Date: 2026-03-13 Category: RAJYASABHA_QNA State: Union Government Country: India

Parliament Question: Development works of Pen Railway Station in the Amrit Bharat Station scheme

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
O.I.H GOVERNMENT OF INDIA MINISTRY OF RAILWAYS RAJYA SABHA UNSTARRED QUESTION NO. 2498 ANSWERED ON 13.03.2026 DEVELOPMENT WORKS OF PEN RAILWAY STATION IN THE AMRIT BHARAT STATION SCHEME 2498# SHRI DHAIRYASHIL MOHAN PATIL: Will the Minister of RAILWAYS be pleased to state: (a) whether Government plans to include Pen Railway Station in the Amrit Bharat Station Scheme (ABSS) in the upcoming phases; (b) if not, whether Government plans to develop Pen Railway Station under any alternative scheme; and (c) details of approved and/or ongoing development works at Pen Railway Station in the past three years? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c) At Pen station, located in Maharashtra, facilities like high level platforms, Foot Over Bridge, drinking water arrangement, Unreserved Ticketing System & Passenger Reservation System window, parking, Pay & Use toilet etc. are available. The work of new Passenger Reservation System (PRS) building has been completed in recent years. Further, the works of upgradation of station building, improvement of platform shelter, platform surfacing, new platform shelter, new toilet blocks, Divyangjan facilities, improvement of circulating area, parking, approach road, lift and Foot Over Bridge have been sanctioned recently for development of Pen railway station. Further, development / redevelopment / upgradation / modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. Development / redevelopment / upgradation / modernisation of a station is carried out based on category of station/condition/traffic handled etc. Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach. §The scheme involves preparation of master plans and their implementation in phases to improve the stations. The master planning includes:  Improvement of access to station and circulating areas  Integration of station with both sides of city  Improvement of station building  Improvement of waiting halls, toilets, sitting arrangement, water booths  Provision of wider foot over bridge/air concourse commensurate with passenger traffic  Provision of lift/escalators/ramp  Improvement /Provision of platform surface and cover over platforms  Provision of kiosks for local products through schemes like ‘One Station One Product’  Parking areas, Multimodal integration  Amenities for Divyangjans  Better passenger information systems  Provision of executive lounges, nominated spaces for business meetings, landscaping, etc. keeping in view the necessity at each station The scheme also envisages sustainable and environment friendly solutions, provision of ballastless tracks etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term. So far, 1337 stations have been identified for development under this scheme, out of which 132 stations are located in Maharashtra. The names of stations identified for development under Amrit Bharat Station Scheme in Maharashtra are as following: State No. of Name of Stations Stations Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road, Akola, Akurdi, Amalner, Amgaon, Amravati, Andheri, Badnera, Balharshah, Bandra Terminus, Baramati, Belapur, Bhandara Road, Bhokar, Bhusawal, Borivali, Byculla, Chalisgaon, Chanda Fort, Chandrapur, Charni Road, Chhatrapati Sambhajinagar, Chhatrapati Shivaji Maharaj Terminus, Chinchpokli, Chinchwad, Dadar (CR), Dadar (WR), Dahisar, Daund, Dehu Road, Devlali, Dhamangaon, Dharangaon, Dharashiv, Dharmabad , Dhule, Diva, Dudhani, Gangakher , Godhani, Gondia, Grant Road, Hadapsar, Hatkanangale, Hazur Sahib §State No. of Name of Stations Stations Nanded, Himayatnagar, Hinganghat, Hingoli Deccan, Igatpuri, Jalgaon, Jalna, Jeur, Jogeshwari, Kalyan Jn, Kamptee, Kandivali, Kanjur Marg, Karad, Katol, Kedgaon, Kinwat , Kopargaon, Kurduwadi Jn, Kurla Jn, Lasalgaon, Latur, Lokmanya Tilak Terminus, Lonand Jn, Lonavla, Lower Parel, Malad, Malkapur, Manmad Jn, Manwath Road , Marine Lines, Matunga, Miraj Jn, Mudkhed Jn, Mumbai Central, Mumbra, Murtizapur Jn, Nagarsol , Nagpur Jn, Nandgaon, Nandura, Nandurbar, Narkher Jn, Nashik Road, Netaji Subhash Chandra Bose Itwari Junction, Pachora Jn, Palghar, Pandharpur, Panvel Jn, Parbhani Jn, Parel, Parli Vaijnath, Partur , Phaltan, Prabhadevi, Pulgaon Jn, Pune Jn, Purna Jn, Raver, Rotegaon , Sainagar Shirdi, Sandhurst Road, Sangli, Satara, Savda, Selu , Sewagram, Shahad, Shegaon, Shivaji Nagar Pune, Shri Chhatrapati Shahu Maharaj Terminus Kolhapur, Solapur, Talegaon, Thakurli, Thane, Titvala, Tumsar Road, Umri, Uruli, Vadala Road, Vidyavihar, Vikhroli, Wadsa, Wardha, Washim, Wathar Completed Stations: Development works at railway stations under Amrit Bharat Station Scheme in Maharashtra have been taken up at a good pace. Till now, works of 17 stations (Amgaon, Baramati, Chanda Fort, Chinchpokli, Devlali, Dhule, Kedgaon, Lasalgaon, Lonand Jn, Matunga, Murtizapur Jn, Nandura, Netaji Subhash Chandra Bose Itwari Junction, Parel, Savda, Shahad, Vadala Road) in Maharashtra have been completed under this scheme. The activities for development at other stations have also been taken up at good pace and progress of some of the stations is as given below:  Diva station: The works of improvement of station building, circulating area and parking on East side, new entry gate, platform raising and flooring of platform no. 5/6 and 7/8, platform shelter at platform no. 7/8, new toilet block, sewage treatment plant on West side, improvement of Foot Over Bridge at Kalyan end and Mumbai end have been completed. The work of new 6 m Foot Over Bridge has been taken up. § Mumbra station: The works for improvement of platform surface, seating arrangement, new toilet block, improvement of booking office, circulating area, sewage treatment plant and flooring of Foot Over Bridge have been completed. The work of escalator has been taken up.  Titwala station: The works for station building, entrance gate, platform surfacing, improvement of ticket booking office, toilet block, sewage treatment plant and improvement of two wheeler parking and approach road on East and West side have been completed. The work of new 6 m Foot Over Bridge has been taken up.  Vikhroli station: The works for improvement of station building on West side, platform surfacing, platform shelter, new toilet block at Mumbai end, improvement of toilet block at Kalyan end and Foot Over Bridge have been completed. The works of new booking office, circulating area on East and West side and parking of East side have been taken up.  Igatpuri station: The structural work new station building, improvement of existing station building, entrance gate, booking office, toilet block, platform surfacing, platform shelter over stairs of Foot Over Bridge and escalator, circulating area shelter and sewage treatment plant have been completed. The finishing work of new station building has been taken up. Development / Upgradation of railway stations is complex in nature involving safety of passengers & trains and requires various statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc. The progress also gets affected due to brownfield related challenges such as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of tracks and high voltage power lines, etc. and these factors affect the completion time. Development / Upgradation / Modernization of stations including Amrit Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer Amenities’. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise or station-wise or state- wise. Maharashtra is covered under the jurisdiction of four railway zones, namely, Central Railway, South Central Railway, South East Central Railway and Western Railway. For these zones, an allocation of ₹ 3,834 crore has been made for the financial year 2025-26, out of which an expenditure (up to January, 2026) of ₹ 3,461 crore has been incurred so far. ***** §

Continue your research