GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3038
ANSWERED ON 06TH AUGUST, 2026
CONSTRUCTION OF RAILWAY OVER BRIDGE
†3038. SHRI PATEL UMESHBHAI BABUBHAI:
Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the date of approval and commencement of construction work
for the Vapi (Chala) to Daman and Mohangam-Navwali to Daman
Railway Over Bridge (ROB) projects in Gujarat along with their
original sanctioned cost, appointed construction agency and
scheduled completion date;
(b) the current physical and financial progress of both projects
along with total expenditure incurred till date;
(c) the reasons for non-completion of said works as per schedule
including land acquisition, railway approvals, utility shifting,
contractor performance or administrative delays and the details of
the action taken or proposed against the officers/agencies
responsible for the delay; and
(d) the total cost escalation caused by the delay along with the
revised cost, additional financial burden and the revised deadline to
complete and open both ROBs for the public?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (d) The Government in the Ministry of Road Transport and
Highways is concerned with the development and maintenance of
National Highways (NHs). Mohangam-Navwali to Daman Railway
Over Bridge (ROB) falls on NH-848B in the State of Gujarat. The
work for construction of this ROB was sanctioned by the
Government on 03.06.2020 at an estimated Total Capital Cost of Rs.
112.17 Crores. The civil construction works have been awarded to
M/s Rachana Construction Co., Mehsana with original scheduled
date of completion on 29.03.2023. So far, 55% cumulative physical
progress has been achieved and an expenditure of Rs. 44.05 Crore
has been incurred on the project.
The above project has been delayed on account of delay in
acquisition of additional land for construction of approaches to
ROB, approval of girder launching scheme by the Railways and cash
flow issues with the Contractor. These pending issues have been
substantially resolved and the work is under implementation with
revised target date of completion on 31.03.2027. As on date, no
revision of the sanctioned Total Capital Cost of the ROB is
anticipated.
As regards the Vapi (Chala) to Daman ROB, the same falls on
State Highway (SH) – 185, the development and maintenance of
which is the responsibility of the State Government of Gujarat.
*****