Date: 2025-08-20 Category: Not Applicable State: Union Government Country: India

Parliament Question: Expansion Plan of Dhubri Railway Station in Assam

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary:** The Ministry of Railways addresses a query regarding the expansion and modernization plans for Dhubri Railway Station in Assam. Dhubri has been identified for development under the Amrit Bharat Station Scheme. Development works at railway stations under Amrit Bharat Station Scheme in the state of Assam have been taken up at a good pace. While improvements are underway, a specific timeframe for completion cannot be provided. **Key Points / Main Content:** **Dhubri Railway Station Details:** * Dhubri Railway Station is classified as an NSG4 station. * The station serves approximately 1000 passengers daily. * Dhubri is the terminating station on Fakiragram-Dhubri section. **Amrit Bharat Station Scheme:** * Dhubri Railway Station is included in the Amrit Bharat Station Scheme. * The scheme focuses on long-term station redevelopment through master planning and phased implementation. * Master plan components include improved access, station integration with the city, building upgrades, enhanced amenities, and sustainable solutions. * 1337 stations across India, including 50 in Assam, are identified for development. **Current Development Status:** * Structural work of station building and platform shelters have been completed. * Finishing works of station building, circulating area improvement, waiting hall, toilet, platform improvements, Foot Over Bridge, and lifts are in progress. * Phase I works of one station Haibargaon in the state of Assam has been completed under this scheme. * Majpat station: The work of platform shelter, platform extension, train indication board, toilet, porch, improvement of circulating area and lighting have been completed. * Rangapara North Junction station: The works of platform shelter has been completed. * Tangla station: The work of platform shelters, platform extension and train indication board have been completed. * Udalguri station: The work platform shelter, platform extension and train indication board have been completed. **General Railway Development:** * Development is ongoing, prioritized by station category and subject to fund availability. * Development faces challenges including statutory clearances, utility shifting, and operational constraints. * Funding is allocated zone-wise under Plan Head 53 (Customer Amenities). * Northeast Frontier Railway zone (covering Assam) has an allocation of ₹554 crore for FY 2025-26, with ₹139 crore spent up to July 2025. **Train Services and Freight:** * Currently, 08 trains serve Dhubri station. * Introduction of new trains depends on capacity, path availability, rolling stock, and infrastructure. * No demand/proposal for freight loading/unloading at Dhubri station has been received in the last three years. **Impact Analysis:** **Passengers:** * *Impact:* Improved amenities, enhanced accessibility, and a better overall station experience. * *Action Required:* Utilize the new and upgraded facilities as they become available. **Railway Authorities (Northeast Frontier Railway):** * *Impact:* Responsible for implementing the Amrit Bharat Station Scheme at Dhubri and other stations. * *Action Required:* Continue with the planning, execution, and monitoring of the development works. **Local Businesses:** * *Impact:* Potential opportunities for kiosks and local product sales through schemes like "One Station One Product". * *Action Required:* Explore opportunities to participate in the "One Station One Product" scheme. **Freight Operators/Businesses:** * *Impact:* Currently, no freight loading/unloading is occurring at Dhubri. Future opportunities may arise if demand increases. * *Action Required:* Assess the potential for utilizing Dhubri station for freight transport and submit proposals if viable. **Divyangjans (People with Disabilities):** * *Impact:* Improved accessibility through ramps, lifts, and other amenities catering to their needs. * *Action Required:* Utilize the accessible facilities and report any issues or areas for improvement.

Key Entities Referenced

Dhubri Railway Station: A railway station located in Assam, identified for development under the Amrit Bharat Station Scheme. It connects Assam to the rest of the country. Amrit Bharat Station Scheme: A scheme launched by Indian Railways for the redevelopment and modernization of railway stations with a long-term approach. 1337 stations have been identified under the scheme. Assam: A state in India where Dhubri Railway Station and 50 other stations are located, all of which have been identified for development under the Amrit Bharat Station Scheme. SHRI ASHWINI VAISHNAW: Minister of Railways, Information Broadcasting and Electronics Information Technology, who provided the answer to the Lok Sabha question. MD. RAKIBUL HUSSAIN: Member of Parliament who raised the unstarred question in Lok Sabha regarding the expansion plan of Dhubri Railway Station. Indian Railways: The entity responsible for the railway network, including the Amrit Bharat Station Scheme and expansion works. Northeast Frontier Railway: The Zonal Railway under whose jurisdiction the state of Assam falls. An allocation of 554 crore has been made for the financial year 2025-26. Alipurduar: A location that Dhubri station connects to via railway. Dhubri is the terminating station on Fakiragram-Dhubri section of Alipurduar division of Northeast Frontier Railway
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 4395 TO BE ANSWERED ON 20.08.2025 EXPANSION PLAN OF DHUBRI RAILWAY STATION IN ASSAM 4395. MD. RAKIBUL HUSSAIN: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government is aware that Dhubri Railway Station is of immense strategic importance and witnesses a hefty footfall due to its geographical importance of connecting Assam to the rest of the country and if so, the details thereof; (b) whether there are any plans to expand and modernise the said Railway Station to accommodate the increasing passenger traffic and improve railway services in the region and if so, the details thereof; (c) the details of the specific expansion plans including infrastructure upgrades, additional platforms/improved passenger amenities; and (d) whether any special provisions are proposed to boost freight transport via Dhubri Railway Station given its economic and logistical significance and if so, the details thereof? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (d) Dhubri Railway Station, located in the state of Assam, has been categorized as a NSG-4 station which serves approximately 1000 passengers daily. It has been identified for development under Amrit Bharat Station Scheme. The structural work of station building and platform shelters have been completed. The finishing works of station building, improvement of circulating area, waiting hall, toilet, platform no. 2 & 3, 12 m Foot Over Bridge and lifts have been taken up.To enhance customer experience and provide better amenities, Indian Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach. The scheme involves preparation of master plans and their implementation in phases to improve the stations. The master planning includes: • Improvement of access to station and circulating areas • Integration of station with both sides of city • Improvement of station building • Improvement of waiting halls, toilets, sitting arrangement, water booths • Provision of wider foot over bridge/air concourse commensurate with passenger traffic • Provision of lift/escalators/ramp • Improvement /Provision of platform surface and cover over platforms • Provision of kiosks for local products through schemes like ‘One Station One Product’ • Parking areas, Multimodal integration • Amenities for Divyangjans • Better passenger information systems • Provision of executive lounges, nominated spaces for business meetings, landscaping, etc. keeping in view the necessity at each station The scheme also envisages sustainable and environment friendly solutions, provision of ballastless tracks etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term.So far, 1337 stations, including 50 stations located in the state of Assam, have been identified for development under this scheme. The names of stations identified for development under Amrit Bharat Station Scheme in the State of Assam are as following: No. of State Amrit Names of Amrit Stations Stations Assam 50 Amguri, Arunachal, Chaparmukh, Dhemaji, Dhubri, Dibrugarh, Diphu, Duliajan, Fakiragram Jn., Gauripur, Gohpur, Golaghat, Gosai gaon hat, Guwahati, Haibargaon, Harmuti, Hojai, Jagi Road, Jorhat Town, Kamakhya Jn, Kokrajhar, Lanka, Ledo, Lumding Jn, Majbat, Makum Jn, Margherita, Mariani Jn, Murkongselek, Naharkatiya, Nalbari, Namrup, Narangi, New Bongaigaon Jn, New Haflong, New Karimganj Jn, New Tinsukia Jn, North Lakhimpur, Pathshala, Rangapara North Jn, Rangiya Jn, Sarupathar, Sibsagar Town, Silapathar, Silchar, Simaluguri, Tangla, Tinsukia, Udalguri, Viswanath Chariali Development works at railway stations under Amrit Bharat Station Scheme in the state of Assam have been taken up at a good pace. Till now, phase-I works of 01 station (Haibargaon) in the state of Assam has been completed under this scheme. The works at other stations have also been taken up at good pace and progress of some of the stations is as given below:• Majpat station: The work of platform shelter, platform extension, train indication board, toilet, porch, improvement of circulating area and lighting have been completed. The works of lift and improvement of parking area have been taken up. • Rangapara North Junction station: The works of platform shelter has been completed. The works of station building, porch, improvement of circulating area, train indication board, lighting and tactile pathways have been taken up. • Tangla station: The work of platform shelters, platform extension and train indication board have been completed. The work of construction of toilet, porch and improvement circulating area,tactile pathways, lifts have been taken up. • Udalguri station: The work platform shelter, platform extension and train indication board have been completed. The work of construction of toilet, porch, improvement of circulating area, tactile pathways have been taken up. Further development / redevelopment / upgradation / modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. The priority for development / redevelopment / upgradation / modernisation of stations is accorded to higher category of station over lower category of station while sanctioning and executing the works. Development / upgradation of railway stations is complex in nature involving safety of passengers & trains and requires various statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc. The progress also gets affected due to brownfield related challengessuch as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of tracks and high voltage power lines, etc. and these factors affect the completion time. Therefore, no time frame can be indicated at this stage. Development / upgradation / modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer Amenities’. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise, or station wise or state-wise. The state of Assam is covered under the jurisdiction of Northeast Frontier Railway. For the zone, an allocation of ₹ 554 crore has been made for the financial year 2025-26, out of which an expenditure (up to July, 2025) of ₹ 139 crore has been incurred so far. Further, Indian Railways is committed to run more trains on its network. However, introduction of new trains, increase in frequency of existing trains, extension of existing trains etc. on any route/section depends on various factors which include: • Capacity of that section, • Availability of path, • Availability of required rolling stock, • Availability of matching infrastructure for rolling stock, • Maintenance requirement of railway tracks and other assets Considering the above factors, presently 08 trains are serving Dhubri station connecting it inter alia to Alipurduar, Guwahati, Silghat Town.To increase the capacity of the rail network and hence to run more trains, Indian Railways have taken up network expansion works in a big way. As far as freight transport is concerned, Dhubri is the terminating station on Fakiragram-Dhubri section of Alipurduar division of Northeast Frontier Railway. No demand/proposal for freight loading/unloading at Dhubri station has been received in the last three years. *****