3006. SHRI APPALANAIDU KALISETTI
Will the PRIME MINISTER be pleased to state :-
(a) the details of the number of Small Modular Reactor (SMR) projects that have been
approved granted in-principle clearance or are presently under examination by the
Department of Atomic Energy;
(b) the details of SMRs under development, including their present stage of progress,
design and capacity-wise;
(c) the details of financial allocations made for SMR research, development and
demonstration during the last three Union Budget cycles along with the estimated cost
of the BSMR-200 and other proposed demonstration units;
(d) whether any public sector undertakings, private industrial entities or State Governments
have expressed interest in hosting or partnering in SMR projects and if so, the details
thereof;
(e) the names of the States where feasibility studies for SMR deployment have been
initiated;
(f) whether any proposal has been submitted by the Government of Andhra Pradesh and if
so, the details thereof; and
(g) the expected timeline for commissioning the first SMR demonstration units and for
scaling up to commercial deployment?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a)(b)&(c) Under the Nuclear Energy Mission announced in the Union Budget 2025–26, a
total budgetary provision of ₹20,000 crore has been made for the research, design,
development, and deployment of Small Modular Reactors (SMRs). Bhabha Atomic Research
Centre (BARC) has undertaken design and development works on SMRs namely,
(i) 220 MWe Bharat Small Modular Reactor (BSMR-200),
(ii) 55 MWe Small Modular Reactor (SMR-55), and(iii) Up to 5 MWth High temperature gas cooled reactor meant for hydrogen generation.
The lead units of these SMRs will be established at DAE sites for technology demonstration.
The estimated utilisation of the allocated funds by BARC toward setting up SMRs is
mentioned below:
Reactor Cost Outlay (Rs Cr.)
Development and Construction of BSMR-200 5960
Development and Construction of SMR-55 (2 units) 7000
Design and construction of High Temperature Gas Cooled Reactor 320
(HTGCR)
Design, engineering & development works for new reactors 800
Civil and General Infrastructure Development for reactors 452
complex
The progress of these SMRs is as follows;
i) BSMR-200: AEC in-principle approval has been received for the project. Proposal for
administrative & financial sanction is cleared by Atomic Energy Commission (AEC) for
submission of the proposal to the Cabinet Committee.
ii) SMR-55: In-principle approval has been received for the project.
iii) HTGCR: In-principle approval has been received for the project. Detailed Project
Report (DPR) has been prepared. Siting consent has been received and Terms of
Reference (ToR) for obtaining environmental clearances has been received from
Ministry of Environment, Forest and Climate Change (MoEF&CC).
(d) Lead units of these SMRs will be constructed by DAE at its existing sites. So far, PSUs
like Engineers India Limited and Bharat Heavy Electrical Limited (BHEL) have been
contacted for detailed engineering of SMRs.
(e) Tarapur Atomic Power Station site, Maharashtra has been identified for lead units of
BSMR-200 and SMR-55 whereas Vizag, Andhra Pradesh site of BARC is identified for
High Temperature Gas Cooled Reactor (HTGCR).
(f) At present no such proposal is received in Department of Atomic Energy (DAE).
(g) Bharat Small Modular Reactor (BSMR) is being jointly designed and developed by
BARC and Nuclear power Corporation of India Limited (NPCIL). Estimated time for
construction of BSMR is 60 to 72 months from receipt of administrative & financial
approval.
*****