GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 2526
ANSWERED ON 13.03.2026
DELAY IN FINALISATION OF FOURTH RAILWAY LINE BETWEEN SANTRAGACHI AND
KHARAGPUR
2526 SHRI SAMIK BHATTACHARYA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the proposal for construction of a fourth railway line between Santragachi and Kharagpur
on the Howrah–Kharagpur section has been under consideration for several years but remains at the
survey/DPR stage;
(b) present status of the DPR, including the reasons for its non-finalisation and approval so far;
(c) whether land acquisition, forest clearance or coordination with State Government of West Bengal
has affected progress of the project; and
(d) the timeframe proposed for completion of DPR and commencement of construction, in view of the
strategic and economic importance of this route?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): The work of Santragachi - Kharagpur (111 Km) 4th line has been sanctioned.
West Bengal
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget allotment of projects is made
commensurate to the progress achieved in any project. Budget allocation for infrastructure projects and
safety works, falling fully/partly in the State of West Bengal is as under:-
Period Outlay
2009-14 ₹ 4,380 Cr./year
2025-26 ₹ 13,955 Cr. (More than 3 times)
…2/-
§-2-
Project Sanctioned:
As on 01.04.2025, 42 projects (12 New Lines, 04 Gauge Conversions and 26 Doubling), of total length
of 4402 Km, costing ₹67,991 crore falling fully/partly in the State of West Bengal are sanctioned, out
of which, 1702 km length has been commissioned and an expenditure of ₹23,410 crore has been
incurred upto March, 2025. The summary is as under:
Category No. of Total Length Length Commissioned Total Exp. upto March,
projects (in Km) till March, 2025 2025
(in Km) (₹ in Cr.)
New Lines 12 1,032 337 11,368
Gauge 4 1,201 854 3,673
Conversion
Doubling/M 26 2,169 511 8,370
ulti-tracking
Total 42 4,402 1,702 23,410
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the State of West Bengal are as
under:
Cost
S. No. Name of Project
(₹ in Cr.)
1 Rampurhat-Mandarhill new line and Rampurhat-Murarai 3rd line 1,500
(159 Km)
2 Azimganj-Murshidabad new line (7 Km) 164
3 Bardhaman-Katwa Gauge Conversion (52 Km) 696
4 Ahmedpur-Katwa Gauge Conversion (52 Km) 440
5 Panskura Kharagpur Doubling (45 Km) 408
6 Lalgola – Jiaganj Doubling (23 Km) 124
7 Krishnanagar-Bethuadahari Doubling (28 Km) 152
8 Nabadwipdham-Patuli Doubling (22 Km) 170
9 Bethuadhahari-Plassey Doubling (23 km) 132
10 Ambikakalna-Nabadwipdham Doubling (23 km) 145
11 Nalhati-Sagardighi Doubling (26 km) 193
12 Tamluk Jn.- Basulya Sutahata Doubling (24 km) 245
13 Plassey- Jiaganj Doubling (54 km) 234
….3/-
§-3-
Cost
S. No. Name of Project
(₹ in Cr.)
14 Azimganj-Manigram Doubling (21 km) 150
15 New Coochbehar-Gumanihat Doubling (29 km) 330
16 New Coochbehar-Samuktala Road Doubling (29 km) 445
17 Sainthia-Tarapith 3rd line (22 Km) 186
18 Ambari Falakata-New Maynaguri Doubling (37 km) 843
19 Bandel-Boinchi - 3rd line (31 km) 546
20 Boinchi-Shaktigarh 3rd line (26 km) 424
21 Bazar Sau-Azimganj Jn. Doubling (42 km) 343
22 Sagardighi- Malda Town Doubling (25 Km) 248
23 Kharagpur-Narayangarh 3rd line (24 km) 270
24 Monigram-Nimtita Doubling (24 Km) 713
25 Purulia-Kotshila Doubling (36 Km) 393
Ongoing Projects:
Some of the projects falling fully/partly in the State of West Bengal which have been taken up are as
under:
S. No. Name of Project Cost
(₹ in Cr.)
1 Chandil-Purulia-Anara-Damodar 3rd Line(121 Km) 1,932
2 Tarakeshwar-Bishnupur New Line (83 Km) 1,542
3 Sivok-Rangpo New Line (44 Km) 11,973
4 Balurghat-Hilli New Line (30 Km) 1,209
5 Kaliyaganj-Buniadpur New Line (33 Km) 1,147
6 Katihar-Kumedpur and Katihar-Mukuria Doubling (65 Km) 943
7 Kharagpur-Adityapur 3rd line (132 Km) 3,250
8 Narayangarh-Bhadrak 3rd line (153 Km) 2,136
9 Kalipahari-Bakhtarnagar 5th Line (18Km) 350
10 Dankuni-Baltikuri 3rd & 4th line (18 Km) 429
11 Murarai-Barharwa 3rd Line (49 Km) 935
12 Ranaghat-Krishnanagar City 3rd Line (26 Km) 446
13 Aluabari Road-New Jalpaiguri 3rd & 4th Line (57 Km) 1,630
….4/-
§-4 -
Land Acquisition:
Execution of important infrastructure projects falling fully/partly in the State of West Bengal are held
up due to delay in land acquisition. Status of land acquisition in West Bengal is as under:
Total Land required 4,662 Ha
Land Acquired 1,273 Ha (27%)
Balance Land to be acquired 3,389 Ha (73%)
Details of some major projects which are delayed due to land acquisition are as under:
SN Name of the project Total land Land Balance Land
required acquired to be acquired
(in Ha) (in Ha) (in Ha)
1. Chandil-Anara- Burnpur - 3rd line 8 0 8
2. Nabadwipghat-Nabadwipdham new line 107 0 107
3. Byepass at Sainthia 22 0 22
4. Naihati – Ranaghat 3rd line 13 0 13
5. Sivok-Rangpo new line 135 128 7
6. Kaliyaganj-Buniadpur new line 168 0 168
7. Canning- Bagankhali new line 18 0 18
8. Adra- Sanka- Rukni doubling 5 0 5
9. Kalipahari-Bakhtarnagar 5th line 15 0 15
10. Rail Flyover at Anara from Rukni to 35 0 35
Anara station
11. Rail Flyover at Gourinathdham end to 34 0 34
Purulia
12. Chandanpur Shaktigarh 4th Line 5 0 5
Further, Tarakeshwar-Bishnupur (83 Km) New Line Project is held up since 2016 due to non-
cooperation by state Govt. of West Bengal. The work was stopped by local villagers in about 900 m
length near “Bhabadighi” pond in Hooghly district. Honourable High Court, Kolkata in March, 2025
directed State Govt of WB to provide all necessary support and deploy adequate police force to enable
the Railways to commence the work within 3 months.
Deshpran -Nandigram (18.5 km) Line was sanctioned in 2009-10 at cost of ₹ 121.44 crores. The entire
Project length is located in East Midnapore District. The project could not progress due to problems in
land acquisition and was kept in abeyance. In April 2023 it was decided to re-start the work. However,
Survey for Land Acquisition from Deshpran to 5.0 Km could not be completed due to law and order
issues. As Deshpran is the connecting station, acquisition of this land is essential for commissioning of
this project.
….5/-
§-5-
Several meetings have been held with officials of Government of West Bengal for land acquisition for
the above projects.
Kolkata Metro:
Metro project in Kolkata started in 1972. The details of the Metro commissioned since then are as
under:
Period Metro Commissioned
1972 to 2014 (42 years) 28 km
2014 to 2025 (11 years) 45 km
The details of Metro Corridors commissioned are as under:
S.No. Metro Corridor Section Commissioned
Kavi Subash – Noapara (28 Km) This Corridor commissioned before year 2014
1 (Blue Line) (This required about 42 years to complete)
Noapara – Dakshineswar (4.14 Km) This Corridor commissioned in 2020-21
2
(Extension of Blue Line)
Noapara – Jaihind Airport - Barasat (18 Noapara – Jaihind Airport section (6.77 Km)
3
Km) (Yellow Line) Commissioned in 2025-26
Joka – Majerhat - Esplanade (14 KM) Joka – Majerhat section (7.74 Km)
4
(Purple Line) Commissioned in stages from 2022 to 2024
New Garia - Belaghata - Dumdum Airport New Garia – Belaghata (9.8 Km)
5 (32 Km) Commissioned in stages between 2023-26
(Orange Line)
Howrah Maidan – Salt Lake Sec. V (16.55 This Corridor commissioned in stages from
6
Km) (Green Line) 2019 to 2025
Further, work pertaining to 4 Metro corridors at total length of about 52 km is under progress, out of
which 20 km of work is held up due to land acquisition and utility shifting issues pertaining to State
Government. In the rest of the Metro stretch, though the work is in progress yet facing difficulties due
to one or other reasons at the end of State Government. Details are as below:
(i) Noapara – Jaihind Airport - Barasat (18 km): Noapara - Jai Hind Airport (6.77 km) has been
commissioned and work from Jai Hind Airport to Michael Nagar is in progress. However, work
from New Barrackpore to Barasat (7.5 km) is held up due to land acquisition and encroachment
issues by State authorities.
….6/-
§-6-
SN Location Issues
1. New Barrackpore to Land acquisition (23,000 sq. m) and removal of heavy
Barasat encroachments (1277 hutments, 764 shops) are involved in
this section.
The matter is not yet resolved by Government of West
Bengal (GoWB).
(ii) Joka –Majerhat - Esplanade (14 km):- Joka - Majerhat (7.74 km) has been commissioned and
balance work from Majerhat to Esplanade (6.26 km) has been taken up. However, progress of the
work is affected due to the following issues:
SN Location Issues
1. Khidderpur Metro For utility shifting and road traffic diversion, 837 sqm
Station permanent and 1,702 sqm temporary land of State Government
(Kolkata Armed Police) is required. The proposal of this land
was sent to State Government on 24.08.2020.
Several meetings were held with officials of Government of
West Bengal (GoWB) for transfer of above land.
After lot of persuasion, State Government finally accorded
approval in July 2025 only after almost 5 years.
2. Dr. B.C. Roy For construction of Esplanade Metro Station, temporary
Market shifting of unauthorised 528 Shops at B.C. Roy Market on
Defence land is required.
The proposal for NOC of temporary/permanent shifting of
these shops was submitted to State Government in February
2022. Shops for temporary shifting of these unauthorized shops
have also been constructed by Railway.
The State Government has been requested to facilitate shifting.
Regular follow up with State PWD is also being done.
Issue is pending for more than 3.5 years.
….7/-
§-7-
(iii) New Garia –Belaghata - Dum Dum Airport (32 km): New Garia - Belaghata (9.8 km) has been
commissioned and balance work from Belaghata to Dum Dum Airport (22.2 km) has been taken
up. However, progress of the work is affected due to the following issues:
SN Location Issues
1. Chingrighata Temporary traffic diversion at Chingrighata crossing for
Crossing (Between launching of viaduct segments is required for 3 nights each
Beleghata – Gour on either side of the road (8 hours on every night).
Kishore Ghosh The proposal was submitted to Government of West Bengal
stations) (GoWB) in December 2024.
The diversion road as desired by Kolkata traffic police has
already been constructed in February 2025.
Since then, several meetings have been held with various
State Government and Kolkata police officials for NOC.
The NOC is still awaited even after about 12 months.
(iv) Baranagar - Barrackpore - Dakshineshwar (14.5 km): Baranagar - Dakshineshwar (2 km) has
been commissioned and balance work from Baranagar to Barrackpore (12.5 km) is held up due to
pending utility shifting in the alignment by state government authorities. The details are as below:
SN Location Issues
1. Baranagar The original alignment along the B.T road was agreed in 2011
to Barrackpore as per MoU among Metro Railway, RVNL and Kolkata
Municipal Corporation.
As per MoU, existing pipeline was to be replaced by new 64-
inch diameter pipeline by the State Government.
Shifting of this pipeline was completed in 2012.
However, NOC is still awaited from Government of West
Bengal.
Government of India is geared up to execute projects, however success depends upon the support of
Government of West Bengal.
….8/-
§-8-
Sanction of any railway project depends upon many parameters/factors which include the following:
Anticipated traffic projections and Remunerativeness of the proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§