GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 3929
ANSWERED ON 27.03.2026
FREIGHT TRAFFIC AUGMENTATION AND LOGISTICS EFFICIENCY
3929 DR. K. LAXMAN:
Will the Minister of RAILWAYS be pleased to state:
(a) the manner in which the approved multi-tracking projects will result in additional freight traffic for
essential commodities like coal, steel, iron ore, cement and food grains;
(b) the expected reduction in logistics costs through modal shift to railways;
(c) the benefits for industrial clusters in Telangana from improved freight connectivity to ports; and
(d) the contribution to decongesting the rail network and improving freight speeds?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Capacity enhancement of railway network has been taken up by Indian Railways in a big
way during last 11 years. The details of commissioning/laying of new track across Indian Railways is
given below:-
New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
Projects sanctioned:
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure projects including port-
connectivity (154 New Line, 33 Gauge Conversion and 244 Doubling) of total length 35,966 Km,
costing approx. 6.75 lakh crore are sanctioned. The summary is as under:-
Page 1 of 7
Β§Total Length Length Commissioned
No of Total Exp upto Mar'25
Category NL/GC/DL till Mar'25
Projects ( in Crore)
(km) (Km)
New Lines 154 16,142 3,036 1,45,318
Gauge Conversion 33 4,180 2,997 22,753
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made available in public domain on Indian
Railwayβs website.
Some of the Major Multi-tracking projects:
Some of the major multi-tracking projects sanctioned for augmentation of Railway Network are as
under:
Cost
SN Project Name
(βΉ in Crore)
1 Chopan β Chunar doubling (102 Km) 1,553
2 Guntur β Bibinagar doubling (239 Km) 3,238
3 Mudkhed β Medchal & Mahbubnagar β Dhone doubling (418 Km) 5,655
4 Samakhiali β Gandhidham Quadrupling (53 Km) 1,571
5 Lumding β Furkating doubling (140 Km) 2,334
6 Ajmer β Chanderiya doubling (178 Km) 1,813
7 Motumari β Vishnupuram with RoR doubling (100 Km) 1,746
8 Chandil β Anara β Damodar 3rd line (121 Km) 2,170
9 Varanasi β Pt. Deen Dayal Upadhyaya Multitracking with rail cum road 2,642
bridge on river ganga (15 Km)
10 Jalgaon β Manmad 4th line (160 Km) 2,773
11 Bhusawal β Khandwa 3rd & 4th line (131 Km) 3,514
12 Sambalpur β Jarapada 3rd & 4th line (127 Km) 3,916
13 Jharsuguda β Sason 3rd & 4th line (35 Km) 1,181
14 Gondia β Ballarshah doubling (240 Km) 4,819
15 Kharsia β Naya Raipur β Parmalkasa 5th & 6th line (278 Km) 8,741
16 Wardha β Balharshah Quadrupling (135 Km) 2,381
Page 2 of 7
Β§Cost
SN Project Name
(βΉ in Crore)
17 Ballari β Chikjajur doubling (185 Km) 3,342
18 Koderma β Barkakana doubling (133 Km) 3,063
19 Itarsi β Nagpur 4th line (297 Km) 5,451
20 Dangoaposi β Jaroli 3rd & 4th line (43 Km) 1,752
21 Secunderabad β Wadi 3rd & 4th line (173 Km) 5,012
22 Furkating β New Tinsukia doubling (194 Km) 3,634
23 Bakhtiyarpur β Rajgir β Tilaiya doubling (104 Km) 2,192
24 Gondia β Dongargarh 4th line (84 Km) 2,223
25 Wardha β Bhusawal 3rd & 4th line (314 Km) 9,197
26 Hosapete β Bellary quadrupling (65 Km) 2,372
27 Kasara β Manmad 3rd & 4th line (131 Km) 10,154
28 Punarakh β Kiul 3rd & 4th line (50 Km) 2,668
29 Gamharia β Chandil 3rd & 4th line (55 Km) 1,168
30 Sainthia- Pakhur 4th Line (81 Km) 1,569
31 Santragachi- Kharagpur 4th line (111 Km) 2,905
32 Nergundi β Barang &Khurda Road β Vizianagaram 3rd line (385 Km) 5,618
33 Son Nagar β Andal Multi tracking (375 Km) 13,606
34 Gorakhpur Cantt β Valmiki Nagar doubling (96 Km) 1,270
35 Jaipur β Sawai Madhopur doubling (131 Km) 1,269
36 Luni β Samdari β Bhildi doubling (272 Km) 3,531
37 Narkatiaganj β Raxaul β Sitamarhi β Darbhanga & Sitamarhi β Muzaffarpur 4,553
doubling (256 Km)
38 Prayagraj (Iradatganj) β Manikpur 3rd line (84 Km) 1,640
39 Tirupati β Pakala β Katpadi doubling (104 Km) 1,332
40 Ratlam β Nagda 3rd and 4th line (41 Km) 1,018
41 Aluabari Road β New Jalpaiguri 3rd & 4th line (57 Km) 1,786
42 Aurangabad (Chhatrapati Sambhajinagar) β Parbhani (177 Km) 2,179
43 Bhagalpur β Dumka β Rampurhat doubling (177 Km) 3,169
44 Itarsi β Bina 4th line (237 Km) 4,329
45 Vadodara β Ratlam 3rd & 4th line (259 Km) 8,885
46 Devbhumi Dwarka (Okha) β Kanalus doubling (141 Km) 1,457
47 Badlapur β Karjat 3rd and 4th line (32 Km) 1,324
Page 3 of 7
Β§Cost
SN Project Name
(βΉ in Crore)
48 Delhi β Ambala Cantt 3rd & 4th line (194 Km) 5,983
49 Gondia β Jabalpur doubling (231 Km) 5,236
Indian Railway has taken several measures during the last few years to enhance the freight loading and
revenue. Freight loading since 2014 is as below:
Freight loading
Year
(in Million Tonnes)
2014-15 1,098
2015-16 1,104
2016-17 1,109
2017-18 1,162
2018-19 1,223
2019-20 1,210
2020-21 1,233
2021-22 1,418
2022-23 1,512
2023-24 1,591
2024-25 1,617
1,700 1,617
1,600
1,500 1,591
1,418
1,512
1,400
1,300 1,210
1,162
1,200
1,104
1,223 1,233
1,100
1,098 1,109
1,000
Because of these measures, the freight loading has increased from 1,233 MT in 2020-21 to 1,617 MT in
2024-25. During 2024-25, IR transported 1,617 MT thus becoming second largest freight carrying
Railways in the world.
Page 4 of 7
Β§
51-4102 61-5102 71-6102 81-7102 91-8102 02-9102 12-0202 22-1202 32-2202 42-3202 52-4202
Freight loading (in Million Tonnes)TELANGANA:
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure
projects and safety works, falling fully/partly in the State of Telangana is as under:
Period Outlay
2009-14 886 Cr./Yr.(including Andhra Pradesh)
2025-26 5,337 Cr.
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the State of Telangana during
2009-14 and 2014-25 is as under:
New Track
Period Average Commissioning of new tracks
Commissioned
2009-14 87 Km 17.4 km/per year
2014-25 774 Km 70.4 km /per year (more than 4 times)
Projects sanctioned:
As on 01.04.2025, 20 Railway projects (6 New Lines and 14 Doubling), of a total length of 2,166 Km,
costing βΉ35,045 crore falling fully/partly in the State of Telangana have been sanctioned. The summary
is as under:-
Length Commissioned Total Exp. upto
No. of Total Length
Category till March, 2025 March, 2025
projects (in Km)
(in Km) ( in Crore)
New Line 6 840 245 4,611
Doubling/Multi-
14 1,326 303 6,939
tracking
Total 20 2,166 548 11,550
Recently completed projects:
Details of some of the completed projects falling fully/partly in the State of Telangana are as under:
Cost
S. N. Project
( in Crore)
1 Peddapalli- Nizamabad new line (178 Km) 926
2 Jaggayyapeta- Janpahad new line (48 Km) 737
3 Akkanapet β Medak new line (17 Km) 205
4 Bhadrachalam Road-Sattupalli new line (56 Km) 990
Page 5 of 7
Β§Cost
S. N. Project
( in Crore)
5 Raghavapuram-Mandamari Doubling (24 Km) 165
6 Raichur-Guntakal Doubling (81 Km) 388
7 Secunderabad- Mehboobnagar Doubling (85 Km) 1,266
8 Multi- Modal Transport System (MMTS) Phase-II, Hyderabad (103 Km) 1,156
9 Byepass line at Peddapalli (2 Km) 37
Ongoing Projects:
Details of some of the projects falling fully/partly in the State of Telangana which have been taken up
are as under:
Cost
S.N. Name of Project
( in Crore)
1 Manoharabad-Kothapalli new line (151 Km) 2,781
2 Malkangiri-Pandurangapuram new line (174 Km) 3,592
3 Kazipet -Vijaywada - 3rd line (220 Km) 3,315
4 Kazipet -Ballarshah - 3rd line (202 Km) 3,183
5 Guntur- Bibinagar Doubling(239 Km) 2,853
6 Mudkhed - Medchal - Dhone Doubling (417 Km) 4,686
7 Bhadrachalam Road β Dornakal Doubling(55 Km) 770
8 Motumari-Vishnupuram doubling and RoR at Motumari (100 Km) 1,596
9 Nashkal (Pindial)-Hasanparthi Road bypass (25 Km) 465
10 Secunderabad (Sanathnagar)- Wadi 3rd and 4th line (173 Km) 5,012
11 Dornakal Rail over Rail (RoR) Flyover (11 Km) 327
Execution of important infrastructure projects falling fully/partly in the State of Telangana is held up
due to delay in land acquisition. Status of land acquisition in Telangana is as under:
Total Land required 2,343 Ha
Land Acquired 1,580 Ha (67%)
Balance Land to be acquired 764 Ha (33%)
Details of some major projects which are delayed due to land acquisition are as under:-
Total land Balance Land to
Land acquired
S.N. Name of the project required be acquired
(Ha)
(Ha) (Ha)
1. Guntur- Bibinagar Doubling 31 0 31
Mudkhed β Medchal & Mahbubnagar β
2. 70 0 70
Dhone Doubling
Page 6 of 7
Β§Total land Balance Land to
Land acquired
S.N. Name of the project required be acquired
(Ha)
(Ha) (Ha)
3. Kazipet-Vijaywada 3rd Line 135 118 17
4. Manoharabad β Kothapalli New Line 1146 1050 96
Completion of Railway project/s depends on various factors which include the following:
ο· Land acquisition by State Government
ο· Forest clearance
ο· Shifting of infringing utilities
ο· Statutory clearances from various authorities
ο· Geological and topographical conditions of area
ο· Law and order situation in the area of project site
ο· Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Various steps taken by the Government for effective and speedy implementation of rail projects
include:
ο· Substantial increase in allocation of funds.
ο· Delegation of powers at field level.
ο· Close monitoring of progress of project at various levels.
ο· Regular follow up with State Governments and concerned authorities for expeditious land
acquisition, forestry and Wildlife clearances and for resolving other issues pertaining to
projects.
*****