See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF POWER
RAJYA SABHA
UNSTARRED QUESTION NO.1912
ANSWERED ON 09.03.2026
DISTRIBUTION AND SUPPLY OF ENERGY FROM VARIOUS SOURCES
1912. SHRI BABUBHAI JESANGBHAI DESAI:
SHRI SHAMBHU SHARAN PATEL:
SHRI BRIJ LAL:
SHRI MITHLESH KUMAR:
SHRI RYAGA KRISHNAIAH:
SHRI AMAR PAL MAURYA:
SHRI NARAYANA KORAGAPPA:
DR. PARMAR JASHVANTSINH SALAMSINH:
SMT. DARSHANA SINGH:
Will the Minister of POWER be pleased to state:
(a) source-wise details of the total energy produced in the country including thermal, hydro,
nuclear and renewable energy during the last five years and current year including States of Bihar and
Uttar Pradesh especially under Uttar Pradesh Power Corporation;
(b) whether energy production capacity in the country is sufficient to meet the present and
projected demands of electricity and energy consumption in the country;
(c) if so, the details thereof, including peak demand met and supply position during the said period;
and
(d) the details of the distribution and supply of energy across the country from various sources
during the said period?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) : The source-wise details of total quantum of electricity generated in the country from various
sources including thermal, hydro, nuclear and renewable energy during the past five (5) financial years
and current financial year 2025-26 (upto January, 2026) are given at Annexure –I.
The details of electricity generated in the state of Bihar and Uttar Pradesh during last five financial
years and current financial year (up to Jan, 2026) are given at Annexure-II. Further, the details of
electricity generated by Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) in the state
Uttar Pradesh during last five financial years and current financial year (up to Jan, 2026) are given at
Annexure-III.
(b) to (d): There is adequate availability of power in the country to meet the present and projected
demand of the electricity. Present installed generation capacity of the country is 520.511 GW.
Government of India has addressed the critical issue of power deficiency by adding 296.388 GW of
fresh generation capacity since April, 2014 transforming the country from power deficit to power
sufficient.The details of Power Supply Position in terms of peak demand and energy requirement for the
last five financial years and the current FY i.e. 2025-26 (upto January, 2026) are attached at
Annexure-IV. These details indicate that Energy Supplied has been commensurate to the Energy
Requirement with only a marginal gap which is generally on account of constraints in the State
transmission/distribution network. Hence there is no impact of shortage on the economy and industrial
growth.
As per midterm review of 20th Electric Power Survey (EPS), the peak electricity demand and
energy requirement for FY 2029-30 is anticipated to be 345 GW and 2388 BU respectively and for
FY 2031-32, the peak electricity demand and energy requirement is anticipated to be 388 GW and
2703 BU respectively.
The Government have taken the following steps to meet the increasing demand of electricity in
the country:
1. Generation and Storage Planning:
(i) As per National Electricity Plan (NEP), installed generation capacity in 2031-32 is likely to be 874
GW. With a view to ensure generation capacity remains ahead of projected peak demand, all the
States, in consultation with CEA, have prepared their “Resource Adequacy Plans (RAPs)”, which
are dynamic 10-year rolling plans and includes power generation as well as power procurement
planning.
(ii) All the States were advised to initiate process for creating/ contracting generation capacities;
from all generation sources, as per their Resource Adequacy Plans.
(iii) In order to augment the power generation capacity, the Government of India has initiated
following capacity addition programme:
(A) The projected thermal (coal and lignite) capacity requirement by the year 2034–35 is
estimated at approximately 3,07,000 MW as against the 2,11,855 MW installed capacity as on
31.03.2023. To meet this requirement, Ministry of Power has envisaged to set up an additional
minimum 97,000 MW coal and lignite based thermal capacity.
To meet this requirement, several initiatives have already been undertaken. Thermal
capacities of around 18,160 MW have already been commissioned since April 2023 till
31.01.2026. In addition, 38,745 MW of thermal capacity (including 4,845 MW of stressed
thermal power projects) is currently under construction. The contracts of 22,920 MW have
been awarded and is due for construction. Further, 24,020 MW of coal and lignite-based
candidate capacity has been identified which is at various stages of planning in the country.
(B) 12,723.50 MW of Hydro Electric Projects are under construction. Further, 4,274
MW of Hydro Electric Projects are under various stage of planning and targeted to be
completed by 2031-32.
(C) 6,600 MW of Nuclear Capacity is under construction and targeted to be completed by
2029-30. 7,000 MW of Nuclear Capacity is under various stages of planning and approval.
(D) 1,57,800 MW Renewable Capacity including 67,280 MW of Solar, 6,500 MW of Wind
and 60,040 MW Hybrid power is under construction while 48,720 MW of Renewable Capacity
including 35,440 MW of Solar and 11,480 MW Hybrid Power is at various stages of planning
and targeted to be completed by 2029-30.
(E) In energy storage systems, 11,620 MW/69,720 MWh Pumped Storage Projects (PSPs) are
under construction. Further, a total of 6,580 MW/39,480 MWh capacity of Pumped Storage
Projects (PSPs) are concurred and yet to be taken up for construction. Currently, 9,653.94 MW/
26,729.32 MWh Battery Energy Storage System (BESS) capacity are under construction and
19,797.65 MW/ 61,013.40 MWh BESS capacity are under tendering stage
2. Transmission Planning: Inter and Intra-State Transmission System has been planned and
implementation of the same is taken up in matching time frame of generation capacity addition. Asper the National Electricity Plan, about 1,91,474 ckm of transmission lines and 1,274 GVA of
transformation capacity is planned to be added (at 220 kV and above voltage level) during the ten year
period from 2022-23 to 2031-32.
3. Promotion of Renewable Energy Generation:
(i) 100% Inter State Transmission System (ISTS) charges have been waived for inter-state sale
of solar and wind power for projects to be commissioned by 30th June 2025 (with waiver
tapering off 25% annually till June 2028), for co-located BESS projects commissioned by
June 2028, for Hydro PSP projects where construction work awarded by June 2028, for
Green Hydrogen Projects commissioned till December 2030 and for offshore wind projects
commissioned till December 2032.
(ii) Standard Bidding Guidelines for tariff based competitive bidding process for procurement
of Power from Grid Connected Solar, Wind, Wind-Solar Hybrid and Firm & Dispatchable
RE (FDRE) projects have been issued.
(iii) Renewable Energy Implementing Agencies (REIAs) are regularly inviting bids for
procurement of RE power.
(iv) Foreign Direct Investment (FDI) has been permitted up to 100 percent under the automatic
route.
(v) To augment transmission infrastructure needed for steep RE trajectory, transmission plan
has been prepared till 2032.
(vi) Laying of new intrastate transmission lines and creating new sub-station capacity has been
supported under the Green Energy Corridor Scheme for evacuation of renewable power.
(vii) Scheme for setting up of Solar Parks and Ultra Mega Solar Power projects is being
implemented to provide land and transmission to RE developers for installation of RE
projects at large scale
(viii) Schemes such as Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-
KUSUM), PM Surya Ghar Muft Bijli Yojana, National Programme on High Efficiency
Solar PV Modules, New Solar Power Scheme (for Tribal and PVTG Habitations/Villages)
under Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan (PM JANMAN) and Dharti
Aabha Janjatiya Gram Utkarsh Abhiyan (DA JGUA), National Green Hydrogen Mission,
Viability Gap Funding (VGF) Scheme for Offshore Wind Energy Projects have been
launched
(ix) To encourage RE consumption, Renewable Purchase Obligation (RPO) followed by
Renewable Consumption Obligation (RCO) trajectory has been notified till 2029-30. The
RCO which is applicable to all designated consumers under the Energy Conservation Act,
2001 will attract penalties on non-compliance.
(x) “Strategy for Establishment of Offshore Wind Energy Projects” has been issued.
(xi) Green Term Ahead Market (GTAM) has been launched to facilitate sale of Renewable
Energy Power through exchanges.
(xii) Production Linked Incentive (PLI) scheme has been launched to achieve the objective of
localization of supply chain for solar PV Modules.
***********ANNEXURE-I
ANNEXURE REFERRED IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 1912
ANSWERED IN THE RAJYA SABHA ON 09.03.2026
*************
Source-wise details of total quantum of electricity generated in the country from FY 2020-21 to FY 2022-23:
(All Generation figures are in Million Units (MUs))
2025-26
Fuel 2020-21 2021-22 2022-23 2023-24 2024-25
(upto
Jan'26)
COAL 9,50,937.55 10,41,487.43 11,45,907.58 12,60,902.62 12,98,872.29 10,31,882.53
DIESEL/HSD 126.31 117.24 229.71 400.58 442.65 358.21
L LIGNITE 30,505.68 37,094.04 36,188.34 33,949.79 32,994.77 24,906.72
A
M
R MULTI FUEL 0.00 0.00 0.00 0.00 0.00 0.00
E
H
T NAPTHA 101.41 0.00 0.83 0.03 0.00 0.00
NATURAL
50,842.59 36,015.77 23,884.21 31,295.91 31,580.05 22,764.15
GAS
THERMAL Total 10,32,513.54 11,14,714.48 12,06,210.67 13,26,548.93 13,63,889.76 10,79,911.61
NUCLEAR 43,029.08 47,112.06 45,861.09 47,937.41 56,680.83 45,193.67
TOTAL [Conventional] 10,75,542.62 11,61,826.54 12,52,071.76 13,74,486.34 14,20,570.59 11,25,105.28
WIND 60,149.95 68,640.07 71,814.16 83,385.35 83,347.19 95,586.95
SOLAR 60,402.26 73,483.94 1,02,014.24 1,15,975.11 1,44,150.23 1,38,386.93
ng
o)
BIOMASS 3,512.98 3,482.70 3,161.32 3,417.19 3,738.67 3,377.60
excludi
e
Hydr
BAGASSE 11,302.85 12,573.88 12,863.16 10,825.59 9,335.32 7,635.91
S
( rg
Ea SMALL
RL 10,258.41 10,463.55 11,170.62 9,485.04 11,568.04 10,885.08
HYDRO
OTHERS 1,621.06 2,268.17 2,529.18 2,746.55 2,869.73 2,453.59
Large Hydro 1,50,299.52 1,51,627.33 1,62,098.77 1,34,053.92 1,48,633.98 1,50,039.12
TOTAL [Renewable] 2,97,547.03 3,22,539.63 3,65,651.45 3,59,888.75 4,03,643.16 4,08,365.18
Bhutan Imp 8,765.50 7,493.20 6,742.40 4,716.10 5,484.18 7,765.68
GRAND TOTAL 13,81,855.15 14,91,859.37 16,24,465.61 17,39,091.19 18,29,697.93 15,41,236.14
************ANNEXURE-II
ANNEXURE REFERRED IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 1912
ANSWERED IN THE RAJYA SABHA ON 09.03.2026
*************
The details of electricity generated in the state of Bihar and Uttar Pradesh during last five financial years and current financial (year up to
Jan, 2026):
(All Generation figures are in Million Units (MUs))
2025-26
State Fuel 2020-21 2021-22 2022-23 2023-24 2024-25 (upto
Jan'26)
Conventional Coal 33,866.14 43,940.40 55,200.21 58,361.80 60,757.75 48,552.97
Total (Conventional) 33,866.14 43,940.40 55,200.21 58,361.80 60,757.75 48,552.97
Solar
160.63 163.08 169.53 195.19 325.86 263.60
Biomass - - - -
21.30 2.14
Bihar Renewable
Bagasse
1.48 65.84 106.68 140.98 104.70 48.36
Hydro
43.20 8.77 12.63 5.92 14.54 18.42
Total (Renewable) 226.61 239.83 288.85 342.08 445.10 330.38
34,092.75 44,180.23 55,489.06 58,703.88 61,202.85 48,883.35
Grand Total
Coal 1,19,592.96 1,30,698.93 1,51,154.99 1,52,505.20 1,61,337.30 1,37,067.34
Natural
Conventional 2,470.75 1,148.49 908.23 1,619.52 1,247.56 764.60
Gas
Nuclear 3,284.81 3,580.25 3,192.62 2,874.63 3,629.48 2,140.05
Total (Conventional) 1,25,348.52 1,35,427.67 1,55,255.84 1,56,999.35 1,66,214.34 1,39,971.99
Solar
1,856.19 2,900.41 3,674.02 3,971.31 4,966.06 4,244.53
Uttar
Biomass
Pradesh 135.82 85.20 66.35 46.65 76.48 88.47
Renewable Bagasse
3,590.87 3,160.39 3,183.67 2,923.55 2,457.35 1,574.63
Hydro
1,737.26 1,565.22 1,208.73 1,025.88 1,452.74 1,626.33
Others -
20.40 58.45 84.85 29.88 30.92
Total (Renewable) 7,320.13 7,731.62 8,191.22 8,052.23 8,982.50 7,564.88
Grand Total 1,32,668.65 1,43,159.29 1,63,447.06 1,65,051.58 1,75,196.84 1,47,536.87
*************ANNEXURE-III
ANNEXURE REFERRED IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 1912
ANSWERED IN THE RAJYA SABHA ON 09.03.2026
*************
The details of electricity generated by UPRVUNL in the state Uttar Pradesh during last five financial
years and current financial year up to Jan, 2026:
(All Generation figures are in Million Units (MUs))
Year 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26
Generation 25,797.94 27,310.19 34,796.96 33,704.12 38,256.72 35,101.54
************ANNEXURE-IV
ANNEXURE REFERRED IN REPLY TO PARTS (b) TO (d) OF UNSTARRED QUESTION
NO. 1912 ANSWERED IN THE RAJYA SABHA ON 09.03.2026
*************
The details of Power Supply Position, for the last five years and the current FY i.e. 2025-26 (upto
January, 2026)
Energy [in Million Unit (MU)] Peak [in Mega Watt (MW)]
Financial Year
Energy Energy Peak Peak Demand Not
(FY) Energy not Supplied
Requirement Supplied Demand Met Met
(MU) (MU) (MU) ( % ) (MW) (MW) (MW) (%)
2020-21 12,75,534 12,70,663 4,871 0.4 1,90,198 1,89,395 -802 -0.4
2021-22 13,79,812 13,74,024 5,787 0.4 2,03,014 2,00,539 -2,475 -1.2
2022-23 15,13,497 15,05,914 7,583 0.5 2,15,888 2,07,231 8,657 4.0
2023-24 16,26,132 16,22,020 4,112 0.3 2,43,271 2,39,931 3,340 1.4
2024-25 16,93,959 16,92,369 1,590 0.1 2,49,856 2,49,854 2 0.0
2025-26 (up to
14,27,436 14,27,009 427 0.0 2,45,444 2,45,416 28 0.0
January, 2026)
************