Parliament Question: Construction of ROBs/RUBs in Ballari Lok Sabha Constituency

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document is a response to an unstarred question in the Lok Sabha regarding the construction of Road Over Bridges (ROBs) and Road Under Bridges (RUBs) in the Ballari Lok Sabha Constituency. The response from the Minister of Railways provides details on the status of proposals for ROBs/RUBs, including budget allocation, sanction status, and expected completion timelines. The reply to the question was given on 03.12.2025. **Key Points / Main Content** * **General Information:** * Sanctioning and execution of ROB/RUB works is a continuous process prioritized based on impact on safety, mobility, and road users. * From 2004-14, 4,148 ROBs/RUBs were constructed, compared to 13,653 from 2014-25 (including 703 in Karnataka). * As of 01.11.2025, 4689 ROBs/RUBs are sanctioned at the cost of ₹1,11,583 Cr on Indian Railways, including 127 in Karnataka at a cost of ₹3,920 crore. Of these, 7 are in Ballari Lok Sabha Constituency. * **Specific ROB/RUB Works in Ballari Constituency:** * **Bridge No. 265A at Ballari Yard:** The widening work of the ROB is to be executed by the State Government (Municipal Corporation, Ballari). The State Govt. has submitted a conceptual plan for widening existing ROB No.262A, and have been advised to deposit plan and estimate charges by 17.03.2025. Reply from State Government is awaited. * **LC No. 8 between Bannihatti and Ranajithpura:** A Road Over Bridge in lieu of LC No. 8 at Km 9/800-900 has been sanctioned as part of the Toranagallu Junction - Ranajitpura Doubling Project. * **LC No. 90 between Papinayakanahalli and Bailavaddigeri:** Preparation of a Detailed Project Report (DPR) for the construction of ROB in lieu of LC No. 90 at Km 159/300-400 has been taken up. * **LC No. 37 at Km 43/200-300 Hagaribommanahalli Mariyammana halli:** ROB work in lieu of LC 37 at Km 43/200-300 has been sanctioned with an estimated cost of ₹ 45.24 crores. The work of preparation of GAD has been taken up. * **Widening of Bridge No. 39 at Km 19/800-900:** Bridge No. 39 located between Ramgad-Yeshwanthnagar stations in the Vyasa Colony Junction - Swamihalli section is a waterway bridge with adequate flow capacity. * **LC No. 10 between Hospet - Vyasa Colony Junction stations:** Preparation of Technical Feasibility Report / Detailed Project Report (TFR / DPR) for the construction of ROB/RUB in lieu of LC No. 10 at Km 4/200-300 has been taken up. * **LC No. 5 between Hospet - Vyasa Colony Junction stations:** The technical feasibility for the construction of ROB in lieu of LC No. 5 at Km 1/900-2/000 has been completed and it is found technically feasible to provide ROB at the location. Joint inspection with State Govt. has been taken up. * **Measures to Expedite Work:** * Joint survey with State Govt./Road Owning Authority is done before finalizing the General Arrangement Drawing (GAD). * Periodic meetings of Railway & State Government officials are conducted. * Standardized superstructure drawings are used. * ROB/RUB works are planned to be executed on a single entity basis by Railway wherever possible. * **Factors Affecting Completion:** * Factors such as approval of General Arrangement Drawing (GAD), land acquisition, removal of encroachment, shifting of infringing utilities, statutory clearances, law and order, and climatic conditions affect project completion timelines. **Impact Analysis** **Stakeholder: State Government (Specifically the Municipal Corporation, Ballari)** * **Impact:** Responsible for executing the widening work of Bridge No. 265A at Ballari Yard. * **Action Required:** Deposit applicable Plan and Estimate charges for the widening of existing ROB No.262A by 17.03.2025. **Stakeholder: Railway Authorities** * **Impact:** Overseeing the sanctioning and execution of ROB/RUB works in the Ballari Lok Sabha Constituency. * **Action Required:** Continue prioritizing and expediting ROB/RUB works in the area, addressing factors affecting completion timelines, and coordinating with the State Government. **Stakeholder: Road Users/Citizens of Ballari Lok Sabha Constituency** * **Impact:** Will benefit from improved safety and mobility due to the construction of ROBs/RUBs. * **Action Required:** No direct action, but will experience positive impact from the completed projects.

Key Entities Referenced

Road Over Bridges (ROBs) / Road Under Bridges (RUBs): Infrastructure projects for constructing or widening bridges and underpasses on railway lines. Ministry of Railways: The primary government body responsible for the construction and maintenance of railway infrastructure including ROBs/RUBs. Ballari Lok Sabha Constituency: The geographical area in Karnataka where the ROB/RUB projects are proposed or underway. Indian Railways: The railway network in India, responsible for the ongoing process of sanctioning and executing ROB/RUB works. South Western Railway: The specific zonal railway responsible for approving and sanctioning the works.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO.667 TO BE ANSWERED ON 03.12.2025 CONSTRUCTION OF ROBS/RUBS IN BALLARI LOK SABHA CONSTITUENCY 667. SHRI E TUKARAM: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government has examined the proposals for construction and widening of Road Over Bridges (ROBs) and Road Under Bridges (RUBs) in the Ballari Lok Sabah Constituency, including (i) Bridge No. 265A at Ballari Yard (Mothi Circle) for conversion to double line, (ii) LC No. 8 between Bannihatti–Ranajithpura, (iii) LC No. 90 between Papinayakanahalli–Bailavaddigeri, (iv) LC No. 37 between Hagaribommanahalli–Mariyammanahalli, (v) Bridge No. 39 between Yashwanthanagar–Ramaghada, and (vi) LC Nos. 10 and 5 between Hospet–V.C. Stations; (b) whether these works have been approved/sanctioned by the South Western Railway and if so, the details thereof and if not, the reasons therefor along with the steps taken for early approval and execution; and (c) the details of budget allocation, sanction status and expected completion timeline for each proposal? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c) : Sanctioning and execution of works of Road Over Bridges/ Road Under Bridges (ROBs/RUBs) is a continuous andongoing process on Indian Railways. Such works are prioritized and taken up on the basis of their impact on safety and mobility in train operations and impact on road users. Nos. of ROBs/ RUBs constructed on Indian Railways during the period 2004-14 vis a vis 2014-25 (Oct’25) is as under: Period ROBs/ RUBs constructed 2004-14 4,148 Nos. 2014-25 13,653 Nos. (including 703 Nos. in the (Oct’25) State of Karnataka) As on 01.11.2025, 4689 Nos. ROBs/ RUBs are sanctioned at the cost of ₹1,11,583 Cr on Indian Railways including 127 Nos. Road Over Bridge (ROB)/Road Under Bridge (RUB) at a cost of ₹ 3,920 crore in the State of Karnataka, which are at various stages of planning and execution. Out of 127 Nos. works of ROBs/RUBs, 07 Nos. are situated on Railway tracks in Ballari Lok Sabha Constituency. The details of ROBs/RUBs works at the mentioned locations are as under:- S.No. Locations & Name Remarks of the work 1 Bridge No. 265A at Road over Bridge No. 265-A is Ballari Yard (Mothi situated near Ballari Railway Circle) station towards Guntakal end. ROB (No.262A) at Ballari Yard (Mothi Circle) is located at Km 207/3-4 between Ballari Cantonment and Ballari stations at Ballari Junction end, Thewidening work of this ROB is to be executed by State Government (Municipal Corporation, Ballari).State Govt. has submitted a conceptual plan to Railway for widening of existing ROB No.262A.The conceptual plan has been scrutinized and state government has been advised to deposit applicable Plan and Estimate charges on 17.03.2025. Reply from State Government is awaited. 2 LC No. 8 at Km 9/800- A Road Over Bridge in lieu of LC 900 between Bannihatti No. 8 at Km 9/800-900 has been and Ranajithpura sanctioned as part of the Toranagallu Junction - Ranajitpura Doubling Project. 3 LC No. 90 at Km The work for preparation of 159/300-400 between Detailed Project Report (DPR) for Papinayakana halli, construction of ROB in lieu of LC Bailavddigeri. No. 90 at Km 159/300-400 has been taken up. 4 LC No. 37 at Km 43/200- ROB work in lieu of LC 37 at Km 300 Hagaribommanahalli 43/200-300 has been sanctioned Mariyammana halli in with an estimated cost of ₹ 45.24 the Hagaribommanahalli crores. The work of preparation of town. GAD has been taken up.5 Widening of Bridge No. Bridge No. 39 located between 39 at Km 19/800- 900 Ramgad–Yeshwanthnagar stations between in the Vyasa Colony Junction - Yashwanthanagar– Swamihalli section is a waterway Ramgad stations on bridge. The width of the bridge is Vyasa Colony Junction - adequate for flow of water to pass Swamihalli section. flood water across through its opening. 6 LC No. 10 between The work of preparation of Hospet - Vyasa Colony Technical Feasibility Report / Junction stations. Detailed Project Report (TFR / DPR) for the construction of ROB/RUB in lieu of LC No. 10 at Km 4/200-300 has been taken up. 7 LC No. 5 between The technical feasibility for the Hospet - Vyasa Colony construction of ROB in lieu of LC Junction stations. No. 5 at Km 1/900-2/000 has been completed and it is found technically feasible to provide ROB at the demanded location. Joint inspection with State Govt. has been taken up. Further, Railways have taken following measures to expedite the progress of work: i. Joint survey with concerned State Govt./Road Owning Authority is done before finalizing the General Arrangement Drawing (GAD) to ensure smooth execution.ii. Periodic meetings of Railway & State Government officials are done to resolve various issues related to ROB/RUB works. iii. Standardization of superstructure drawings for various combinations of span, skewness and width of road on Railway portion has been done to avoid delays during the design approval. This has been issued in the form of compendium, which can be directly adopted for Road Over Bridge across Railway lines for expeditious planning. iv. ROB/RUB works are planned to be executed on a single entity basis by Railway wherever possible. In case any Road Owning authority/State Govt. wants then Railway may permit them to execute the work on a single entity basis. Completion of any ROB/RUB work depends on various factors like, fixing of approach alignment, approval of General Arrangement Drawing (GAD), land acquisition, removal of encroachment, shifting of infringing utilities, statutory clearances from various authorities, law and order situation in the area of project / work sites, number of working months in a year for particular project / work sites due to climatic conditions etc. All these factors affect the completion time of the projects / works. *****