**Executive Summary**
This document is the response from the Minister of Railways to questions raised in Lok Sabha Unstarred Question No. 641 regarding the Chetak and Mewar Express trains. The response addresses the possibility of extending service to Dungarpur, improving connectivity to the Banswara-Dungarpur region, and the status of railway projects in the area. The question was to be answered on 03.12.2025.
**Key Points / Main Content**
* **Chetak and Mewar Express Operations:**
* Chetak Express (20473/20474) runs between Delhi Sarai Rohila and Udaipur with approximately nine hours of lie-over time at Udaipur.
* Mewar Express (12963/12964) runs between Hazarat Nizamuddin and Udaipur with approximately eleven hours of lie-over time at Udaipur for primary maintenance.
* Both Chetak and Mewar Express trains have 100% occupancy in both directions.
* Indian Railways utilizes lie-over periods for maintenance, cleaning, and special train operations.
* **Extension of Services and Connectivity:**
* Gauge conversion of the Udaipur - Dungarpur-Himmat Nagar section is completed, leading to the introduction of five pairs of trains connecting Dungarpur to cities like Kota, Indore, Udaipur, Ahmedabad, and Jaipur.
* Introduction/extension of train services is an ongoing process dependent on operational feasibility, capacity, path availability, rolling stock, infrastructure, and maintenance.
* A new line project was sanctioned for Ratlam-Banswara-Dungarpur (188 km) at a cost of ₹2083 crore with 50:50 cost-sharing between Rajasthan and the Ministry of Railways.
* Land acquisition for the project is the responsibility of the State Government of Rajasthan.
* 646 hectares of land have been acquired of the total 1,736 hectares needed.
* **Land Acquisition and Compensation:**
* Compensation for land acquisition is provided by the State Government’s Revenue Department following the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
* **Surveys for New Lines:**
* A survey has been sanctioned for the Nimach-Banswara-Dahod-Alirajpur-Nandurbar new line (380 km) for DPR preparation.
* A survey has also been sanctioned for a new line from Mandsor-Pratapgarh-Ghatol-Banswara (168 km), and field survey work is complete.
* **Connectivity Improvement Projects:**
* Ratlam-Nagda 3rd and 4th line (41 km, ₹964 Cr) has been sanctioned.
* Ratlam-Vadodara 3rd and 4th line (259 km, ₹8387 Cr) has been sanctioned.
* A feasibility survey has been sanctioned for doubling the Chanderiya-Dungarpur-Himmatnagar section (326 km).
* **Project Sanctioning Factors:**
* Project sanctioning depends on consultations, appraisals, approvals from NITI Aayog, the Ministry of Finance, traffic projections, connectivity, missing links, and congestion.
* Project completion depends on land acquisition, forest clearance, utility shifting, statutory clearances, geological conditions, law and order, and working months available.
**Impact Analysis**
**Stakeholders: People of Banswara-Dungarpur Lok Sabha Constituency**
* **Impact:**
* Increased connectivity to major cities such as Delhi, Mumbai, Kota, Indore, Udaipur, Ahmedabad, and Jaipur.
* Potential for economic development due to improved rail infrastructure.
* Impacted by land acquisition processes for railway projects.
* **Action Required:**
* Cooperate with land acquisition processes and provide necessary documentation.
* Stay informed about project developments and timelines.
* Coordinate with the State Government about compensation and transparency in land acquisition.
**Stakeholders: State Government of Rajasthan**
* **Impact:**
* Required to provide land for railway projects and bear 50% of the cost for the Ratlam-Banswara-Dungarpur line.
* Responsible for land acquisition and compensation disbursement.
* Increased coordination with Indian Railways for project approvals and execution.
* **Action Required:**
* Expedite land acquisition processes for railway projects.
* Ensure transparent and fair compensation to land owners.
* Coordinate with Indian Railways to secure necessary approvals and clearances.
**Stakeholders: Indian Railways (IR)**
* **Impact:**
* Responsible for optimizing train services and infrastructure.
* Dependent on State Government for land acquisition and project approvals.
* Needs to manage lie-over periods for maintenance and operations.
* **Action Required:**
* Continuously assess the feasibility of extending train services.
* Coordinate with the State Government to expedite land acquisition.
* Efficiently utilize lie-over periods for maintenance and special operations.
Key Entities Referenced
Ministry of Railways: The primary government body responsible for the Indian railway network.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and resettlement Act, 2013: The governing act for land acquisition related to railway projects.
Indian Railways (IR): The state-owned railway company of India.
Chetak Express and Mewar Express: Specific train services under consideration for extension.
Ratlam-Banswara-Dungarpur new line project: A specific railway line project mentioned in the document.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 641
TO BE ANSWERED ON 03.12.2025
EXTENSION OF CHETAK AND MEWAR EXPRESS
†641. SHRI RAJKUMAR ROAT:
Will the Minister of RAILWAYS be pleased to state:
(a) whether it is a fact the Chetak and Mewar Express trains running
between Udaipur and Delhi have a halt at Udaipur railway station for more
than eight hours;
(b) if so, whether the Government proposes to extend its service upto
Dungarpur;
(c) if so, the time by when it is likely to be done and if not, the reasons
therefor;
(d) whether the Banswara-Dungarpur Lok Sabha Constituency lacks direct
train connectivity to Delhi, Mumbai and other major cities;
(e) if so, the details of efforts of the Government to directly connect the
Banswara- Dungarpur Lok Sabha Constituency with Delhi and Mumbai;
(f) the time by when the Dungarpur-Ratlam via Banswara rail project
approved in 2012 is expected to be completed and the details of work
completed so far; and
(g) the details of the timeframe for completion of the remaining work and
the amount of compensation received by the people and the extent to
which it remains unpaid?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (g) Chetak Express 20473/20474 runs between Delhi Sarai Rohila and
Udaipur and has a lie over of about nine hours at Udaipur. Mewar Express
12963/12964 runs between Hazarat Nizamuddin and Udaipur and it has a
lie over of about eleven hours at Udaipur during which it undergoes
primary maintenance.Occupancy of both Chetak & Mewar express is about 100% in both
directions at present.
Indian Railways (IR) constantly endeavour to optimise the utilisation of its
assets by gainfully utilising the lie-over periods. The lie-over periods are
utilised for undertaking maintenance (Primary and Secondary) and/or
cleaning of coaches for ensuring safety of operation and cleanliness. The
lie-over periods are also utilised for operation of special trains.
Gauge conversion of Udaipur - Dungarpur-Himmat Nagar section has been
recently completed. After gauge conversion, 5 pairs of trains connecting
Dungarpur to important cities like Kota, Indore, Udaipur, Ahmedabad,
Jaipur etc have been introduced.
Introduction of new train services including extension of existing train
services to enhance connectivity, is an ongoing process on IR subject to
operational feasibility on any route/section. It depends on various factors
which include-
• Capacity of that section,
• Availability of path,
• Availability of required rolling stock,
• Availability of matching infrastructure for rolling stock,
• Maintenance requirement of railway tracks and other assets
Strengthening of Rail connectivity of Dungapur-Banswara area
Ratlam-Banswara-Dungarpur (188 Km) new line project was sanctioned at
a cost of 2083 crore on 50:50 cost-sharing between Government of
Rajasthan and the Ministry of Railways. Land for this project is to be
provided by State Government of Rajasthan at their own cost. So far, 646
hectares land out of total required 1,736 hectares land has been acquired.
Railway acquires land through concerned State/District Authorities. All the
activities in connection with land acquisition like assessment of amount of
compensation to land owners and disbursement of compensation etc. are
under purview of the State Government.Compensation for land acquisition is made to the last owners by the
Revenue Department of the State Government after demanding the same
from Railways. The process is undertaken in coordination with State
Governments, following the provisions of the Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and resettlement Act,
2013.
To connect Banswara and surrounding area to Mumbai and Delhi, a survey
for Nimach Banswara Dahod-Alirajpur-Nandurbar new line (380 Km) has
also been sanctioned for preparation of Detailed Project Report (DPR)
In addition, a survey of new line from Mandsor- Pratapgarh - Ghatol -
Banswara (168 Km) has been sanctioned for preparation of the Detalled
Project Report. The field survey work has been completed.
To improve the connectivity of the Banswara - Ratlam region, following
projects have been sanctioned recently:-
Sl Project Length (in Km) Cost ( ₹ in Cr. )
1. Ratlam-Nagda 3 rd and 4 th line 41 964
2. Ratlam-Vadodara 3 r d and 4 t h line 259 8387
Feasibility survey of doubling of Chanderiya (Chittaurgarh) - Dungarpur -
Himmatnagar (326 Km) has also been sanctioned.
Further, after preparation of DPR, sanctioning of the project requires
consultation with various stakeholders including State Governments and
necessary approvals viz. appraisal of NITI Aayog, Ministry of Finance etc.
As sanctioning of projects is a continuous and dynamic process, exact
timelines depend upon appraisal and approval by various stakeholders.
Sanction of any railway project depends upon many parameters/factors
which include the following:
● Anticipated traffic projections and Remunerativeness of the
proposed route
● First and last mile connectivity provided by the project
● Connection of missing links and providing additional route
● Augmentation of congested/saturated lines● Demands raised by State Governments/Central Ministries/Public
representatives,
● Railway's own operational requirements
● Socio-economic considerations
● Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
● Land acquisition by State Government
● Forest clearance
● Shifting of infringing utilities
● Statutory clearances from various authorities
● Geological and topographical conditions of area
● Law and order situation in the area of project site
● Number of working months in a year for particular project site
etc.
All these factors affect the completion time and cost of the project/s.
*****