**Executive Summary**
This document is the response to Unstarred Question No. 1930 in Lok Sabha, answered on December 11th, 2025, regarding the dilapidated condition of roads in Sonbhadra. The Minister of Road Transport and Highways clarifies the Ministry's responsibility for the development and maintenance of National Highways (NHs). The document also outlines the ongoing and planned maintenance and development projects in the Sonbhadra district of Uttar Pradesh. The widening of Rewa-Renukoot-Garwa-Daltonganj-Ranchi of NH-39 is planned for 2025-26.
**Key Points / Main Content**
* **Responsibilities and Policies:**
* The Ministry of Road Transport and Highways is responsible for the development and maintenance of National Highways (NHs).
* Development and maintenance of NHs is a continuous process, prioritized based on inter-se priority, traffic density, and synergy with the PM Gati Shakti framework National Master Plan (NMP).
* Maintenance and Repair (M&R) of NH stretches under Operation, Maintenance and Transfer (OMT) Concessions / Operation and Maintenance (O&M) Contracts are the responsibility of the concerned Concessionaires / Contractors until the end of the Defect Liability Period (DLP) / Concession Period.
* For remaining NH stretches, the government undertakes maintenance through Performance based Maintenance Contract (PBMC) or Short Term Maintenance Contract (STMC).
* **NH-39 in Sonbhadra District:**
* NH-39, connecting Ranchi to Rewa, passes through Wyndhamganj and Dudhinagar, with a length of approximately 91 km in the Sonbhadra district of Uttar Pradesh.
* This stretch of NH-39 is currently under the Defect Liability Period (DLP).
* Contractors are responsible for rectifying damages, defects, maintenance, and repair during the concurrent DLP/ Maintenance period.
* Widening to 4L of Rewa-Renukoot-Garwa-Daltonganj-Ranchi of NH-39 is planned for Annual Plan 2025-26.
* **Other Roads:**
* Tilgudwa and Kon are connected to NH-39 via State Roads, and their development and maintenance is the responsibility of the State Government of Uttar Pradesh.
* **Ongoing Projects:**
* Three projects are detailed in the annexure; Stage Strengthening from Km. 220.000 to 221.000, 222.000 to 224.000, 225.000 to 247.000, 249.000 to 254.000 & 263.535 to 298.000 of NH-75E, Stage Strengthening from Km. 211.200 to 220.00, 221.00 to 222.00, 224.00 to 225.00, 247.00 to 249.00, 254.00 to 263.535 and 298.00 to 302.478 of NH-75E and Construction of ROB at LC no.50/B/E at km.298.000 on NH-75E on EPC mode
**Impact Analysis**
**Government of India, Ministry of Road Transport and Highways**
* **Impact:** Responsible for overseeing the development, maintenance, and repair of National Highways in the Sonbhadra district.
* **Action Required:** Ensure that contractors fulfill their responsibilities during the Defect Liability Period (DLP) and continue with the planned expansion and maintenance projects within the framework of the PM Gati Shakti National Master Plan.
**Concessionaires / Contractors**
* **Impact:** Responsible for the maintenance and repair of NH stretches under their concession agreements until the end of the Defect Liability Period.
* **Action Required:** Fulfill their contractual obligations for maintenance, repair, and rectification of damages within the DLP, and construct the ROB as per project specifications.
**Citizens of Sonbhadra District and Uttar Pradesh**
* **Impact:** Benefit from improved road conditions, reduced travel times, and enhanced safety on National Highways.
* **Action Required:** None specified.
**State Government of Uttar Pradesh**
* **Impact:** Responsible for the development and maintenance of State Roads connecting to NH-39.
* **Action Required:** Continue to maintain and develop State Roads in coordination with the central government's efforts on National Highways.
Key Entities Referenced
Ministry of Road Transport and Highways: The primary government body responsible for the development and maintenance of National Highways, and the focus of the unstarred question.
National Highways (NHs): The roads that are the subject of the parliamentary question regarding their dilapidated condition and repair.
NH-39: A specific National Highway, particularly the stretch connecting Ranchi to Rewa, discussed in the context of its condition in Sonbhadra district.
Sonbhadra: The district in Uttar Pradesh where the roads in question are located, making the location essential for understanding the policy’s scope.
PM Gati Shakti: A national master plan framework used in synergy with the development and maintenance of National Highways.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1930
ANSWERED ON 11TH DECEMBER, 2025
DILAPIDATED CONDITION OF ROADS IN SONBHADRA
†1930. Shri Chhotelal:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether Ranchi-Rewa, Kon, Wyndhamganj, Duddhi and Telgudwa
roads in Sonbhadra district of Robertsganj Parliamentary
Constituency are in dilapidated condition; and
(b) if so, the time by which these roads are likely to be repaired?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) and (b) The Government in the Ministry of Road Transport and
Highways is responsible for development and maintenance of
National Highways (NHs).
Development and maintenance of NHs, including NHs in the
State of Uttar Pradesh, is a continuous process. Works on NHs are
accordingly taken up depending upon inter-se priority, traffic
density and synergy with PM Gati Shakti framework National Master
Plan (NMP) to keep the NHs in traffic worthy conditions.Maintenance and Repair (M&R) of NH stretches, where development
works have commenced or Operation, Maintenance and Transfer
(OMT) Concessions / Operation and Maintenance (O&M) Contracts
have been awarded, are the responsibility of the concerned
Concessionaires / Contractors till the end of Defect Liability Period
(DLP) / Concession Period.
For the remaining NH stretches, Government has taken a
policy decision to undertake maintenance works either through
Performance based Maintenance Contract (PBMC) or through Short
Term Maintenance Contract (STMC).
The NH-39 connecting Ranchi to Rewa passes through
Wyndhamganj and Dudhinagar. Length of NH-39 in Sonbhadra
district of Uttar Pradesh is about 91 km and presently under Defect
Liability Period (DLP).
The details of ongoing NH projects in Sonbhadra district of
Uttar Pradesh are annexed;
The Contractor is responsible for rectification of damages,
defects, maintenance and repair in this section during concurrent
DLP/ Maintenance period.
Proposal of Widening to 4L of Rewa-Renukoot-Garwa-
Daltonganj-Ranchi of NH-39 is included under Annual Plan 2025-26.
Tilgudwa and Kon are connected to NH-39 via State Roads,
development and maintenance of which is the responsibility of the
State Government of Uttar Pradesh.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) AND (b) OF LOK SABHA UNSTARRED QUESTION NO.
1930 FOR ANSWER ON 11.12.2025 ASKED BY SHRI CHHOTELAL REGARDING DILAPIDATED CONDITION
OF ROADS IN SONBHADRA.
Details of ongoing NH projects in Sonbhadra district of Uttar Pradesh
Sl Name NH Total Name of Work Sanction Awarded Cost (Rs. Date of Start Date of Remarks
. of NH No. Length Cost (Rs. in Cr.) Completion/
N (in Km.) in Cr.) Target date
o. of
completion
Stage Strengthening from Km. 220.000 to
221.000, 222.000 to 224.000, 225.000 to
15.07.2020 07.07.2022 DLP upto
1 247.000, 249.000 to 254.000 & 263.535 to 57.50 34.50
06.07.2027
298.000 of NH-75E (New NH No. 39) length
64.465 Km.
NH-
91
39
Stage Strengthening from Km. 211.200 to
Rewa 220.00, 221.00 to 222.00, 224.00 to 225.00, 26.10.2021
07.10.2020 DLP upto
2 - 247.00 to 249.00, 254.00 to 263.535 and 29.63 17.11
25.10.2026
Ranc 298.00 to 302.478 of NH-75E (New NH No.
hi 39) length 26.813 km.
Road
NH-
39
Physical
Construction of ROB at LC no.50/B/E at 28.69 16.78
3 - 09.10.2021 31.12.2026 progress –
km.298.000 on NH-75E on EPC mode
15%
******