GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2831
TO BE ANSWERED ON 05.08.2026
DEVELOPMENT OF ERNAKULAM MARSHALLING YARD AS A NEW RAILWAY
TERMINAL
2831. SHRI HIBI EDEN:
Will the Minister of RAILWAYS be pleased to state:
(a) whether it is a fact that the existing railway stations in the
Ernakulam area are facing severe capacity constraints and if so,
the details thereof;
(b) whether the Government has considered developing the Ernakulam
Marshalling Yard, where Railways owns around 110 acres of land,
into a new terminal to ease congestion and improve train
operations in Central Kerala and if so, the details thereof;
(c) whether there is a master plan for the proposed terminal at the
Ernakulam Marshalling Yard and if so, the details thereof;
(d) whether the Government will take steps to expedite the
administrative procedures so that the proposal for developing the
Ernakulam Marshalling Yard Terminal can move forward without
further delay and if so, the details thereof; and
(e) whether it is a fact that nearly 110 acres of railway land at the
Ernakulam Marshalling Yard remain unutilised/underutilised and if
so, the details thereof and if not, the reasons therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Ernakulam area is catered by Ernakulam Junction and Ernakulam
Town Railway Station.
§ Page 1 of 10Ernakulam Junction station is served by 136 passenger trains daily. Also,
08 Goods trains ply through the station daily. Presently, following facilities
are available at Ernakulam Junction Station:
• 10 Lines
• 06 Platforms
• 03 Pit lines
• 06 Stabling lines
Further, Ernakulam Town Station is served by 107 passenger trains daily.
Also, 08 Goods trains ply through the station daily. Presently, following
facilities are available at Ernakulam Town Station:
• 04 lines
• 02 Platforms
The Coaching Terminals/Coaching Maintenance Depots are planned and
executed based on anticipated passenger footfall, traffic trends,
operational & maintenance requirements and requirements for further
development.
59.57 acre Railway land is available at Ernakulam Marshalling yard which
has been planned to be used for railway facilities and developmental
works.
Further, to improve the capacity and strengthen the railway network in
Keralam, the following surveys/works have been taken up:
S.N Project Status
1 Mangaluru – Kasaragod - Field Location Survey (FLS) has
Shoranur 3rd Line (307 Km) been sanctioned for preparation of
Detailed Project Report (DPR). Field
Survey work completed.
2 Shoranur - Ernakulam 3rd & FLS has been sanctioned for
Page 2 of 104th Line (107 Km) preparation of DPR. Field Survey
work completed.
3 Ernakulam - Kayankulam 3rd FLS has been sanctioned for
Line (via Kottayam) (115 Km) preparation of DPR. Traffic survey
completed.
4 Kayankulam - FLS has been sanctioned for
Thiruvananthapuram 3rd Line preparation of DPR. Field Survey
(105 Km) work completed.
5 Thiruvananthapuram - FLS has been sanctioned for
Nagercoil 3rd Line (71 Km) preparation of DPR.
6 Shoranur - Coimbatore 3rd & FLS has been sanctioned for
4th Line (99 Km) preparation of DPR. Field Survey
work completed.
7 Ernakulam - Kumbalam Work has been sanctioned recently
doubling (8 km) at a cost of Rs. 808 cr.
8 Kumbalam-Turavur doubling Work has been sanctioned recently
(16 km) at a cost of Rs. 1,172 cr.
9 Turavur - Mararikulam Work has been sanctioned recently
doubling (21 km) at a cost of Rs. 451 cr.
10 Mararikulam - Alappuzha Work has been sanctioned recently
doubling (11 km) at a cost of Rs. 221 cr.
11 Alappuzha - Ambalapuzha Work has been sanctioned recently
doubling (13 km) at a cost of Rs. 324 cr.
After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines depend upon appraisals and approvals by
various stakeholders.
Keralam:-
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
Page 3 of 10fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2026-27 ₹3,795 crore (more than 10 times)
Projects Sanctioned:-
As on 01.04.2026, 09 projects (03 new line and 06 doubling) of 302 km
length, costing ₹11,650 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Total Expenditure
projects Length Commissioned upto March, 2026
(in Km) upto March, 2026 (₹ in Cr.)
(in Km)
New line 03 148 0 317
Doubling 06 154 40 3,550
/multitracking
Total 09 302 40 3,867
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in the
State of Keralam are as under:
S. Project Cost
No. (₹ in Crores)
1 Dindigul - Palghat & Pollachi - Coimbatore gauge 1,360
conversion (217 km)
2 Quilon- Tiruchendur gauge conversion (357 km) 1,122
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
Page 4 of 10Ongoing Projects:-
Some of the projects falling fully/partly in the State of Keralam which have
been taken up are as under:
S.No. Project Cost
(₹ in Crores)
1 Angamali-Sabarimala new line (111 km) 3,801
2 Ernakulam-Kumbalam doubling (8 km) 808
3 Kumbalam - Thuravur doubling (16 km) 1,172
4 Trivandrum- Kanyakumari doubling (87 km) 4,494
5 Alappuzha-Ambalapuzha doubling (13 km) 324
6 Turavur - Mararikulam doubling (21 km) 451
7 Mararikulam-Alappuzha doubling (11 km) 221
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of
land acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 618 ha
Land Acquired 78 ha (13%)
Balance Land to be acquired 540 ha (87%)
Railway had deposited ₹1,976 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:
SN Name of the project Total Land Balance
land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Angamali - Sabarimala new line (111 304 25 279
km)
2. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam–Turavur Patch doubling (16 10 9 1
km)
Page 5 of 104. Shoranur-Vallathol doubling (10 Km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Page 6 of 10Station Redevelopment:-
Ministry of Railways has identified Ernakulam Town and Ernakulam
Junction Railway Station for redevelopment under Amrit Bharat Station
Scheme. The progress at Ernakulam Town and Ernakulam Junction stations
is given below:
At Ernakulam Junction station, the structural works of east terminal
building, west terminal building, multi-level car parking and service
building have been taken up. The structural works of P-way depot and P-
way office has been completed and finishing works taken up.
At Ernakulam Town railway station, the structural work of west terminal
building- segment 1, multi level car parking, residential tower and
foundation for the foot over bridge have been completed. The finishing work
of multi level car parking, west terminal building (segment I) and super
structure work of foot over bridge was taken up. However, due to slow
progress of the work, the contract was terminated and retendering process
has been taken up.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Page 7 of 10 Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term. So far, 1340 stations have been identified for
development under Amrit Bharat Station
Scheme, out of which 35 stations including Ernakulam Junction and
Ernakulam Town railway stations are located in Keralam. The names of
stations identified for development under Amrit Bharat Station Scheme in
Keralam are as following:
State No. of Names of Stations
Stations
Alappuzha , Angadippuram, Angamali for Kaladi,
Chalakudi, Changanassery, Chengannur,
Chirayinkeezh, Ernakulam, Ernakulam Town,
Ettumanur, Ferok, Guruvayur , Kannur, Kasargod,
Keralam 35 Kayankulam Jn, Kollam Jn, Kozhikode,
Kuttippuram, Mavelikara, Neyyattinkara , Nilambur
Road, Ottappalam, Parappanangadi, Payyanur,
Punalur, Shoranur Jn., Thalassery,
Thiruvananthapuram Central, Thrisur, Tirur,
Page 8 of 10Tiruvalla, Tripunithura, Vadakara, Varkala
Shivagiri, Wadakancheri
Completed Stations:-
Development works at railway stations under Amrit Bharat Station Scheme
in Keralam have been taken up at a good pace. The detail of stations where
development works are completed in Keralam is as given below:
State No. of Name of Stations
Stations
Angamaly for Kaladi, Chalakudi, Changanassery,
Chirayinkeezh, Ferok, Guruvayur, Kuttippuram,
Keralam 16 Mavelikara, Nilambur Road, Parappanangadi,
Shoranur Jn., Thalassery, Tirur, Tripunithura,
Vadakara, Wadakancheri
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Kasargod Station: The works of improvements of station building,
new entrance porch, improvements of booking office and concourse,
improvement of platform surface of platform no. 2 & 3, improvements
of circulating area and parking, improvement of waiting hall, toilets,
platform shelters, lifts, installation of coach indication board and
improvement of amenities for Divyangjan have been completed. The
works of extension of platform no. 1, 6 m wide foot over bridge,
escalator and parking at second entry have been taken up.
Angadippuram station: The works of improvement of station building,
new entrance porch, concourse and booking office, platform shelter,
improvement of platform surfacing of platform no. 1 & 2, waiting hall,
toilet, improvement of circulating area and parking, approach road,
Page 9 of 10installation of coach indication board, train indication board, signages
and lifts have been completed. The work of provision of 6 m wide foot
over bridge has been taken up.
Payyanur station: The works of raising platform no. 2 & 3, provision of
platform shelter, improvement of concourse, booking office, waiting
hall, circulating area at second entry, parking, installation of coach
indication board and train indication board have been completed. The
works of improvement of station building, circulating area at main
entry, amenities for Divyangjan, 6 m wide foot over bridge and lifts
have been taken up.
Kollam station: The works of service building, multi level car parking
and parcel building have been completed. The works of 12 m wide
foot over bridge, air concourse, north terminal building, south
terminal building and platform upgradation have been taken up.
Further, development / upgradation of stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time.
*****
Page 10 of 10