See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1829
TO BE ANSWERED ON 29.07.2026
EARLY COMPLETION OF SANCTIONED ROB WORKS IN PEDDAPALLI LOK
SABHA CONSTITUENCY
1829. SHRI VAMSI KRISHNA GADDAM:
Will the Minister of RAILWAYS be pleased to state:
(a) whether any Road Over Bridge works have been sanctioned in
Peddapalli Lok Sabha Constituency and if so, the present status
thereof;
(b) the status of ROBs at LC Nos. 31 and 32 Odela, LC No. 34 Kolanur, LC
No. 38 Cheekurai, LC No. 39 Konaram, LC Nos. 40 and 46 Gaureddypeta,
LC No. 46E/A Kannala, LC No. 49 Kundhanapalli and LC No. 52
Pedampeta;
(c) whether there has been any delay in each ROB work and if so, the
reasons therefor;
(d) whether funds have been sanctioned and expenditure incurred for above
said ROBs and if so, the details thereof;
(e) whether the Government proposes to prepare a time-bound completion
plan for above said ROBs and if so, the details thereof; and
(f) whether the expected date of completion of each ROB has been fixed
and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Sanctioning of works of Road over Bridge (ROB)/Road under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic
process of Indian Railway. Such works are prioritised and taken up on the
basis of their impact on safety in train operations, mobility of trains &
impact for road users and feasibility etc.
§ Page 1 of 5No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (520 Nos. in the State of Telangana)
As on 01.06.2026, 4,993 Nos. ROB/ RUB works are sanctioned at a
cost of approx. ₹ 1,17,492 Cr on Indian Railways including 118 Nos. ROB/
RUB at a cost of approx. ₹ 4,883 Cr in the state of Telangana which are at
various stages of planning and execution.
As on 01.06.2026, there are 13 ROBs, 26 RUBs and 20 LCs in
Peddapalli Constituency. 16 works are sanctioned in Peddapalli
Constituency for construction of ROB and the work of preparation of
Technical Feasibility Report/ Detailed Project Report (TFR/DPR) has been
taken up for 04 LCs. The details are as under:
S. LC Details ROB Cost of Remarks
No. / work (₹
RUB in Cr
approx.)
1 LC No. 27 at km 317/5-7 ROB 48 GAD has been approved.
on Bisugir Sharif- Tender has been
Potkapalli awarded.
2 LC No. 28 at km 315/10- ROB 31 The work of GAD and
12 on Bisugir Sharif- estimate have been
Potkapalli taken up.
3 LC No. 29 at km 314/44- ROB 31 The work of GAD and
46 on Potkapalli- estimate have been
Page 2 of 5Bisugir Sharif taken up.
4 LC No. 31 at km 310/34- ROB 26 The work of GAD and
36 on Potkapalli- estimate have been
Kolanoor taken up.
5 LC No. 32 at km 309/40- ROB 26 The work of GAD and
310/4 on Potkapalli- estimate have been
Kolanoor taken up.
6 LC No. 34 at km 304/46- ROB 61 The work of GAD and
48 on Kolanoor- estimate have been
Peddapalli taken up.
7 LC No. 38 at km 295/20- ROB 44 The work of GAD and
24 on Kolanoor- estimate have been
Peddapalli taken up.
8 LC No. 39 at km 292/28- ROB 137 Railway portion has
32 on Kolanoor- been completed.
Peddapalli Approach work has
been taken up.
9 LC No.40 at km 291/14- ROB 96 GAD has been approved.
16 on Peddapalli- Tender has been
Raghavapuram awarded.
10 LC No.42 at km 289/14- ROB 46 The work of GAD and
16 on Peddapalli – estimate have been
Raghavapuram taken up.
11 LC No. 44 at km 285/24- ROB 46 The work of GAD and
26 on Peddapalli - estimate have been
Raghavapuram taken up.
12 LC No. 45 at km 284/40- ROB 50 The work of GAD and
44 on Peddapalli - estimate have been
Raghavapuram taken up.
Page 3 of 513 LC No. 46 at km 282/10- ROB 86 GAD under review.
12 on Raghavapuram - Tender has been
Ramagundam awarded.
14 LC No. 49 at km 275/46- ROB 111 GAD under review.
48 on Raghavapuram - Tender has been
Ramagundam awarded.
15 LC No. 52 at km 270/41- ROB 35 The work of GAD and
43 on Ramagundam- estimate have been
Peddampet taken up.
16 LC No. 68 at km 226/12- ROB 52 The work of GAD and
14 on Rechni Road- estimate have been
Repalliwada taken up.
17 LC No. 1 at km 3/2-3 on - - The work of preparation
Peddapalli- Karimnagar of Technical Feasibility
18 LC No. 2 at km 3/13-14 - - Report/ Detailed
on Peddapalli- Project Report
Karimnagar (TFR/DPR) for the
19 LC No. 5 at km 7/11-12 - - construction of ROB
on Peddapalli- at these LCs has been
Karimnagar taken up.
20 LC No. 6 at km 13/0-1 - -
on Peddapalli-
Karimnagar
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
Page 4 of 5authorities, law and order situation in the area of project / work
sites, duration of working season in a year for the particular project /
area due to climatic conditions etc. All these factors affect the
completion time of the projects / works.
16 Nos. ROBs are delayed/held up on account of the State Govt. The
details are as under:
S.No. Reason ROBs (in No.)
1. Delay in Land Acquisition by State Govt. 15
2. Finalization of Alignment by State Govt. 01
Railways have taken following measures to expedite the progress of
ROB/RUB works:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure and substructure drawings for
various combinations of span, skewness and width of road on the
Railway portion has been done to avoid delays during the design
approval. This has been issued in the form of a compendium, which
can be directly adopted for Road Over Bridge across Railway lines for
expeditious planning.
*****
Page 5 of 5