GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO - 2979
ANSWERED ON 18/03/2026
DELAYS IN PROJECTS DUE TO LAND ACQUISITION
2979. DR. FAUZIA KHAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) whether the Ministry is aware that a substantial number of national highway and road
projects, reportedly over 489, are facing significant delays due to persistent land acquisition,
statutory clearance;
(b) if so, the steps being taken to streamline land acquisition processes, strengthen coordination
between Central and State agencies and ensure timely resolution of compensation, rehabilitation
and statutory bottlenecks that impede progress on these critical infrastructure projects;
(c) whether the Ministry has reviewed project appraisal and monitoring mechanisms to address
implementation delays, facilitate early stakeholder engagement and reduce risks of cost
escalation; and
(d) if so, the details thereof and if not, the reasons therefor?
ANSWER
THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) Currently, as per the available data, 85 under construction National Highways (NHs) projects
are delayed by more than three years, attributable to various issues such as, bottlenecks relating
to land acquisition, statutory clearances / permissions, utility shifting, encroachment removal,
law & order issues, financial crunch affecting implementation capacity of concessionaire /
contractor, poor performance of contractor / concessionaire, and Force Majeure events such as
Covid-19 pandemic, Change of Law, etc.
(b) to (d) The Government has undertaken various initiatives to prevent recurrence of delays and
cost escalations. These include streamlining and expediting land acquisition and compensation
using “BhoomiRashi” portal integrated with Public Finance Management System (PFMS) andGIS-based Land Acquisition Plan, revamping “Parivesh” Portal, to facilitate faster forest and
environmental clearances, enabling online approval of General Arrangement of Drawings (GAD)
of Road Over Bridge/ Road Under Bridge (ROB/ RUB), and leveraging the mechanism of
review and resolution of bottlenecks / hindrances in ongoing projects, in active collaboration
with the State Governments and other stakeholders. Government has also launched a web portal
for Railway related clearances with defined timelines for various approvals.
The Government has put in place a strong framework using multiple mechanisms for
monitoring project progress and contractor inefficiencies. Regular review meetings are
conducted at various levels with stakeholders to assess project progress, and critical projects,
such as those delayed by more than three years or pending for award/ appointment. Cost
escalation is not incurred in all delayed projects. If delay is not attributable to the Contractor,
escalation is paid as per contract conditions, which may or may not result in additional cost,
depending upon final value of price escalation determined on actual completion of project. If
delay is attributable to the Contractor, damages are imposed and there is no additional cost due to
delay.
Many State Governments conduct coordination meetings led by the Chief Secretary to
resolve issues affecting project execution. Projects where issues remain unresolved are escalated
for further review through the Project Monitoring Group and also through “PRAGATI”. As a
result of the above, no. of projects delayed by more than 3 years has come down from 152 in
April'2024 to 85 in February'2026.
The optimal alignment for a new project is approved by an empowered committee keeping
in view the viability of the project taking into consideration various factors such as the cost of
the land, the time period for acquisition etc.
*****