GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1809
TO BE ANSWERED ON 29.07.2026
GOPALPUR–RAYAGADA NEW RAILWAY LINE
1809. SHRI SAPTAGIRI SANKAR ULAKA:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the present status of the Final Location Survey (FLS)
sanctioned for the proposed Gopalpur–Rayagada New Railway Line
including the alignment, stations proposed and expected date of
completion of the survey;
(b) whether the Government has received representations seeking
examination of an alternative alignment connecting Akhusingi–Naira–
Gudari–Bankili/Durgi with the proposed Gunupur–Therubali Railway Line
instead of the presently contemplated merger near Ramanaguda and if
so, the details thereof and the action taken thereon;
(c) whether the Government is aware that Gudari lacks railway
connectivity despite being an NAC (Notified Area Council) and Block
Headquarters in Rayagada district serving a large tribal and rural
population, remains without railway connectivity;
(d) whether the Government proposes to conduct a Preliminary
Engineering-cum-Traffic Survey or feasibility study of the alternative
alignment through Gudari; and
(e) if so, the details and timeline thereof and, if not, the reasons therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Gopalpur and Rayagada are already connected on Indian Railway
Network via Vizianagram Jn. However to provide a direct alternate
connectivity Final Location Survey (FLS) for Gopalpur – Rayagada New
Railway Line (250 Km) has been sanctioned. The Field Survey Work has
§ Page 1 of 5been taken up for preparation of Detailed Project Report (DPR) which
involves finalisation of techno-economically feasible alignment based on
study of alternate alignments, connectivity to economic nodes and
consultation with various stake holders such as State Government, Forest
Department, District Revenue officials, Industries/Mines etc.
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
sanctioning of projects is a continuous and dynamic process, exact
timelines cannot be fixed.
ODISHA
Railway Budget:
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Odisha is as under:
Period Outlay
2009-14 ₹ 838 Cr./year
2026-27 ₹ 10,928 Cr. (More than 13 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Odisha is as under:
Period New Track Average Commissioning of new tracks per
Commissioned year
2009-14 267 Km 53 Km
2014-26 2,236 Km 186 Km (More than 3.5 times)
Page 2 of 5Project Sanctioned:
As on 01.04.2026, 55 projects (19 New Lines and 36 Doubling/Multi-
tracking), of a total length of 4,256 Km, costing ₹ 81,739 crore, falling
fully/partly in Odisha, are sanctioned. The summary is as under:-
Category No of Total Length Total Exp
sanctioned Length Commissioned upto Mar'26
Projects NL/GC/DL till Mar'26 (₹ in Cr)
(in Km) (in Km)
New Lines 19 1,544 277 7,288
Doubling/Multi- 36 2,712 1,309 21,675
tracking
Total 55 4,256 1,586 28,963
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in
Odisha are as under:
S. Name of Project Cost
No. (In Crores of ₹)
1 Daitari-Banspani New Line and Jakhapura- 1,317
Haridaspur 3rd Line (179 Km)
2 Jharsuguda - Sardega New Line (53 Km) 1,598
3 Haridaspur-Paradeep New Line (82 Km) 2,397
4 Angul-Sukinda New Line (104 Km) 2,834
5 Champa-Jharsuguda 3rd Line (152 Km) 1,227
6 Sambalpur-Titlagarh Doubling (182 Km) 2,262
7 Rourkela-Jharsuguda 3rd Line (101 Km) 1,313
8 Banspani- Jakhapura Doubling (164 Km) 1,827
9 Sambalpur-Talcher Doubling (174 Km) 1,539
10 Raipur - Titlagarh Doubling (203 Km) 1,171
11 Jharsuguda-Sardega Doubling (50 Km) 3,200
Ongoing Projects:
Further, some of the main projects falling fully/partly in Odisha which have
been taken up are as under:
S. Name of Project Total Cost
No. (In Crores of ₹)
1 Junagarh-Nabarangpur New Line (116 Km) 2,865
Page 3 of 5S. Name of Project Total Cost
No. (In Crores of ₹)
2 Nabarangpur-Jeypore New Line (41 Km) 748
3 Jeypore-Malkangiri New Line (130 Km) 2,344
4 Malkangiri – Pandurangapuram New Line (174 3,592
Km)
5 Buramara-Chakulia New Line (60 Km) 1,459
6 Gunupur-Therubali New Line (74 Km) 1,166
7 Puri - Konark New Line (32 Km) 492
8 Badampahar-Kendujhargarh New Line (82 Km) 1,876
9 Bangriposi-Gorumahisani New Line (86 Km) 2,269
10 Bargarh Road-Nawapara Road New Line (138 2,622
Km)
11 Nergundi - Vizianagaram 3rd Line (385 Km) 4,963
12 Vizianagram-Titlagarh 3rd Line (265 Km) 6,996
13 Sambalpur - Jarapada 3rd and 4th line (127 Km) 3,574
14 Budhapank- Salegaon via Rajatgarh 3rd & 4th Line 3,035
(170 Km)
15 Kottavalasa-Koraput Doubling (189 Km) 3,580
16 Koraput-Singapur Road Doubling (165 Km) 2,462
17 Jagdalpur-Koraput Doubling (107 Km) 1,547
18 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
19 Jharsuguda-Sason 3rd and 4th line (35 Km) 1,113
20 Bondamunda-Ranchi Doubling (159 Km) 3,029
21 Narayangarh-Bhadrak 3rd line (153 Km) 3,425
22 Bhadrak-Nergundi 3rd Line (92 Km) 1,632
23 Cuttack-Nergundi 4th line along with Rail flyover 759
at Nergundi (16 Km)
24 Dangoaposi-Jaroli (Banspani) 3rd & 4th Line (43 1,638
Km)
25 Jarapada- Budhapank 3rd & 4th Line with flyover 929
at Talcher (101 Km)
26 Flyover from Bondamunda A Cabin to 135
Bondamunda Link B Cabin (5 Km)
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Page 4 of 5 Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****