GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1810
TO BE ANSWERED ON 29.07.2026
DOUBLING OF MERTA ROAD–NAGAUR–BIKANER RAILWAY SECTION
†1810. SHRI HANUMAN BENIWAL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether any proposal for doubling of Merta Road-Nagaur-Bikaner
railway section is under consideration;
(b) if so, the details thereof including the expected timeline for approval of
budget/commencement of work and the current status of the project;
(c) whether the Government has approved the survey for construction of
Nagaur-Phalodi new railway line;
(d) if so, the details of the progress made in the survey work, estimated
length of railway lines, estimated cost and the action taken so far
regarding approval of the project;
(e) whether the completion of the said two projects is likely to boost
railway connectivity, freight transport, tourism, defence and industrial
activities in Western Rajasthan; and
(f) if so, the details of the time-bound action plan prepared by the
Government for speedy approval and implementation of these projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) : Merta Road - Nagaur - Bikaner is an existing single rail line
section on Indian Railway Network. To augment the connectivity in this
section, Final Location Survey (FLS) for Merta Road- Bikaner Doubling
(173 Km) has been sanctioned. Field survey has been completed and
Detailed Project Report (DPR) has been prepared.
§ Page 1 of 3Nagaur and Phalodi are existing railway stations on Indian Railway
Network and connected via Lalgarh as well as via Merta Road/Raikabag
Palace (Jodhpur). However, to provide direct additional connectivity, FLS
for Nagaur - Phalodi (148 km) new line has been sanctioned for preparation
of DPR. Survey work has been taken up.
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
sanctioning of projects is a continuous and dynamic process, exact
timelines depend upon appraisal and approval by various stakeholders.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway's own operational requirements
Socio-economic considerations
Overall availability of funds
Railway Infrastructure projects enable socio-economic development of the
region including:
Better integration of the region with other parts of the country
Faster movement of goods and services
Improving logistics efficiency
Enhance line capacity
Page 2 of 3 Increase in direct and indirect employment opportunities for the
people of the region
Reduces operational bottlenecks
Development of tourism industry and increase in industrial activities
in the region.
*****