GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
STARRED QUESTION NO. 236
ANSWERED ON 13.03.2026
DEMANDS FOR NEW RAILWAYS PROJECTS IN TAMIL NADU
*236 SHRI I.S. INBADURAI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Government has reviewed the long-pending demands in Tamil Nadu relating to new lines,
doubling, electrification and stoppages, if so, the details thereof;
(b) whether a State-wise prioritisation mechanism exists for sanctioning railway projects and the
criteria adopted, including Tamil Nadu’s position;
(c) whether proposals including new line connectivity between Kanyakumari, Rameswaram and
Tisayanvilai, additional express services and station upgrades have been pending for over five
years, if so, the details thereof; and
(d) whether adequate funds were allocated during the last three years and whether delays are due to
land acquisition, funding or administrative reasons, if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF STARRED QUESTION
NO.236 BY SHRI I.S. INBADURAI ANSWERED IN RAJYA SABHA ON 13.03.2026 REGARDING
DEMANDS FOR NEW RAILWAYS PROJECTS IN TAMIL NADU
(a) to (d): Budget allocation in the recent years has increased significantly. Budget allocation for
infrastructure projects and safety works, falling fully/partly in the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2025-26 ₹ 6,626 crore (more than 7.5 times)
Project sanctioned:-
As on 01.04.2025, 15 projects (09 new line, 03 gauge conversion and 03 doubling) of 1,700 km length,
costing ₹22,808 Crore, falling fully/partly in the State of Tamil Nadu, are sanctioned. The summary is
as under:-
Category No. of Total Length Length Expenditure
sanctioned (in km) Commissioned upto Mar’ 25
projects upto Mar’25 (₹ in Cr.)
(in km)
New Line 9 812 24 1,337
Gauge Conversion 3 748 604 3,471
Doubling /Multitracking 3 140 37 2,783
Total 15 1,700 665 7,591
Zonal Railway wise details of Railway projects are made available in public domain on Indian
Railway’s website.
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in Tamil Nadu are as under :
S.N Cost
Project
. (₹in Crores)
1 Dindigul-Palani-Pollachi gauge conversion (121 km) 610
2 Pollachi-Palghat gauge conversion (56 km) 350
3 Pollachi-Podhanur gauge conversion (40 km) 400
4 Quilon-Tirunelveli-Tiruchendur gauge conversion (357 km) 1,122
5 Mayiladuturai-Thiruvarur-Karaikkudi gauge conversion (187 km) 1,338
6 Madurai-Bodiyakannur gauge conversion (90 km) 593
7 Chengalpattu-Villupuram doubling (102 km) 670
8 Tiruvallur-Arakkonam 4th line (27 km) 83
...2/-
§-2-
9 Chennai Central-Basin Bridge doubling (2 km) 31
10 Thanjavur-Ponmalai doubling (48 km) 370
11 Villupuram-Dindigul doubling (273 km) 2,000
12 Chennai Beach-Korukkupet 3rd line (5 km) 168
13 Chennai Beach-Attipattu 4th line (22 km) 293
14 Omalur-Metturdam Patch doubling (29 km) 327
15 Chengalpattu-Villupuram and Tambaram-Chengalpattu-3rd line (133 km) 1,122
16 Salem-Magnesite Junction-Omalur doubling (11 km) 115
17 Madurai- Maniyachi-Tuticorin doubling (160 km) 1,891
18 Maniyachi-Nagercoil doubling (102 km) 1,752
19 Chennai Beach-Chennai Egmore doubling (4 km) 272
20 Karaikal-Peralam new line (23 km) 373
21 Northern End Port connectivity to Karaikal Port (1 km) 18
Ongoing Projects:-
Some of the projects falling fully/partly in the State of Tamil Nadu which have been taken up are as
under :
Cost
S.N Project
(₹ in Crores)
1 Tindivanam-Nagari new line (184 km) 3,631
2 Morappur-Dharmapuri new line (36 km) 359
3 Nagapattinam-Tiruturaipundi new line (43 km) 742
4 Trivandrum-Kanyakumari doubling (87 km) 3,785
5 Arakkonam yard 3rd & 4th line (6 km) 98
6 Perambur - Ambattur 5th & 6th lines (6 Km) 178
7 Irugur-Podanur doubling (11 Km) 277
8 Tambaram-Chengalpattu 4th Line (30 km) 757
9 Attipattu-Gummidipundi 3rd & 4th line (23 km) 375
10 Tirupati-Pakala-Katpadi doubling (105 km) 1332
11 Tindivanam-Gingee-Tiruvannamalai New Line (71 Km) 1400
12 Atipattu – Puttur New Line (88 Km) 1700
13 Chennai – Cuddulore via Mahabalipuram New Line (179 2670
Km)
Execution of important infrastructure projects falling fully/partly in the State of Tamil Nadu are held up
due to delay in land acquisition. Status of land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4,326 ha
Land Acquired 1,052 ha (24%)
Balance Land to be acquired 3,274 ha (76%)
...3/-
§-3-
Support of the Government of Tamil Nadu is needed to expedite the land acquisition.
Details of some major projects which are delayed due to land acquisition are as under:-
SN Name of the project Total land Land Balance
required acquired Land to be
(in ha) (in ha) acquired
(in ha)
1. Tindivanam - Tiruvannamalai new line 2 7 6 33 243
(71 km)
2. Attiputtu-Puttur new line (88 km) 189 0 189
3. Morappur-Dharmapuri new line (36 km) 92 45 47
4. Mannargudi-Pattukkottai new line (41 km) 196 0 196
5. Thanjavur-Pattukottai new line (52 km) 152 0 152
Further, Rameshwaram – Dhanushkodi new line (18 km) was sanctioned at a cost of ₹734 Cr. The
Foundation Stone of the project was laid on 01.03.2019. However, the project could not be started
because the land acquisition has not been undertaken by the State Govt. of Tamil Nadu.
Government of India is geared up to execute projects, however success depends upon the support of
Government of Tamil Nadu.
In last three years i.e. 2022-23, 2023-24, 2024-25 and current financial year 2025-26, 29 surveys (06
new line and 23 doubling) covering a total length of 2,478 km has been sanctioned falling fully/partly
in the State of Tamil Nadu.
Rameswaram is already connected to Kanniyakumari with existing railway network via Virudhanagar,
Tirunelveli and Nagercoil. The Kulasekharapatnam Light Railway (private narrow gauge railway), in
Tisayanvilai-Kulasekharapatnam-Tiruchendur (43 km) section, had been operational till 1940 on
private land. Thereafter, it was closed.
Railway Electrification:
Electrification of railway network on Indian Railways has been taken up in mission mode. So far, about
99.4% of Broad Gauge (BG) network has been electrified. The electrification in remaining network has
been taken up. Electrification carried out during 2014-25 and before 2014 is as under:-
Period Route Kilometer
Before 2014 (about 60 years) 21,801
2014-25 46,900
...4/-
§-4-
In Tamil Nadu, 97% of BG network has been electrified and electrification in remaining network has
been taken up.
Trains Stoppage:
Proposals/ requests/ suggestions/ representations, both formal and informal inter alia for
introduction/provision of stoppage of trains are received from Members of Parliament, elected
representatives, organizations/rail users etc. at various levels including Railway Board, Zonal Railways,
Divisional Office etc. As receipt of such proposals/ requests/suggestions is a continuous and dynamic
process, centralized compendium of such requests is not maintained. However, these are examined and
action as found feasible and justified is taken from time to time, which is an on-going process.
Further, as the Railway network straddles across State/district boundaries, trains are operated, as per
network requirement, across such boundaries.
However, to facilitate the passengers of Tamil Nadu, during the period 01.04.2021 to 28.02.2026, 295
stoppages have been provided and following 52 new train services (including 16 Vande Bharat train
services and 12 Amrit Bharat) have been introduced on orignating/terminating basis:
Sl. Train No. and Name
1 20609/20610 Tiruchchirappalli - New Jalpaiguri Amrit Bharat Express
2 16121/16122 Tambaram - Trivandrum central Amrit Bharat Express
3 16329/16330 Nagercoil - Mangaluru Junction Amrit Bharat Express
4 20603/20604 Nagercoil - New jalpaiguri Amrit Bharat Express
5 16107/16108 Tambaram - Santragachi Amrit Bharat Express
6 16601/16602 Erode - Jogbani Amrit Bharat Express
7 20671/20672 Madurai - Bangalore Cantt. Vande Bharat Express
8 20627/20628 Chennai Egmore - Nagercoil Vande Bharat Express
9 20663/20664 Mysuru - MGR Chennai Central Vande Bharat Express
10 20641/20642 Bengaluru Cantt. - Coimbatore Vande Bharat Express
11 20665/20666 Chennai Egmore - Triunelenveli Vande Bharat Express
...5/-
§-5-
12 20677/20678 MGR Chennai Central - Vijayawada Vande Bharat Express
13 20643/20644 MGR Chennai Central Chennai - Coimbatore Vande Bharat Express
14 20607/20608 MGR Chennai Central - Mysuru Vande Bharat Express
15 66621/66622 Salem - Erode MEMU
16 20625/20626 MGR Chennai Central - Bhagat Ki Kothi Express
17 16103/16104 Tambaram - Rameswaram Express
18 66563/66564 Yesvantpur- Hosur MEMU
19 16765/16766 Mettupalaiyam - Tuticorin Express
20 16367/16368 Kanniyakumari - Banaras Kashi Tamil Sangamam Express
21 56113/56114 (Old no. 06421/06422) Coimbatore - Pollachi Passenger
22 16361/16362 Ernakulam - Velankanni Express
23 20683/20684 Tambaram - Sengottai Express
24 76627/76628 Agastiampalli - Tiruturaipundi DEMU
25 76629/76630 Agastiampalli - Tiruturaipundi DEMU
26 56701/56702 (Old no. 06701/06702) Madurai - Teni Passenger
Besides, provision of stoppages of train services and introduction of new train services which depends
on the traffic justification, operational feasibility, competing demands, etc., are on-going processes on
Indian Railways.
Amrit Bharat Stations:
Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with
a long-term approach.
The scheme involves preparation of master plans and their implementation in phases to improve
the stations. The master planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
…6/-
§-6-
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water booths
Provision of wider foot over bridge/air concourse commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business meetings, landscaping, etc.
keeping in view the necessity at each station.
The scheme also envisages sustainable and environment friendly solutions, provision of ballastless
tracks etc. as per necessity, phasing and feasibility and creation of city centre at the station in the
long term.
So far, 1,337 stations have been identified for development under the Amrit Bharat Station
Scheme. Out of these, 77 stations are located in Tamil Nadu.
The name of stations identified under Amrit Bharat Station Scheme in Tamil Nadu are as
following:
No. of
State Name of Stations
Stations
Tamil Nadu 77 Ambasamudram, Ambattur, Arakkonam Jn, Ariyalur, Avadi,
Bommidi, Chengalpattu Jn, Chennai Beach, Chennai Egmore,
Chennai Park, Chidambaram, Chinna Salem, Chrompet,
Coimbatore Jn, Coimbatore North, Coonoor, Dharmapuri,
Dindigul, Erode Jn., Guduvancheri, Guindy, Gummidipundi,
Hosur, Jolarpettai Jn, Kanniyakumari Terminus, Karaikkudi
Jn, Karur Jn, Katpadi Jn, Kovilpatti, Kulitturai,
Kumbakonam, Lalgudi, Madurai Jn, Mambalam, Manaparai,
Mannargudi, Mayiladuturai Jn, Mettupalayam, Morappur,
Nagercoil Jn, Namakkal, Palani, Paramakkudi, Perambur,
Podanur Jn., Pollachi Jn, Polur, Pudukkottai, Puratchi
Thalaivar Dr. M.G. Ramachandran Central, Rajapalayam,
Ramanathapuram, Rameswaram, Salem, Samalpatti,
Sholavandan, Srirangam, Srivilliputtur, St.Thomas Mount,
§ ...7/--7-
No. of
State Name of Stations
Stations
Tambaram, Tenkasi, Thanjavur Jn, Thiruvarur Jn.,
Tiruchendur, Tirunelveli Jn, Tirupadripulyur, Tirupattur,
Tiruppur, Tirusulam, Tiruttani, Tiruvallur, Tiruvannamalai,
Tuticorin, Udagamandalam, Vellore Cantt., Villupuram Jn.,
Virudhunagar, Vriddhachalam Jn.
Completed stations:
Development works at railway stations under Amrit Bharat Station Scheme in Tamil Nadu have
been taken up at a good pace. Details of stations completed in Tamil Nadu are as under:
No. of
State Name of stations
stations
Bommidi, Chennai Park, Chidambaram, Chinna Salem, Karaikkudi
Jn, Kulitturai, Mambalam, Manaparai, Mannargudi, Morappur,
Tamil
20 Pollachi Jn, Polur, Samalpatti, Sholavandan, Srirangam, Srivilliputtur,
Nadu
St. Thomas Mount, Thiruvarur Jn., Tiruvannamalai, Vriddhachalam
Jn.
The activities for development at other stations have also been taken up at good pace and progress
of some of the above stations is as given below:
Palani station: The works of improvement of station building, platform shelter, waiting hall, toilet,
circulating area, parking, entry/exit arch, lift at existing Foot Over Bridge, coach indication board
and train indication board have been completed. The works of Divyangjan facilities and 6 m Foot
Over Bridge have been taken up.
Virudhunagar Junction station: The works of circulating area, parking, entry/exit arch,
Divyangjan facilities, coach indication board and train indication board have been completed. The
works of improvement of station building and 6 m Foot Over Bridge have been taken up.
Karur Junction station: The works of improvement of station building, main entrance arch, AC
waiting hall, toilet at platform no. 1, 2/3 & 4/5, circulating area and parking have been completed.
The works of lift, escalator and 12 m Foot Over Bridge have been taken up.
Thanjavur Junction station: The works of portico, improvement of concourse, platform shelter,
...8/-
§-8-
improvement of booking office, circulating area, exit arch and signages have been completed. The
works of parking, lift, escalator, coach indication board and train indication board have been taken
up.
Villupuram Junction station: The works of new arrival building, platform shelter, improvement
of platform surface, booking counter, parcel office, improvement of parking and signages have
been completed. The works of improvement of concourse, circulating area, parking, entrance arch,
coach indication board, train indication board, escalator and 6 m Foot Over Bridge have been taken
up.
Further, development / redevelopment / upgradation / modernisation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are undertaken as per requirement, subject to
inter-se priority and availability of funds. Development / redevelopment / upgradation / modernisation
of a station is carried out based on category of station/condition/traffic handled etc.
Development / Upgradation of stations is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc.
The progress also gets affected due to brownfield related challenges such as shifting of utilities
(involving water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines, etc. and these factors affect
the completion time.
Development / Upgradation / Modernization of stations including Amrit Bharat Station Scheme is
generally funded under Plan Head-53 ‘Customer Amenities’. The details of allocation and expenditure
under Plan Head-53 are maintained Zonal Railway-wise and not work-wise or station-wise or state-
wise. Tamil Nadu is covered under the jurisdiction of two railway zones, namely, Southern Railway and
South Western Railway. For these zones, an allocation of ₹ 4,632 crore has been made for the last two
years and the current year (up to January, 2026), out of which an expenditure of ₹ 4,439 crore has been
incurred so far.
Sanction of any railway project depends upon many parameters/factors which include the following:
Anticipated traffic projections and remunerativeness of the proposed route
First and last mile connectivity provided by the project
...9/-
§-9-
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§