GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 635
TO BE ANSWERED ON 22.07.2026
DEVELOPMENT OF KOLLAM RAILWAY STATION
635. SHRI N K PREMACHANDRAN:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government proposes to complete the railway
development works in a time-bound manner and if so, the details
thereof;
(b) the present status of development work of Kollam Railway Station and
the percentage of works completed, physical progress, financial
progress and proposed date of completion;
(c) whether the Government initiated action to complete the development
of Railway Over Bridge (ROB) works in Kollam Lok Sabha Constituency
and if so, the details thereof;
(d) whether the Government initiated action to construct the ROB at
Kundara Pallimukku in a time-bound manner and if so, the details
thereof; and
(e) whether the Government initiated timely action to give permission to
construct a ROB at Valacode considering the black spot if so, the
details of action taken thereon?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e):
Keralam:
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
§ Page 1 of 9fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2026-27 ₹3,795 crore (more than 10 times)
Projects Sanctioned:-
As on 01.04.2026, 09 projects (03 new line and 06 doubling) of 302 km
length, costing ₹11,650 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Total Exp.
projects Length Commissioned upto upto March,
(in Km) March, 2026 2026
(in Km) (₹ in Cr.)
New line 03 148 0 317
Doubling 06 154 40
3,550
/multitracking
Total 09 302 40 3,867
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in the
State of Keralam are as under:
S.N Project Cost
(₹ in
Crores)
1 Dindigul - Palghat & Pollachi - Coimbatore gauge 1,360
conversion (217 km)
2 Quilon- Tiruchendur gauge conversion (357 km) 1,122
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
Page 2 of 9Ongoing Projects:-
Some of the projects falling fully/partly in the State of Keralam which have
been taken up are as under:
S No. Project Cost
(₹ in Crores)
1 Tirunnavaya –Guruvayur new line (35 km) 144
2 Angamali-Sabarimala new line (111 km) 3,801
3 Ernakulam-Kumbalam doubling (8 km) 808
4 Kumbalam - Thuravur Patch doubling (16 km) 1,172
5 Trivandrum- Kanyakumari doubling (87 km) 4,494
6 Alappuzha-Ambalapuzha doubling (13 km) 324
7 Turavur - Mararikulam doubling (21 km) 451
8 Mararikulam-Alappuzha doubling (11 km) 221
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 618 ha
Land Acquired 78 ha (13%)
Balance Land to be acquired 540 ha (87%)
Railway had deposited ₹1,976 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
Page 3 of 9SN Name of the project Total Land Balance
land acquired Land to
required (in Ha) be
(in Ha) acquired
(in Ha)
1. Angamali - Sabarimala new line (111 304 25 279
km)
2. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam – Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur-Vallathol doubling (10 km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Station Redevelopment:-
Ministry of Railways has identified Kollam Railway Station for
redevelopment under Amrit Bharat Station Scheme. The works at Kollam
station has been taken up at good pace.
At Kollam station, the works of service building, multi level car parking and
parcel building have been completed. The works of 12 m wide foot over
bridge, air concourse, north terminal building, south terminal building and
platform upgradation have been taken up.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Page 4 of 9 Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 35 stations including Kollam are
located in Keralam. The names of stations identified for development under
Amrit Bharat Station Scheme in Keralam are as following:
State No.of Names of Stations
Stations
Alappuzha , Angadippuram, Angamali For Kaladi,
Keralam 35
Chalakudi, Changanassery, Chengannur,
Chirayinkeezh, Ernakulam, Ernakulam Town,
Ettumanur, Ferok, Guruvayur ,Kannur, Kasargod,
Page 5 of 9Kayankulam Jn, Kollam Jn, Kozhikode,
Kuttippuram, Mavelikara, Neyyattinkara ,
Nilambur Road, Ottappalam, Parappanangadi,
Payyanur, Punalur, Shoranur Jn., Thalassery,
Thiruvananthapuram Central, Thrisur, Tirur,
Tiruvalla, Tripunithura, Vadakara, Varkala
Shivagiri, Wadakancheri
Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Keralam have been taken up at a good pace. The detail of stations where
development works are completed in Keralam is as given below:
State No. of Name of Stations
Stations
Keralam 16 Angamaly for Kaladi, Chalakudi, Changanassery,
Chirayinkeezh, Ferok, Guruvayur, Kuttippuram,
Mavelikara, Nilambur Road, Parappanangadi,
Shoranur Jn., Thalassery, Tirur, Tripunithura,
Vadakara, Wadakancheri
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Page 6 of 9Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise. Kollam railway station falls under the jurisdiction of Southern
Railway. For this zone, an allocation of ₹ 665 crore has been made for the
financial year 2026-27, out of which an expenditure of ₹ 398 crore (upto
June, 2026) has been incurred so far.
Development / Upgradation of stations is complex in nature involving safety
of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipe lines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried out
in close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Page 7 of 9 Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
ROBs/ RUBs:-
Sanctioning of works of Road over Bridge (ROD)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Railway. Such works are prioritised and taken up on the basis of their
impact on safety in train operations, mobility of trains & impact for road
users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis-a-vis 2014-26 (Upto May'26) is as under:
Period ROBS/RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May'26) 14,451 Nos. (131 Nos. in the State of Keralam)
Page 8 of 9As on 01.06.2026, 4,993 Nos. ROBS/ RUBs works are sanctioned at a cost
of approx. ₹1,17,492 Cr. on Indian Railways including 145 Nos. ROBs/ RUBs
works at a cost of approx. ₹24,786 Cr. in the state of Keralam which are at
various stages of planning and execution.
In Kollam Lok Sabha Constituency, 11 Nos. ROBs/ RUBs works are ongoing
at a cost of approx. ₹390 Cr in which are at various stages of planning and
execution.
The construction of ROB at Kundara Pallimukku is in lieu of LC No.526 at
Km.748/1-2 in between Ezhukone-Kundara stations in Kollam-Sengottai
Section of Madurai Division was sanctioned at cost ₹37.24 Cr. on cost
sharing basis. The General Arrangement Drawing (GAD) has been approved
by Railways and land acquisition has been taken up.
The work for widening of the existing ROB No. 2134 at Valacode at Km
714/900-715/100 in between Edamon-Punalur section is being taken up by
NHAI. The General Arrangement Drawing (GAD) has been taken up.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for closure
of LC, fixing of approach alignment, approval of General Arrangement
Drawing (GAD), land acquisition, removal of encroachment, shifting of
infringing utilities, statutory clearances from various authorities, law and
order situation in the area of project / work sites, duration of working
season in a year for the particular project / area due to climatic conditions
etc. All these factors affect the completion time of the projects / works.
*****
Page 9 of 9