Punching in Deck Slab
Km 23.150, Km 88.300, Km carried out the necessary
(LHS) of the minor bridge
92.100 of NH- 223 (New NH- rectifications at their own
across BD Nallah at Km
67 4) connecting South Andaman 2024 expense including
88+300 and other quality
and Baratang Island in the replacement of slab as
issues including bad
Union Territory of Andaman & recommended by CRRI-CSIR
workmanship.
Nicobar Islands on EPC report.
mode.
*****