O.I.H.
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 730
TO BE ANSWERED ON JULY 24, 2025
DELAY IN COMPLETION OF WORKS BY CLASS-I CONTRACTORS
NO. 730. SHRI DHARMENDRA YADAV:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to
state:
(a) the total number of works costing more than Rupees 50 crore
that have been completed through Class-I contractors and
handed over by through agencies such as CPWD, NBCC, HSCC,
HITES, etc. to the respective client
Governments/Departments/Agencies since 2014;
(b) the number of contracts where the works were not completed on
time as per tender documents along with the details of cost and
time overruns in such cases;
(c) the number of Class-I contractors who were allowed to complete
works with more than 20% delay beyond the original time-frame
and the details/extent of cost escalation in such cases along
with reasons for the same; and
(d) the number of Class-I contractors who have been
disqualified/barred from bidding on account of delay in
completion of previous projects?
ANSWER
THE MINISTER OF STATE IN THE
MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (d): Information in respect of CPWD, NBCC, HSCC and HITES are
enclosed at Enclosures I, II, III and IV respectively.
*****CPWD (Enclosure-I)
Parliament Question Reply
a. The total number of works costing more than Rupees 87 Nos.
50 crore that have been completed and handed over
by Class-I Contractors through agencies such as
CPWD to the respective client
Governments/Departments/Agencies since 2014;
b. The number of contracts where the works were not 71 Nos.
completed on time as per tender documents along
As per
with the details of cost and time overruns in such
Annexure
cases;
A
attached.
c. The number of Class-I Contractors who were allowed 46 Nos.
to complete works with more than 20 % delay beyond
As per
the original time frame, and the extent of cost
Annexure
escalation permitted in such cases, along with
A
reasons; and
attached.
d. The number of Class-I Contractors who have been 1 No.
disqualified/barred from bidding on account of delay
in completion of previous projects?CPWD (Annexure - A)
Sl. Name of Office Total number of The number of contracts where The number of Class – I Contractors The number of
No. works costing more the works were not completed who were allowed to complete Class – I
than Rupees 50 crore on time as per tender works with more than 20% delay contractors
that have been documents along with the beyond the original time frame, and who have been
completed and details of cost and time the extent of cost escalation disqualified/barr
handed over by class overruns in such cases; permitted in such cases, along with ed from bidding
– I Contractors reasons; and on account of
through agencies delay in
such as CPWD to the completion of
respective clients previous
Governments/Depart projects?
ments/Agencies since
2014;
1. ADG(Bhopal)CE Raipur 5 1 C/o GPOA at Naya Raipur C. 1 C/o GPOA at Naya Raipur C. G.
G. Cost escalation 0.71 crore
Cost overrun Time 2 C/o Administrative building school
overrun building, Boys hostel & Girls hostel
Nil 25 including development works for
months 2 C/o NIBSM of Baronda Raipur (CG)
Administrative building school Cost escalation 2.96 Crore
building, Boys hostel & Girls 3 C/o 100 Bedded ESIC Hospital at
hostel including development Bhilai
works for NIBSM of Baronda Cost escalation2.74 crore
Raipur (CG) 4 C / o P e r m a n e n t c a m p u s of IIT
Cost overrun Time Bhillai at Kutelabhata Durg, CG,
overrun Phase-I (stage-I)
Nil 13 Cost escalation 56 Crore
months 3 C/o 100 5 C/o Super speciality hospital,
Bedded ESIC Hospital at Bhilai J a g d a l p u r u n d e r P M S S Y ( P h a s e-IV)
Cost overrun Time on Engineering procurement and
overrun construction (EPC) basis.
Nil 34 Cost escalation 0.07 crore
months 4 C/o Permanent Reason for cost and time overruns -
campus of IIT Bhillai at 10C/10CA, extra work. GST increase
Kutelabhata Durg, CG, Phase-I is the reason for cost overruns and
(stage-I) d e l a y due to disturbed site in
Cost overrun Time Jagdalpur, 1st and 2nd wave of
overrun COVID, land disputes etc.
56 Crore 20
months 5 C/o Super
speciality hospital, Jagdalpur
under PMSSY(Phase-IV) on
Engineering procurement and
construction (EPC) basis.
Cost overrun Time
overrun23 crores 44
monthsCE Bhopal 1 1 C/o Various Building under Reason for cost and time overruns -
different schemes at HSER, 10C/10CA, extra work. GST increase
Bhopal (MP)(Package-I) i s t h e r e a s o n f o r c o st overruns and
Tend. Amt. 55.05 crore d e l a y d ue to non-availability / delay
Completion Cost - 100.08 crore of receipt of drawings from the
Time overrun - 18 months c o n s ultant hired by the client
department.
SE & PD RPC 2 1 EE & SM (C)I and EE&SM(E) 1 . 1 E E & S M (C)I and EE&SM(E)
Raipur Cost overrun Nil S h i f t i n g o f e x i s t i ng services in the
Time overrun 36 months l a y o u t which were not conveyed by
2 EE & SM (C)II and EE&SM(E) c l i e n t w h i l e t e n d e ring the work
Cost overrun 0.40 crore 1 . 2 I m p a c t o n w ork due to 1st and
Time overrun 21 months 2nd wave of COVID-19 & drastically
impacted due to project located in
containment zone. 2. EE & SM (C)II
and EE&SM(E) Reasons for Cost
Overruns Due to payment on
account of change in GST slab from
12% to 18% Additional 6% GST has
been paid to the Agency from
01.07.2022. Reason for time overrun
- Due to COVID pandemic .SE & PD Indore 3 1 M/s Asian constn Co. Ajmer C h a n g e i n s c o p e a n d a d ditional
Est. Cost - 51.78 crore s c o p e b y t h e c lient.
upto date expn. - 65.82 crore
Time overrun- 17 months
2 M/s. B L Infra Proj P Ltd.
Est. Cost - 69.86 crore
Actual expn. 129.16 crore
Time overrun - 13 months
3 M/s. DEE VEE Proj Ltd.
Tend Amt. 255.96 crore
Actual expn. 343.25 crore
Time overrun- 14 months
SE & PD Bhopal 1 1 C/o CAPT at Kanhasaiya Delay due to drawings and decision
village, Bhopal (Package-4b) p e n d i n g , s h o r t a g e o f f u n d etc.
Time overrun - 453 days
2 ADG(Border) Nil Nil Nil Nil3 ADG(Guwahati) 1 Cost overrun Time overrun Nil Nil
Nil 256 days
4 ADG(Hyderabad) 11 2 3 Nil
5 ADG(Jammu) nil nil nil Nil6 ADG(Kochi) 6 6 (annex B) 6 (annex B) (annex B)
7 SDG(Chennai) 8 10(annex C) 6(annex C) Nil
8 ADG(Delhi) 5 1No. - Time overrun 2yr 01 No. - Escalation paid as per Nil
4months 18 days C l a u s e o f a greement amounting to
1No. - Time overrun 3 Rs. 6,56,65,221/- and EOT was
months Cost overrun - 78 sanctioned without levy of
crore compensation.
02 Nos. - Escalation paid as per
Clause of agreement amounting of
Rs. 7,76,42,588/- and EOT was
sanctioned without levy of
compensation.
01 No. - Cost escalation
26%(Approx.) due to Covid-19.9 SDG(PRND) 1 Tend. Amount 66.48 crore 0 1 n o . Of contractor was allowed to Nil
Final cost 80.99 crore complete such work with a cost
Time overrun - 1 year 7 months excalation of Rs 14.50 crore. The
29 days delay was due to various hindrances
at site.10 ADG Lucknow 14 10 Nos. 10 Nil
1. Construction of Office
Building for Central Excise &
Custom, DRI. CBN, NACEN etc.
including water supply,
sanitary installation, internal
electrical installation, Fire
Fighting System. Fire Alarm,
Sub-Station, DG Sets, Lifts,
HVAC & UPS at Vibhuti Khand,
Gomti Nagar, Lucknow.
No Cost Over run
Time over run 3 Year 7 Months
2. C/o Office Building & Guest
House for AG, UP, Gomti Nagar,
Lucknow. No Cost Over run
Time over run 3 Year 3 Months
3. C/o Engineering core lab
building Basement plus ground
plus five storey including
plumbing, sewerage system,
internal and external Electrical
works, Fire-fighting, Fire alarm,
CCTV, system, Access Control
System, PA system, Building
Management System, Lift.
HVAC all complete at IIT
Campus, Kanpur. No Cost Over
run Time over
run 1 Year 10 MonthsADG Lucknow 4. C/o Retrofitting of Aerospace
Engineering department
building into multi-storeyed
building basement plus ground
plus six storey including
plumbing, sewerage system,
internal and external Electrical
works, Fire fighting, Fire alarm,
CCTV, system, access Control
System, PA system, Building
management System, Lift,
HVAC all complete at IIT
Campus, Kanpur. No Cost
Over run Time over run
2 Year 8 Months
5. Construction of Science &
Technology building (G+5) for
IIT Kanpur including internal
water supply, sanitary
installation, internal electrical
installation, HVAC, IMBS, Lifts,
Fire fighting, Fire Alarm
System, Public Address
System, pathways and all other
related work to make the
building function on
Engineering procurement and
construction (EPC) basis at IIT
Campus, Kanpur. No Cost Over
run
Time over run 1 Year 5 MonthsADG Lucknow 6. Construction of Research
Lab Complex Building,
basement plus Ground plus
Four Storey with mezzanine
floor including plumbing, Fire
alarm, sewerage system,
Building external Electronic
works, Fire fighting, Fire alarm,
PA system, Building
Management system, Lift,
HVAC, external development,
pathways all complete and all
other related work to make the
building function on
Engineering Procurement and
construction EPC basis at IIT
Campus, Kanpur.
No Cost Over run
Time over run 1 Year 9
Months
7. Construction of General Pool
office accommodation i/c water
supply sanitary installation
internal electrical installation
lift, electrical sub-station
installation, DG sets, fire-
fighting system and
mechanical ventilation at
Fazalganj, Kanpur.
No Cost Over run
Time over run 2 Year 8 MonthsADG Lucknow 8. Construction of GST building
(2 Basement + G+7 Floor)
composite structure on EPC
basis at Kamla Nehru Nagar
(Near HapurChungi), Ghaziabad
(UP) Tendered
Cost - 74.64 crore
Gross Work done - 96.37 crore
Time over run 1 Years 2
Months
9. Re-surfacing of runway at
Air Force Station Hindan (SH:
Surfacing and widening of
runway, taxi track, dispatch
etc. and conversion of
ORA/SGA into rigid pavements
rigid turn pads)
Tender Cost- 1,16.50 crore
Gross Work done - 133.28 crore
Time over run 2 Months
10 Provision of Security Wall at
Air Force Station, Hindan (SH:
Civil work)
Tender Cost- Rs. 76.27 crore
Gross Work done - 95.36crore
Time over run 2 Years 6
Months11 ADG (Bangalore) 0 Nil Nil Nil
12 ADG(Proj Delhi) 2 Nil Nil Nil
13 ADG(Patna) 11 Nos (annexure D) 11 Nos (Annexure D) 11 Nos (Annexure D) Nil
14 SDG (Kolkata)CE (Kolkata) 3 1. C/o Building for ICDWQ at No of Contractor allowed - 3 Not Aplicable
Joka Cost Esclation - 0
Cost overrun Time
overrun
87.92 cr 22
months
2. C/o I.T Park for STPI at Plot
No.5/1 Block DP
Cost overrun Time
overrun
69.64 cr 2yrs
10 months
3. C/o Office building for CFSL
at Rajarhat
Cost overrun Time
overrun
72.04 cr. 5yrs 2
months
CA (Kolkata) Nil
CE (Berhampur) 1 No of works not completed. 1 No of Contractor allowed - 1 Not Aplicable
Cost overrun Time Cost Esclation - 75,22,764
overrun
Nil 392 days
CE Nil Not Aplicable
(Bhubaneswar)
CE (IIT 1 No of works not completed. 1 No of Contractor allowed - 1 Not Aplicable
Kharagpur) Cost overrun Time Cost Esclation - 0
overrun
Nil 699 days
SE Siliguri 2 NilSE (IIIT Kalyani) Nil No of works not completed. 1 No of Contractor allowed - 1 No of
Cost overrun Time Cost Esclation - 0 contractor
overrun barred - 1
Nil 52
months
SE (Durgapur) Nil
SE (IIMC Joka) Nil
SE (Rourkela) 1 Nil Not Pertains
SE (Barasat) 2 1. C/o office cum residential No of Contractor allowed - 1 Not Aplicable
and hostel complex for the Cost Esclation - 0
Dept. of NIPER at Panihati,
Kolkata
Cost overrun Time
overrun
Nil 07
Months
SE 0 1. C/o New Admin. Building No of Contractor allowed - 2 Not Aplicable
(AIIMS Cost overrun Time Cost Esclation - 0
Bhubaneswar) overrun
Nil 49
Months
2. C/o Critical Care Hospital
Cost overrun Time
overrun
Nil 12
MonthsSE (Rajarthat) 1 1. C/o Corporate Bhawan, New No of Contractor allowed - 1 Not Aplicable
Town, Kolkata Cost Esclation - 0
Cost overrun Time
overrun
Nil 3 Years & 4
Months
SE (RTI) Nil
15 ADG(Chandigarh 6 Nos (annexure E) 6 Nos (Annexure E) 6 Nos (Annexure E) Nil
)CPWD (Annexure-B)
Sl.No Agreement Completion Cost Over Time as Time for Time Reason for delay
Amount Cost (Cr) run (Cr) per Actual over run
(Cr) Contract Completion (Months)
condition (Months)
(Months)
1 Rs. 77.78 Rs. 87.68 9.90 15 51 36 1) Restricted working space and
However, shortage of space for material
No cost storage.
over run. 2) Work affected during Covid 19
Completion lockdown.
was within
the AA&ES
sanction
2 Rs. 73.52 Rs. 67.01 Nil 24 41 17 1) Delay in removal of old centring
shuttering done by earlier agency
engaged by IISER.
2) Delay in handing over of entrance
room multipurpose hall & central
court in indoor stadium done by
earlier agency engaged by IISER.
3) Due to floods in August 2018.
3 Rs. 135.01 Rs. 118.95 Nil 24 38 14 1) Additional requirement fromclient regarding E&M works.
2) Due to floods in August 2018.
4 Rs. 76.04 Rs. 69.53 Nil 24 42 18 1) Due to floods in August 2018,
August 2019.
2) Revision in foundation drawings,
lift well details and retaining walls
etc.
5 Rs. 106.15 Rs. 56.74 Nil 18 60 42 1) Major reasons are revision in
Structural drawings due to changes
asked by the client and shortage of
funds.
2) Due to floods in August 2018,
August 2019.
3) Covid Pandemic 2020, 2021 and
litigation.
6 Rs. 68.53 Rs. 84.57 Rs. 16.04 18 43 25 1. Non availability of funds
2. Delay in providing drawings by
consultant appointed by Client.CPWD (Annexure-C)
Sl No Name of Work Cost over run Time Over Run
1 Construction of 96B Type 4 Cr 1.32 times
faculty apartments (3 block
each 32 flats G+8 floor) at
IIT Madras at Chennai
2 Construction of Boys 10 Cr 1.82 times
Hostel by replacing
existing Mandakini Hostel
at IIT Madras, Chennai-36.
Sub work 1: Building
Portion including Water
Supply, Sanitary
Installations, Drainage,
Dismantling of existing
structured Development
works
3 Construction of New 34 Cr 2.03 times
Academic Complex-II at IIT
Madras, Chennai-36
4 Construction of Hostel NA 2.14 times
blocks G plus 4, Academic
Research Block G plus 2
with Food Court, Utility and
Common Services at
Thaiyur B Village for IIT
Madras Discovery Campus.
(Determined under Clause-
3)
5 Construction of 152 NIL 724 days
Quarters (60 Nos. Type II,
30 Nos. Type III, 30 Nos.
Type IV, 20 Nos. Type V
and 12 Nos. Type VI), M.S.
Residence, Dean
Residence, Servant
Quarters, 240 Nos. BoysHostel, 240 Nos. Girls
Hostel, 150 Nos. Nurses
Hostel, Service Buildings
and development works
like filling, roads, storm
water drains, drainage,
bore wells, underground
sump, sewage treatment
plant, open parking, water
treatment plant, etc. for
Residential and Academic
Campus for JIPMER,
Karaikal.
6 Construction of Composite Work in 25 Months upto
Block Building and 2 Nos. Progress July 25
Semi-Permanent Buildings
including associated
development works and
bulk services at NIT
Puducherry Campus,
Karaikal.
7 Construction of Medical NIL 416 days
College Building and
associated development
works and bulk services at
Academic Campus for
JIPMER, Karaikal
8 Construction of 456 Boys work in 16 months upto
Hostel Block No. 2 (G+4) progress July 25
Storeys, Vertical Extension
of existing Girls Hostel for
2 (Two) Floors, Common
Amenities Centre (Single
Storey building) at NITpy
campus, Karaikal.
9 Construction of 152 Nos. Rs.230.89 1048 days
Type- II, 304 Nos. Type-III Crores
and 76 Nos. Type- IV for
Central Revenue Quarters
at Ranganathan Garden,Anna Nagar West, Chennai.
10 Construction of 726 Nos. Rs.282.07 409 days
Residential Quarters (288 Crores
Nos. Type- II, 288 Nos.
Type-III with stilts parking
and 150 Nos. Type-IV) for
Customs/Central Excise
Department at Central
Revenue Colony Land at
Ranganathan Garden, Anna
Nagar West, Chennai.Sl No Name of Work Cost Escalation Reason
1 Construction of 96B Type Nil Delay due to
faculty apartments (3 reasons beyond
block each 32 flats G+8 the control of
floor) at IIT Madras at the contractor
Chennai
2 Construction of Boys 9 Lakhs Delay due to
Hostel by replacing reasons beyond
existing Mandakini Hostel the control of
at IIT Madras, Chennai-36. the contractor
Sub work 1: Building
Portion including Water
Supply, Sanitary
Installations, Drainage,
Dismantling of existing
structure and
Development works
3 Construction of New 90 Lakhs Delay due to
Academic Complex-II at reasons beyond
IIT Madras, Chennai-36 the control of
the contractor
4 - 4.5% permitted Due to Force
Majeure COVID
and abnormal
bad weather
conditions
5 Construction of 152 Nos. Rs.30,18,23,565 1) Covid 19
Type- II, 304 Nos. Type-III Lock down
and 76 Nos. Type- IV for period.
Central Revenue Quarters 2) Want of fund.
at Ranganathan Garden,
Anna Nagar West,
Chennai.
6 Construction of 726 Nos. Rs.10,41,40,007 1) Covid 19
Residential Quarters (288 Lock down
Nos. Type- II, 288 Nos. period.
Type-III with stilt parking 2) Want of fund.
and 150 Nos. Type-IV) for
Customs/Central Excise
Department at Central
Revenue Colony at
Ranganathan Garden,
Anna Nagar West,
Chennai.CPWD (Annexure - D)
Reply received from different Unit under O/o ADG, Patna
Sl. Question CE(Patna) CE ( AIMS & SE SE ( SE cum CE & ED Dhanbad SE Bhagalpur
No (Ranchi) IIT Patna) (Bodhgaya) Muzaffa PD (
rpur) Jamshed
pur)
(A) The total number of Nil Nil 02 02 Nil 02 3 Nos. 02
works costing more
than Rupees 50
crore that have been
completed and
handed over by
Class-1 contractors
through CPWD to the
respective client
Governments /
Departments
Agencies since 2014:
(B) The number of Not Not T.O.R (a) - 02 Not T.O.R (a) 3 Nos. 02
contracts where the Applicable Applicab 2.26 Applica - 1.25 1 . T .O.R. 3.92 T.O.R (a) - 2.95
works were not le C.O.R - 0 ble T.O.R (b) C.O.R. Rs. 43.88 T.O.R (b) - 1.78
completed on time T.O.R (b) - - 1.8 Cr.
as per tender 2.47 2. T.O.R. 1.9
documents along C.O.R-0 C.O.R. Rs. 23.41
with the details of Cr.
cost and time 3. .T.O.R. 2.72
overrums in such C.O.R. Rs. 22.60
cases: Cr.(C The number of Class- Not Not There is 02 Cost Not 1. Cost 3 Nos. 02
) I contractors who Applicable Applicab no cost Escalatio Applica escalati 1. C/o 1000 Room 01. Nil
Boys Hostel
were allowed to le escalation permitted ble on was 02. 1.75 Crore
C.O.R. Rs. 43.88 Cr.
complete works with for both as per NIT paid as
Reason:
more than 20% delay the works conditions per the
a) Existing services
beyond the original as both provisio
line.
time frame, and the have been ns of the
b) Change in layout
extent of cost completed agreeme from sanctioned
escalation permitted within AA nt. No G+10 floor to G+15
in such cases along & ES escalati floor due to site
with reasons; and on has constraints.
c) Fund constraint
been
during 2016 to
granted
2019.
on
d) COVID-19
account
pandemic
of time
e) Delay go ahead
overrun. decision for 8th to
2. Cost 10th floor of
escalati kitchen block.
on was f) Relocation of UG
sump etc.
nil as
2. C/o 600 Room
escalati
Girls Hostel
on
C.O.R. Rs. 23.41 Cr.
clause
Reason:
was not
a) Existing services
applicab & structure.
le) b) Fund constraint
during 2016 to
2019.
c) Restriction
imposed for lifting
of sand by NGT.
3. C/o Type-V & VIQtrs.
C.O.R. Rs. 22.60 Cr.
Reason:
a) Existing services
& structure.
b) Fund constraint
during 2016 to
2019.
c) COVID-19
pandemic.(D) The number of class- Doesn't pertain to this office.
I Contractors who
have been
disqualified / barred
from bidding on
account of delay in
completion of
previous project ?CPWD (Annexure-E)
S.No. Question Reply
(a) The total number of
works costing more
than Rs. 50 crore
that have been 6 Nos.
completed and
handed over by
Class-I Contractors
through CPWD to the
respective client
Governments/
Departments/
Agencies since
2014;
(b) The number of S. Name of work Cost Time overrun
contracts where the No. overrun
works were not (in Cr.)
completed on time 1. C/o 240 bedded hospital 23.70 25 months
as per tender building at Hamirpur
documents 2. C/o office building for Nil 31 months
alongwith the RBI at IT park,
details of cost and Dehradun
time overrun in such 3. Construction of faculty Nil 26 Months
cases; housing (Phase I, 60
flats &Phase II, 120
flats) at IIT Roorkee,
Roorkee, Uttarakhand
4. Construction of 800 Nil 37 Months
capacity students Hostel at
IIT Roorkee, Roorkee,
Uttarakhand.
5. Construction of 572seater Nil 14 Days
student EWS hostel (Phase-1
works on EPC basis at
Vigyan Kunj, IIT Roorkee,
Roorkee, Uttarakhand.
6. C/o 72 Nos. T-V & 27 Nos. T- Nil 27 months
VI qtrs. at AIIMS Rishikesh.
(c) The number of Unit No. of Cost Reason
Class-1 contractors Class-I overrun
who were allowed contra (in Cr.)
to complete works ctor
with more than 20% CE cum ED, 1 No. 23.70delay beyond the Chandigarh
original time frame, CE-Dehradun 1 No. Nil
and the extent of SE cum PD, 2 Nos. Nil
cost escalation Roorkee Permitted as per the
permitted in such SE cum PD, 1 No. Nil provision of agreement.
cases, alongwith Uttarakhand
reasons; and Total 5 Nos.
(d) The number of
Class-1 contractors
who have been 1 No.
disqualified / barred
from bidding on
account of delay in
completion of
previous projects?NBCC (Enclosure-II)
Sl.
Question Reply (in Nos.)
No.
The total number of works costing more
than Rupees 50 Crore that have been
completed and handed over by Class-I
(a) 92
Contractor through NBCC to the respective
client/Governments/Departments/Agencies
Since 2014.
The number of contracts where the works There was time overrun
were not completed on time as per tender for 57 Projects.
(b)
documents along with the details of cost
Out of 57 Projects, 54
and time overruns in such cases.
Projects’ time overrun
was more than 20% of
original time frame.
The number of Class-I Contractors who Out of 54 Projects, for 7
were allowed to complete works with more Nos. Contract cost
than 20% delay beyond the original time escalation was paid as
(c)
frame, and the extent of cost escalation per the Contract
permitted in such cases, along with (Enclosure-II-A)
reasons; and
For remaining 3, details
of time/cost overrun are
as per Enclosure-II-B
The number of Class-I Contractors who
have been disqualified/barred from bidding
(d) 5
on account of delay in completion of
previous projects?
Further, it is to mention that, there is no any contractor class bifurcation in bidding
process at NBCC (I) Ltd., all the tenders are called through open e-tender process.NBCC (Enclosure-II-A)
Sl. No. Name of Time Over Run / Cost Over Run
Project
1 East Kidwai 03 nos. of contractor are allowed to complete
Nagar, New the work beyond the time frame due to various
Delhi hindrance at site like Relocation of Labour
Hutment and shifting of existing services etc.
Escalation is paid only as per applicable whole
sale Price index for labour and material rate.
Time Extent approx. 18 months.
2 ESIC MGM Rs. 12.33 Cr Escalation released by client on
Hospital Parel, account of delay in deviation approval and delay
Mumbai in decision from the client. Time Extent:
approx.36 Months .
3 ESIC Trauma Rs. 4.5 Cr (Escalation paid to Contractor. ), Delay
centre, in handing over of encumbrance free site, Delay
Lucknow in approval of deviation & decision from client.
Time Extent: approx. 24 Months.
4 ESIC dental Rs. 10.13 Cr (Escalation released to contractor),
college & Delay in handing over of encumbrance free site,
Renovation of Delay in approval of deviation & decision from
ESIC hospital, client. Time Extent: approx. 12 Months.
Pandu Nagar,
Kanpur :
5 ESIC Mandi, Rs.66 Cr (Cost Escalation), Delay in handing
Himachal over of encumbrance free site, Delay in approval
Pradesh of deviation & decision from client. Time Extent:
approx. 15 Months.
Total Nos 07 NosNBCC (Enclosure-II-B)
Sl. No. Name of Project Time Over Run / Cost Over Run
1 CISF, Ranchi. Time overrun - 24 Months,
Cost Overrun - Nil.
Reason of Time overrun - Delay on the part of
Contractor.
2 CISF, Mahipalpur. Time overrun - 3 Months,
Cost overrun - Nil.
Reason of Time overrun - Delay on the part of
Contractor.
3 Medical College Time overrun - 14 Months,
Dungarpur,
Cost overrun - Nil.
Rajasthan.
Reason of Time overrun - Delay in vacant old
quarters and handing over of encroachment
free site, Shifting of overhead HT line, Delay
in release of funds from Medical Education
Dept.HSCC (Enclosure-III)
Sl.
Question Reply (in Nos.)
No.
The total number of works costing more than
Rupees 50 Crore that have been completed and
handed over by Class-I Contractor through HSCC
(a) 52
to the respective
client/Governments/Departments/Agencies Since
2014.
The number of contracts where the works were
50
not completed on time as per tender documents
(b)
along with the details of cost and time overruns
(Enclosure–III-A)
in such cases.
The number of Class-I Contractors who were
allowed to complete works with more than 20%
42
(c) delay beyond the original time frame, and the
(Enclosure-III-A)
extent of cost escalation permitted in such
cases, along with reasons; and
The number of Class-I Contractors who have
(d) been disqualified/barred from bidding on account Nil
of delay in completion of previous projects?HSCC (Enclosure–III-A)
(d)
CONTRACTOR
(a) ( b ) ( c ) D I S Q A L I F I E D /
WORKS COMPLETED BY WORKS NOT COMPLETED BY WORKS COMPLETED B A R R ED
S.No. CONTRACTOR S . N o . C O N T R A C T O R O N T I M E ( 2 0 % d e l a y b e y o n d o r i g i n a l (on account
(50 cr. or more since (with details like Project Cost, time), if esacalation, of delay in
2014) Time overrun) mentioned reasons completion of
previous
project)
1 Construction of OPD 1 Construction of OPD Block & Rs. 126403865, Escalation NIL
Block & Other Associated Other Associated Services and Amount was paid upto actual
Services and their their Maintenance during Defect date of completion whereas
Maintenance during Liability Period in AIIMS indices were freezed as per
Defect Liability Period in Campus, Ansari Nagar, New stipulated date of completion
AIIMS Campus, Ansari Delhi for AIIMS, New Delhi REASONS: Extension of Time
Nagar, New Delhi for was granted without levy of
AIIMS, New Delhi Liquidity Damages. (Reason
not attributable to contractor
and HSCC)
2 Construction of Geriatrics 2 Construction of Geriatrics Block final bill not submitted
Block Including Including Associated Works,
Associated Works, Operation & Maintenance during
Operation & Maintenance defect liability period in AIIMS
during defect liability Campus, Masjid Moth, Newperiod in AIIMS Campus, Delhi
Masjid Moth, New Delhi
3 Construction of Mother & 3 Construction of Mother & Child Rs. 203762349, Escalation
Child Block Including Block Including Associated Amount was paid upto actual
Associated Works, Works, Operation & date of completion whereas
Operation & Maintenance Maintenance during defect indices were freezed as per
during defect liability liability period at Masjid Moth stipulated date of completion
period at Masjid Moth Area, Ansari Nagar, New Delhi REASONS: Extension of Time
Area, Ansari Nagar, New for AIIMS, New Delhi was granted without levy of
Delhi for AIIMS, New Liquidity Damages. (Reason
Delhi not attributable to contractor
and HSCC)
4 Construction of Burn & 4 Construction of Burn & Plastic Rs. 173215726, Escalation
Plastic Surgery Block & Surgery Block & Other Amount was paid upto actual
Other Associated Associated Services and their date of completion whereas
Services and their Maintenance during Defect indices were freezed as per
Maintenance during Liability Period at J.P.N. APEX stipulated date of completion
Defect Liability Period at Trauma Centre AIIMS, New REASONS: Extension of Time
J.P.N. APEX Trauma Delhi was granted without levy of
Centre AIIMS, New Delhi Liquidity Damages. (Reason
not attriibutable to contractor
and HSCC)5 Construction of Hospital, 5 Construction of Hospital, OPD & Rs 649368228, Escalation
OPD & Other Associated Other Associated Services and Amount was paid upto actual
Services and their their Maintenance during Defect date of completion whereas
Maintenance during Liability Period for National indices were freezed as per
Defect Liability Period for Cancer Institute at Badsha, stipulated date of completion
National Cancer Institute Jhajjar, Haryana REASONS: Extension of Time
at Badsha, Jhajjar, was granted without levy of
Haryana Liquidity Damages. (Reason
not attributable to contractor
and HSCC)
6 Construction of 6 Construction of Residential Rs. 293550535, Escalation
Residential Complex for Complex for National Cancer Amount was paid upto actual
National Cancer Institute Institute (NCI) including date of completion whereas
(NCI) including Associated Services and indices were freezed as per
Associated Services and Operation & Maintenance during stipulated date of
Operation & Maintenance Defect Liability Period at completionREASONS:
during Defect Liability Badsha, Jhajjar, Haryana Extension of Time was
Period at Badsha, Jhajjar, granted without levy of
Haryana Liquidity Damages. (Reason
not attributable to contractor
and HSCC)7 Construction of New Paid 7 Construction of New Paid Ward Rs. 93658486, Escalation
Ward including including Associated Works, Amount was paid upto actual
Associated Works, Operation & Maintenance during date of completion whereas
Operation & Maintenance defect liability period in AIIMS indices were freezed as per
during defect liability Campus, Ansari Nagar, New stipulated date of completion
period in AIIMS Campus, Delhi for AIIMS, New Delhi REASONS: Extension of Time
Ansari Nagar, New Delhi (Balance Work) was granted without levy of
for AIIMS, New Delhi Liquidity Damages (Reason
(Balance Work) not attributable to contractor
and HSCC)
8 Construction of Hostel 8 Construction of Hostel Block for Rs. 260365035, Escalation
Block for Resident Resident Doctor’s including Amount was paid upto actual
Doctor’s including associated works, Operation & date of completion whereas
associated works, Maintenance during defect indices were freezed as per
Operation & Maintenance liability period for PGIMER, Dr. stipulated date of completion
during defect liability RML Hospital, New Delhi REASONS: Extension of Time
period for PGIMER, Dr. was granted without levy of
RML Hospital, New Delhi Liquidity Damages (Reason
not attributable to contractor
and HSCC)
9 Construction of Hospital, 9 Construction of Hospital, OPD & Rs. 6837990, Escalation
OPD & Other Associates Other Associates Works for Amount was paid upto actual
Works for Kalpana Kalpana Chawla Govt. Medical date of completion whereas
Chawla Govt. Medical College (KCGMC), Karnal, indices were freezed as perCollege (KCGMC), Karnal, Haryana (Package-II) stipulated date of completion
Haryana (Package-II) REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attriibutable to contractor
and HSCC)
10 Construction of Housing 10 Construction of Housing Block Rs. -580167, Escalation
Block for Proposed for Proposed Kalpana Chawla Amount was paid upto actual
Kalpana Chawla Govt. Govt. Medical College (KCGMC), date of completion whereas
Medical College Karnal, Haryana indices were freezed as per
(KCGMC), Karnal, stipulated date of completion
Haryana REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
11 Construction of Hospital 11 Construction of Hospital & Rs. 169892348, Escalation
& Medical College for All Medical College for All India Amount was paid upto actual
India Institute of Medical Institute of Medical Sciences date of completion whereas
Sciences (AIIMS) at (AIIMS) at Raebareli, Uttar indices were freezed as per
Raebareli, Uttar Pradesh Pradesh (U.P.). stipulated date of completion
(U.P.). REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reasonnot attributable to contractor
and HSCC)
12 Construction of Housing 12 Construction of Housing Rs. 169892348, Escalation
Complex including Complex including external Amount was paid upto actual
external development & development & services for date of completion whereas
services for AIIMS (Under AIIMS (Under PMSSY) at indices were freezed as per
PMSSY) at Raebareli Raebareli (U.P.). stipulated date of completion
(U.P.). REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
13 Construction of 13 Construction of ADVANCED Rs. 111579143, Escalation
ADVANCED NEUROSCIENCES CENTRE and Amount was paid upto actual
NEUROSCIENCES their Maintenance during Defect date of completion whereas
CENTRE and their Liability Period at PGIMER, indices were freezed as per
Maintenance during Chandigarh on Comprehensive stipulated date of completion
Defect Liability Period at Design, Engineering, REASONS: Extension of Time
PGIMER, Chandigarh on Procurement and Construction was granted without levy of
Comprehensive Design, EPC basis Liquidity Damages (Reason
Engineering, Procurement not attributable to contractor
and Construction EPCbasis and HSCC)
14 Construction of Sub- 14 Construction of Sub-Specialty Nil
Specialty Hospital block Hospital block for NIMHANS.
for NIMHANS. Bangalore” Bangalore”
15 Construction for left out 15 Construction for left out building Nil
building works including works including finishing,
finishing, airconditioning, airconditioning, electrical
electrical works, roads, works, roads, footpaths,
footpaths, sewerage, OT, sewerage, OT, auditorium, IT,
auditorium, IT, gases gases manifold, electrical,
manifold, electrical, substations and all otherelated
substations and all services for Oncology and
otherelated services for Academic Block under
Oncology and Academic comprehensive Redevelopment
Block under Plan for Lady Hardinge Medical
comprehensive College and Associated
Redevelopment Plan for Hospitals New Delhi and their
Lady Hardinge Medical Operation and Maintenance
College and Associated during the Defect Liability
Hospitals New Delhi and Period.
their Operation andMaintenance during the
Defect Liability Period.
16 Construction for left out 16 Construction for left out building Nil
building works including works including finishing, air-
finishing, air-conditioning, conditioning, electrical works,
electrical works, roads, roads, footpaths, sewerage,
footpaths, sewerage, OT0, electrical substations and
OT0, electrical all other related services for
substations and all other OPD, IPD and Accident and
related services for OPD, Emergency A and E Block under
IPD and Accident and comprehensive Redevelopment
Emergency A and E Block Plan for Lady Hardinge Medical
under comprehensive College and Associated
Redevelopment Plan for Hospitals, New Delhi and their
Lady Hardinge Medical Operation and Maintenance
College and Associated during the Defect Liability
Hospitals, New Delhi and Period
their Operation and
Maintenance during the
Defect Liability Period17 Construction of Super 16 Construction of Super Rs. 89204215, Escalation
specialty hospital and specialty hospital and other Amount was paid upto actual
other facilities for Dr. B. facilities for Dr. B. C. Roy date of completion whereas
C. Roy Institute of Institute of Medical Sciences indices were freezed as per
Medical Sciences and and Research at IIT-Kharagpur, stipulated date of completion
Research at IIT- West Bengal REASONS: Extension of Time
Kharagpur, West Bengal was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
18 Construction of Academic 18 Construction of Academic Rs. 44755559, Escalation
Block, Boys and Girls Block, Boys and Girls Hostel, Amount was paid upto actual
Hostel, Staff Quarters, Staff Quarters, Resident Hostel date of completion whereas
Resident Hostel Block, Block, UGT, STP, Indoor Sports indices were freezed as per
UGT, STP, Indoor Sports Block, Guest House, ESS and stipulated date of completion
Block, Guest House, ESS other services etc. with 03 REASONS: Extension of Time
and other services etc. years Defect liability period and was granted without levy of
with 03 years Defect Operation and maintenance for Liquidity Damages (Reason
liability period and 05 years after completion of not attributable to contractor
Operation and works for Establishment of New and HSCC)
maintenance for 05 years Medical College at
after completion of works Hanumangarh, Rajasthan
for Establishment of New
Medical College atHanumangarh, Rajasthan
19 Construction of Phase-I 19 Construction of Phase-I works Rs. 929466, Escalation
works comprising comprising research lab with Amount was paid upto actual
research lab with R&D R&D office, hostel block date of completion whereas
office, hostel block including guest house, type III indices were freezed as per
including guest house, residential quarter, security stipulated date of completion
type III residential lodge, Animal farms & Animal REASONS: Extension of Time
quarter, security lodge, House, STP including was granted without levy of
Animal farms & Animal Associated works for NIAB at Liquidity Damages (Reason
House, STP including Hyderabad not attributable to contractor
Associated works for and HSCC)
NIAB at Hyderabad
20 Construction of Academic 20 Construction of Academic Rs. 49593698, Escalation
Hostel Blocks and Hostel Blocks and auditorium at Amount was paid upto actual
auditorium at Rajkumari Rajkumari Amrit Kaur College of date of completion whereas
Amrit Kaur College of Nursing, New Delhi and their indices were freezed as per
Nursing, New Delhi and maintenance during defect stipulated date of completion
their maintenance during liability period REASONS: Extension of Time
defect liability period was granted without levy of
Liquidity Damages (Reasonnot attributable to contractor
and HSCC)
21 Construction of Satellite 21 Construction of Satellite Centre Rs199846181, Escalation
Centre of PGIMER, of PGIMER, Chandigarh at Amount was paid upto actual
Chandigarh at Sangrur Sangrur (Punjab) including date of completion whereas
(Punjab) including Maintenance during Defect indices were freezed as per
Maintenance during Liability Period stipulated date of
Defect Liability Period completionREASONS:
Extension of Time was
granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
22 AIIMS @ Nagpur 22 AIIMS @ Nagpur Residential Rs127638773, Escalation
Residential Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractorand HSCC)
23 AIIMS @ Nagpur (Pakage 23 AIIMS @ Nagpur (Pakage II) Rs 113549605, Escalation
II) Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
24 PMSSY - III - Guwahati 24 PMSSY - III - Shimla Rs. 111383264, Escalation
Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractorand HSCC)
25 PMSSY - III - Dibrugarh 25 PMSSY - III - Moti Lal Nehru Rs. 106892194, Escalation
(ssb Dibrugarh (assam Medical College, Allahbad, U.P. Amount was paid upto actual
medical college)) date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
26 PMSSY - III - Shimla 26 SSB , Safdarjung Hospital Rs62527770, Escalation
Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attriibutable to contractorand HSCC)
27 PMSSY - III - Moti Lal 27 Emergency Block, Safdarjung Rs60740552, Escalation
Nehru Medical College, Hospital Amount was paid upto actual
Allahbad, U.P. date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
28 SSB , Safdarjung Hospital 28 AIIMS @ Kalyani Pakage I OPD Rs140567595, Escalation
AND RESIDENTAL Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of
completionREASONS:
Extension of Time was
granted without levy of
Liquidity Damages (Reason
not attributable to contractorand HSCC)
29 Emergency Block, 29 AIIMS @ Kalyani Pakage II Rs69940095, Escalation
Safdarjung Hospital HOSPITAL AND ACADEMIC Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
30 AIIMS @ Kalyani Pakage I 30 SSB Burla, PMSSY PH-III Rs190695367, Escalation
OPD AND RESIDENTAL Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)31 AIIMS @ Kalyani Pakage II 31 PMSSY - III - Udaipur Rs79311927, Escalation
HOSPITAL AND Amount was paid upto actual
ACADEMIC date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
32 SSB Burla, PMSSY PH-III 32 Medical College at Pali, Rs119318855, Escalation
Rajasthan Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)33 PMSSY - III - Udaipur 33 PMSSY - III - Goverment Medical Rs60937818, Escalation
College - Kota Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
34 Medical College at Pali, 34 ESIC - Siliguri Nil
Rajasthan
35 PMSSY - III - Goverment 35 AIIMS @ Guntur (Pakage I)-OPD Rs65035498, Escalation
Medical College - Kota & Residential Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)36 ESIC - Siliguri 36 AIIMS @ Guntur (Pakage II)- Nil
Hospital & Academic Block
37 AIIMS @ Guntur (Pakage 37 PMSSY - III - Goa Rs102721429, Escalation
I)-OPD & Residential Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of
completionREASONS:
Extension of Time was
granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
38 AIIMS @ Guntur (Pakage 38 PMSSY - III - Goverment Medical Rs18479596, Escalation
II)-Hospital & Academic College- Aurangabad Amount was paid upto actual
Block date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)39 PMSSY - III - Goa 39 PMSSY - III - Goverment Medical Rs163332243, Escalation
College- Latur Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
40 PMSSY - III - Goverment 40 Construction Balance work of Rs. 84268018, Escalation
Medical College- hostel and residential quarters Amount was paid upto actual
Aurangabad FOR INCREASE OF UG seats date of completion whereas
RIMS, Imphal indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
41 PMSSY - III - Goverment 41 PMSSY - III - Goverment Medical Rs. 21136211, Escalation
Medical College- Latur College, Rewa Amount was paid upto actual
date of completion whereas
indices were freezed as perstipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
42 Package - I -Hospital 42 PMSSY - III - NSB Medical NIl
LGBRIMH, Tezpur, Assam College, Jabalpur
43 Package - II - Residential 43 PMSSY - III - Gajra Medical NIl
LGBRIMH, Tezpur, Assam College, Gwalior
44 Const. Add. Facility 44 PMSSY - III - Patiala, Punjab Nil
RIPANS - Aizwal, Mizoram
45 PMSSY - III - Goverment 45 PMSSY - III - Goverment Medical Rs64017134, Escalation
Medical College, Rewa College, Jhansi, U.P. Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)46 PMSSY - III - NSB Medical 46 CNCI, Kolkata Rs54229774, Escalation
College, Jabalpur Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
47 PMSSY - III - Gajra 47 PMSSY - III - MKCG Medical Rs73438228, Escalation
Medical College, Gwalior Colloege, Berahampur Amount was paid upto actual
date of completion whereas
indices were freezed as per
stipulated date of
completionREASONS:
Extension of Time was
granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)48 PMSSY - III - Patiala, 48 PMSSY - III - North Bengal Rs57538284, Escalation
Punjab Medical College - Siliguri, West Amount was paid upto actual
Bengal date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
49 PMSSY - III - Goverment 49 PMSSY - III - MKCG Medical Rs66534415, Escalation
Medical College, Jhansi, Colloege, Berahampur Amount was paid upto actual
U.P. date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
50 CNCI, Kolkata 50 PMSSY - III - North Bengal Rs331526041, Escalation
Medical College - Siliguri, West Amount was paid upto actual
Bengal date of completion whereas
indices were freezed as perstipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages
51 PMSSY - III - MKCG Rs79123506, Escalation
Medical Colloege, Amount was paid upto actual
Berahampur date of completion whereas
indices were freezed as per
stipulated date of completion
REASONS: Extension of Time
was granted without levy of
Liquidity Damages (Reason
not attributable to contractor
and HSCC)
52 PMSSY - III - North Bengal NIL
Medical College - Siliguri,
West BengalHITES (Enclosure-IV)
WORK COMPLETED BY CLASS -I CONTRACTORS
Sl. Description No. of Projects
No
1 The total number of works costing more 12 Nos.
than Rupees 50 crore that have been
completed and handed over by Class-I
Contractors through HITES to the
respective client
Government/Department/Agencies since
2014;
2 The number of contracts where the 12 Nos. (Enclosure-IV-A
works were not completed on time as attached)
per tender documents along with the
details of cost and time overruns in such
cases;
3 The number of Class-I Contractors who 12 Nos. (Enclosure-IV-A
were allowed to complete works with attached)
more than 20% delay beyond the original
time frame, and the extent of cost
escalation permitted in such cases,
along with reasons.
4 The number of Class- I Contractor who Nil
have been disqualified/barred from
bidding on account of delay in
completion of previous project.HITES (Enclosure-IV-A)
Constructi
on of 100
Justified delay not
Bedded M/s Asian Applicable
10- 10- 23- attributed to the
General DGHS 17.3 Construct as per
1 49.93 67.32 02- 02- 03- 311% contractor. work
Hospital at MoHFW 9 ion tender
2019 2020 2023 completed within
RHTC Company conditions
the budgeted cost
Najafgarh,
Delhi
Constructi
Levy of
on of 200
Compensation
Bedded Applicable
02- 01- 31- amount of Rs. 1.96
Mother and M/s KMV as per
2 NHM 77.35 75.14 Nil 09- 03- 01- 129% Cr. imposed to
Child Projects tender
2016 2018 2020 contractor. Work
Hospital at conditions
completed within
Chitrakoot
the budgeted cost.
(U.P)
Justified delay not
25- 24- 30- attributed to the
AIIMS 582.8 25.4 M/s NCC Not
3 MoHFW 557.48 08- 08- 04- 84% contractor. work
Bathinda 9 1 Ltd applicable
2018 2020 2022 completed within
the budgeted costConstructi
on of
Upgradatio
M/s
n of
Sivanssh Justified delay not
Ganesh Applicable
Infrastru 02- 01- 31- attributed to the
ShankarVid as per
4 MoHFW 101.37 95.11 Nil cture 12- 04- 01- 138% contractor. work
yarthi tender
Develop 2018 2020 2022 completed within
Memorial conditions
ment the budgeted cost
Medical
Pvt. Ltd.
College,
Kanpur
(U.P)
Justified delay not
Surgical 10CA is attributed to the
M/s
Block- 03- 02- 31- applicable contractor. work
Govt. of 129.6 15.1 Jatan
5 GMC 114.43 02- 08- 01- 100% as per completed within
Kerala 1 8 construc
Kottayam , 2020 2022 2025 tender the budgeted cost
tions
Kerala conditions & final bill under
process
Justified delay not
23- 22- 20- attributed to the
GMC Konni Govt. of M/s NCC Not
6 167.33 129 Nil 12- 06- 12- 434% contractor. work
Phase - I Kerala Ltd applicable
2013 2015 2021 completed within
the budgeted cost10CA &
Justified delay not
GMC 10CC are
M/s KMV 15- 14- 13- attributed to the
Thanjavur applicable
7 MoHFW 79.8 84.31 4.51 Projects 06- 12- 12- 67% contractor. work
PMSSY_III , as per
Ltd 2016 2017 2018 completed within
Tamil Nadu tender
the budgeted cost
conditions
10CA &
Justified delay not
GMC 10CC are
M/s KMV 22- 21- 31- attributed to the
Tirunelveli applicable
8 MoHFW 79.64 85.98 6.34 Projects 06- 12- 12- 69% contractor. work
PMSSY_III as per
Ltd 2016 2017 2018 completed within
Tamil Nadu tender
the budgeted cost
conditions
10CA &
Justified delay not
RIMS 10CC are
M/s KMV 16- 15- 16- attributed to the
Adilabad, applicable
9 MoHFW 77.58 76.92 Nil Projects 07- 01- 03- 277% contractor. work
PMSSY_III as per
Ltd 2016 2018 2022 completed within
Telangana tender
the budgeted cost
conditions
10CA &
Justified delay not
KMC 10CC are
M/s KMV 16- 15- 08- attributed to the
Warangal, applicable
10 MoHFW 78.65 78.82 0.17 Projects 07- 01- 06- 226% contractor. work
PMSSY_III as per
Ltd 2016 2018 2021 completed within
Telangana tender
the budgeted cost
conditionsM/s
Justified delay not
Cherian 10CA &
attributed to the
SSB, GMC Varkey 10CC are
12- 11- 31- contractor. work
Kozhikode, Construc applicable
11 MoHFW 71.14 80.24 9.1 07- 04- 12- 156% completed within
PMSSY_III, tion as per
2017 2019 2021 the budgeted cost
Kerala Compan tender
& final bill under
y Pvt. conditions
process
Ltd.
M/s
Justified delay not
Upgradatio Cherian 10CA &
attributed to the
n of T.D Varkey 10CC are
12- 11- 31- contractor. work
MC, Construc applicable
12 MoHFW 74.15 81.98 7.83 07- 04- 01- 161% completed within
Alappuzha, tion as per
2017 2019 2022 the budgeted cost
PMSSY_III, Compan tender
& final bill under
Kerala y Pvt. conditions
process
Ltd.