GOVERNMENT OF INDIA
MINISTRY OF CIVIL AVIATION
RAJYA SABHA
UNSTARRED QUESTION NO. : 2575
TO BE ANSWERED ON THE 16th March 2026
DEVELOPMENT OF AIRPORTS IN THE COUNTRY AND FUTURE
PLANS
2575. DR. SANDEEP KUMAR PATHAK
Will the Minister of CIVIL AVIATION be pleased to state:-
(a) the number of new airports constructed and existing airports expanded in the country
during the last five years, the details thereof State-wise;
(b) the number of airports currently under construction and their expected timeline for
completion;
(c) whether any long-term master plan has been prepared through the airports Authority of
India and other agencies to make India a global aviation hub by 2047, if so, the details
thereof; and
(d) the budget allocated and spent so far for the above projects, the details thereof?
ANSWER
Minister of State in the Ministry of CIVIL AVIATION (Shri Murlidhar
Mohol)
(a) & (b): As per the Greenfield Airports (GFA) Policy, 2008, Government of India (GoI) has
accorded 'In-Principle' approval for setting up of 24 Greenfield Airports across the country.
Out of these, 13 Greenfield airports have been operationalised.
Further, Upgradation/ Modernisation of airports is a continuous process. Since FY 2019-20,
airport projects have been undertaken by Airports Authority of India (AAI) and airport
operators/developers under Public Private Partnership (PPP) at several airports across the
country including at Delhi, Bengaluru, Hyderabad, Lucknow, Guwahati, Ayodhya,
Kushinagar, Itanagar, Dehradun, Agartala, Patna, Vijayawada, Deoghar, Amrtisar, Chennai,
Tirupati, Mangalore, Kolkata, Port Blair, Surat, Tiruchirapally, Kolhapur, Jabalpur, Gwalior,
Rajkot, Leh, Hubballi, Imphal, Jodhpur, Udaipur, Rajahmundry, Belagavi, Prayagraj,
Tuticorin, Patna etc.
The timeline for completion of the airport projects depend upon several factors such as land
acquisition, financial closure, obtaining mandatory clearances including environmental
clearances etc.(c): AAI has prepared Master Plans for AAI airports up to year 2047.
(d): The responsibility for implementation of the airport projects including funding lies with
the Project Proponent. AAI and other airport operators/developers have incurred Capital
Expenditure of more than Rs. 96000 crore under six year National Infrastructure Pipeline
during FY 2019-20 to FY 2024-25. Out of this, more than Rs. 28000 crore has been incurred
by AAI and the remaining by airport operators/developers under PPP mode.
******