See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF POWER
RAJYA SABHA
UNSTARRED QUESTION NO.1105
ANSWERED ON 09.02.2026
ECONOMIC VIABILITY OF COAL BASED POWER PLANTS
1105 SHRI K.R.N. RAJESHKUMAR:
Will the Minister of POWER be pleased to state:
(a) whether Government has assessed the economic viability of adding coal-based power capacity
beyond what is already under construction;
(b) if so, the details of such assessment and the projected Plant Load Factor (PLF) of coal plants
through 2032;
(c) whether Government has conducted a comparative cost analysis between new coal- based
electricity and renewable energy coupled with battery storage; and
(d) if so, the current tariff ranges for coal-based electricity versus firm and dispatchable renewable
energy options?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) & (b): Generation expansion planning study is carried out by Central Electricity Authority
(CEA) to determine the optimal mix of different generation resources (coal, hydro, solar, wind,
storage, nuclear etc.) to meet the projected electricity demand. Various parameters like the capital cost
of different generation technologies, fuel cost, O&M cost, useful life etc. are considered in the
Generation expansion planning study.
As per the studies, projected thermal (coal and lignite) capacity requirement by the year 2034โ
35 is estimated at approximately 3,07,000 MW as against the 2,11,855 MW installed capacity as on
31.03.2023. To meet this requirement, Ministry of Power has envisaged to set up an additional
minimum 97,000 MW coal and lignite based thermal capacity.
As against the above-mentioned requirement, thermal capacities of around 17,360 MW have
already been commissioned since April 2023 till 20.01.2026. In addition, 39,545 MW of thermal
capacity (including 4,845 MW of stressed thermal power projects) is currently under construction. The
contracts of 22,920 MW have been awarded and is due for construction. Further, 24,020 MW of coal
and lignite-based candidate capacity has been identified which is at various stages of planning in the
country.
The projected Plant Load Factor (PLF) of coal-based plants by the year 2031-32 is estimated
to be around 61%. However, PLF of coal-based power plants will depend on a number of factors like
the increase in electricity demand, actual coal based and RE capacity materializing etc.
โฆโฆ.2.- 2 -
(c) & (d) : The generation expansion planning model, while arriving at optimal capacity mix, does
the comparative analysis between new coal- based plants, solar, wind, storage etc. considering the cost
of different technologies, projected electricity demand, RE generation profile, fuel cost, operational
characteristics of different types of technologies, storage duration etc.
The cost of the electricity generated from coal-based plants depends on various factors such as
life of the plant, distance of the plant from the coal mines, type of technology (sub-critical, super-
critical) etc.
The all-India Weighted Average Rate of Sale of Power (WARSP) of the electricity generated
from existing coal-based plants for the past three years ranges from INR 4.36/kWh to INR 4.58/kWh,
with the lowest tariff being about INR 1.52/kWh.
The tariff discovered for new coal based Thermal Power Projects selected through Tariff Based
Competitive Bidding (TBCB) route is in the range of INR 5.38 - 6.30 /kWh. This is based on bidding
carried out in the year 2025.
The Tariff discovered under firm and dispatchable renewable energy (FDRE) tenders awarded
by SECI in August, 2024, is the range of INR 4.98 - 4.99/kWh.
Although the tariff ranges appear broadly similar, a direct comparison is not appropriate on
like-to-like basis due to the inherent differences in the nature, operational characteristics, risk
allocation, fuel cost structure, dispatch profile, and contractual framework of coal-based thermal
power and FDRE projects. The two categories of power serve different system requirements and
involve distinct cost components and performance obligations.
************