GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6415
ANSWERED ON 2ND APRIL, 2026
DEVELOPMENT OF ROAD INFRASTRUCTURE IN NASHIK
6415. SHRI RAJABHAU PARAG PRAKASH WAJE:
Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government is aware of the acute traffic congestion,
frequent accidents and infrastructure stress on the stretch between
Dwarka Circle and Nashik Road in Nashik city and if so, the corrective
action taken thereof;
(b) whether any proposal has been approved or is under consideration
for construction of a flyover on the said stretch and if so, the present
status thereof;
(c) the details of statutory clearances required for the project,
including land, environmental and railway clearances and the status of
such clearances as received and pending;
(d) the timelines fixed for execution of the project and the budgetary
allocations made so far;
(e) whether the said stretch falls under National Highways Authority of
India (NHAI) and is included under Bharatmala Pariyojana;
(f) whether the Government proposes to complete and operationalise
the flyover before Kumbh Mela-2027 and if so, the details thereof; and
(g) whether the Government has planned or sanctioned any new
National Highway projects, an Outer Ring Road in view of the
increasing traffic demand in Nashik and if so, the project-wise details
thereof along with the present status and timelines?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (f) The Government has sanctioned the construction of a grade-
separated interchange at the Dwarka Circle in Nashik city at an
estimated cost of Rs. 213.86 crore, which is under implementation by
the Maharashtra State Infrastructure Development Corporation Limited
(MSIDCL). In addition, the State Government has submitted a proposal
for the development of the Dwarka Circle junction – Upnagar Naka –
Datta Mandir Chowk stretch of NH-60 at an estimated cost of Rs.
258.53 crore to be implemented through Nashik Municipal Corporation.
The proposal will be considered for sanction based on requirement of
connectivity & traffic density.
The work for the construction of Dwarka Circle interchange is
under implementation with the scheduled date for completion in
February 2027, before the Kumbh Mela - 2027. The interchange is
being developed within the available Right of Way (ROW), and all the
statutory clearances for the project have been obtained.
(g) The alignment for construction of outer ring road for Nashik city
has been approved. A part of this ring road has been taken up by the
State Government of Maharashtra through its own funds.
*****