UNSTARRED QUESTION NO - 2191
ANSWERED ON - 11/03/2026
DELHI‑AMRITSAR‑KATRA EXPRESSWAY PROJECT
2191. SHRI SAT PAUL SHARMA:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:-
(a) the current status of the Delhi‑Katra‑Amritsar Expressway project, including the progress made so
far and the expected completion date;
(b) whether Government has conducted any study on the potential economic and social impact of the
expressway on the regions it will pass through; and
(c) if so, the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) The details are enclosed as Annexure.
(b) and (c) The proposed Delhi-Katra-Amritsar Expressway is envisaged to provide
efficient connectivity between major origin-destination points. The project is expected to significantly
reduce travel distance and time, resulting in savings in vehicle operating costs and improved travel
experience. It will also help de-congest the existing National Highways and reduce traffic bottlenecks.
The Expressway is expected to reduce the distance between Delhi and Amritsar/Katra by about
40 km and enable travel from Delhi to Amritsar in about 5 hours and Delhi to Katra in about 7 hours.
The Expressway Connects major cities including Rohtak and Jind in Haryana; Sangrur,
Malerkotla, Patiala, Ludhiana, Jalandhar, Kapurthala and Gurdaspur in Punjab; and Kathua and Jammu
in the Union Territory of Jammu & Kashmir. Apart from providing improved connectivity to the
religious destinations of Amritsar and Katra, the project will also enhance industrial connectivity in
Punjab and Haryana and promote tourism in Jammu & Kashmir.
Further, development of the Expressway is expected to improve infrastructure in the region and
contribute to overall economic development.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF RAJYA SABHA UNSTARRED
QUESTION NO. 2191 ANSWERED ON 11/03/2026 ASKED BY SHRI SAT PAUL SHARMA
REGARDING DELHI-AMRITSAR-KATRA EXPRESSWAY PROJECT.
Length Date of Physical Scheduled
State Section Expected Completion date
(Km) Start Progress (%) completion date
I 34 27.12.2021 100% Dec’ 2023 Completed
II 26.8 14.01.2022 100% Jan’ 2024 Completed
Haryana
III 30.6 24.12.2021 100% Dec’ 2023 Completed
IV 28.85 14.12.2021 100% Dec’ 2023 Completed
Haryana &
V 37.67 23.05.2022 99.10% May’ 2024 March’ 2026
Punjab
VI 30.91 23.05.2022 95.33% May’ 2024 Completed
VII 36.94 11.07.2022 95.80% Jul’ 2024 March’ 2026
Contract foreclosed & Bids
VIII 35.09 15.03.2023 31.08% Mar’ 2025
for balance works invited
IX 43.04 18.07.2022 71.81% Jul’ 2024 June’ 2026
Punjab Contract foreclosed & Bids
X 39.5 11.07.2022 62.99% Jul’ 2024
for balance works invited
Contract foreclosed & Bids
XI 43.02 15.11.2022 43.45% Nov’ 2024
for balance works invited
XII 35.28 20.02.2025 26.12% Feb’ 2027 Feb’ 2027
XIII 25.8 Stretch overlapping with Pathankot – Amritsar section of NH-54
Punjab & J&K XIV 44.6 26.09.2022 82.81% Sept’ 2024 June’ 2026
XV 35.15 26.09.2022 88.87% Sept’ 2024 Oct’ 2026
XVI 20.39 27.09.2022 92.93% Sept’ 2024 June’ 2026
J&K
XVII 28.92 15.06.2023 59.06% June’ 2025 Sept’ 2026
XVIII 15.3 21.11.2023 59.11% Nov’ 2025 Aug’ 2026
I 16.9 17.04.2023 28.64% April’ 2026 March’ 2028
Punjab (Spur to
II 30.05 Contract terminated & fresh Bids invited
Amritsar)
III 28.07 27.10.2022 29.70% Oct’ 2024 Feb’ 2027
Total 667
*****