GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1743
TO BE ANSWERED ON 29.07.2026
DEVELOPMENT OF BUXAR, DUMRAON AND RAGHUNATHPUR STATIONS
UNDER THE ABSS
†1743. SHRI SUDHAKAR SINGH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Buxar, Dumraon and Raghunathpur stations under Buxar
district of Bihar have been selected for development under Amrit Bharat
Station Scheme (ABSS) and if so, the details thereof;
(b) the current status of the said stations, the date for commencement and
completions of the said work; and
(c) whether there is delay in completion of work due to officials and
contractors and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Ministry of Railways has identified Buxar, Dumraon and
Raghunathpur Railway Stations for redevelopment under Amrit Bharat
Station Scheme. The progress at these stations is given below:
Dumraon station: The master plan of Dumraon station redevelopment work
envisages following works:
New station building on main entry
New 6 m wide foot over bridge
Improvement of circulating area and parking on both entries
New platform shelter
New platform no. 3
§ Page 1 of 6The works of new main entry station building, new platform, new platform
shelter, new 6 m wide foot over bridge, improvement of circulating area and
parking have been taken up at this station.
Raghunathpur Station: The master plan of Raghunathpur station
redevelopment work envisages following works:
New station building on main entry
New 6 m wide foot over bridge
Improvement of circulating area and parking on main entry
Raising platform no. 3
The work of new station building, 6 m Foot Over Bridge, improvement of
circulating area and parking on main entry side and raising of platform
have been taken up at this station.
Buxar Station, in recent years, the works of ramps in existing foot over
bridge and improvement of amenities for Divyangjan have been completed.
The works of improvement of waiting hall, platform surface, toilet and
ballastless track of line no. 1, 4 & 5 has been sanctioned.
Further, master planning for redevelopment of Buxar Railway Station under
Amrit Bharat Station Scheme has been taken up. Master planning for
development of Railway stations under 'Amrit Bharat Station Scheme' is an
iterative process requiring optimization and the time frame for such
optimization cannot be indicated at this stage.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Page 2 of 6 Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 98 stations including Buxar, Dumraon
and Raghunathpur railway stations are located in Bihar.The names of
stations identified for development under Amrit Bharat Station Scheme in
Bihar are as following:
State No. of Name of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, BapudhamMotihari,
Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah,
Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif,
Page 3 of 6State No. of Name of Stations
Stations
Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra,
Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri
On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma,
Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn,
Jamalpur, Jamui, Janakpur Road, Jaynagar,
Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road,
Katihar, Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai, Madhubani,
Maheshkhunt, Mairwa, Mansi Jn, Mashrakh, Mokama,
Motipur, Munger, Muzaffarpur, Nabinagar Road,
Narkatiaganj, Naugachia, Nawadah, Paharpur,
Patliputra, Patna, Piro, Pirpainti, Rafiganj,
Raghunathpur, Rajendra Nagar, Rajgir, Ram Dayalu
Nagar, Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur
Kamal, Sakri, Salauna, Salmari, Samastipur, Sasaram,
Shahpur Patoree, Shivanarayanpur, Simri Bakhtiyarpur,
Simultala, Sitamarhi, Siwan, Sonpur Jn., Sultanganj,
Supaul, Taregna, Thakurganj, Thawe
Completed Stations:
Development works at railway stations under Amrit Bharat Station
Scheme in Bihar have been taken up at a good pace. Details of stations
completed in Bihar are as under:
State No. of Name of stations
stations
Bihar 8 Banmankhi, DauramMadhepura, Kahalgaon, Pirpainti,
Sabaur, Shivanarayanpur, Simultala, Thawe
Page 4 of 6The activities for development at other stations in Bihar have also
been taken up at good pace and progress of some of the stations is
as given below:
Gaya station: The work of new second entry arrival building has been
completed. The works of new second entry departure building, main
entry new arrival & departure building, new platform no. 8, new
platform shelters, air concourse and improvement of circulating area
have been taken up.
Muzaffarpur station: The work of combined terminal building, 3 m
wide skywalk (north side), booking counter and office buildings have
been completed. The work of main station building (phase-I), elevated
road, arrival terminal building, departure terminal building, multi-level
car parking, 6m wide skywalk (south side), 18 m wide foot over bridge
and sewage treatment plant have been taken up.
Kishanganj station: The works of platform surfacing at platform no.
1&2, drinking water taps at platform no. 1&2, improvement of
circulating area, parking at second entry, approach road and
boundary wall have been completed. The works of platform shelter
and 12 m Foot Over Bridge have been taken up.
Luckeesarai Junction station: The works of new station building,
extension of foot over bridge towards new station building and
improvement of circulating area have been completed. The work of
lift has been taken up.
Thakurganj station: The works of 12 m wide foot over bridge,
improvement of platform surface at platform no. 2, platform shelters,
toilet block and raising of platform no. 1 have been completed. The
works of improvement of platform surface at platform no. 1, Coach
Indication Board and Train Indication Board have been taken up.
Page 5 of 6Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of stations is complex in nature involving safety
of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipe lines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried out
in close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time.
Indian Railways has a well-established mechanism to monitor
implementation of projects including their reviews, inspection, check for
time and cost overruns, quality of works and audits. Monitoring of projects
is done at various levels including through dedicated portal of Indian
Railways named Indian Railway Project Sanction and Management (IRPSM).
Works are carried out adhering to the standards and specifications laid
down in various codes and manuals. Inspections/audits/checks are carried
out from time to time by various agencies/officials/multi-disciplinary teams
as per laid down instructions and actions for correction are taken
immediately. The issues faced by the executing units are accordingly
addressed. This is a continuous and ongoing process.
*****
Page 6 of 6