GOVERNMENT OF INDIA
DEPARTMENT OF ATOMIC ENERGY
RAJYA SABHA
UNSTARRED QUESTION NO-3045
ANSWERED ON 19/03/2026
EXPANSION OF NUCLEAR POWER GENERATION CAPACITY
3045. SHRI PRADIP KUMAR VARMA
Will the PRIME MINISTER be pleased to state:-
(a) the current installed nuclear power generation capacity in the country;
(b) the total power generated from nuclear power plants during the last three years;
(c) the number of new nuclear projects that are under construction; and
(d) the targets for nuclear power capacity expansion during the coming years?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a) The present installed nuclear power capacity in the country is 8,780 MW comprising
of 24 nuclear power plants (excluding RAPS-1 – 100 MW).
(b) The total generation from the nuclear power plants during the past three years have
been 45855 Million Units (MUs) in 2022-23, 47971 MUs in 2023-24 and 56681 MUs
in 2024-25.
(c) & (d) At present, there are 18 nuclear power reactors with a total capacity of 13600 MW
under implementation, comprising of 10 nuclear reactors under construction (including
PFBR – 500 MW) and 8 reactors under pre-project activities.
Location Project Capacity (MW)
Projects Under Construction / Commissioning
Rajasthan RAPP-8 700
KKNPP-3&4 2 X 1000
Kudankulam, Tamilnadu
KKNPP-5&6 2 X 1000
Gorakhpur, Haryana GHAVP-1&2 2 X 700
Kaiga, Karnataka Kaiga-5&6 2 X 700
PFBR, Kalpakkam PFBR 1 X 500Projects Under Pre-project Activities
Gorakhpur, Haryana GHAVP-3&4 2 X 700
Chutka, Madhya Pradesh Chutka-1&2 2 X 700
Mahi Banswara, Mahi Banswara-1&2 2 X 700
Rajasthan Mahi Banswara-3&4 2 X 700
BHAVINI is currently commissioning a 500 MWe Prototype Fast Breeder Reactor
(PFBR) project at Kalpakkam, Tamil Nadu. Government has accorded approval to carry
out pre-project activities for 2 x 500 MWe twin unit of FBR 1&2 project at Kalpakkam,
Tamil Nadu. On attaining first criticality of PFBR, Government will be approached for
financial sanction of FBR 1&2 projects.
*****