GOVERNMENT OF INDIA
MINISTRY OF PORTS, SHIPPING AND WATERWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3328
ANSWERED ON 07.08.2026
INLAND WATERWAYS IN NORTH-EAST REGION
3328. SHRI BAIJAYANT PANDA:
Will the Minister of PORTS, SHIPPING AND WATERWAYS be pleased to state:
प(cid:419)न, पोत प(cid:464)रवहन और जलमाग (cid:91) म(cid:287)ं ी
(a) whether the Government has undertaken any measures to strengthen trade and
connectivity through inland waterways in the North-Eastern Region and if so, the
details thereof;
(b) the details of the cargo movement on National Waterway-2; and
(c) whether the Government has undertaken any infrastructure and investment
initiatives for the development of inland waterways in the North-Eastern Region and if
so, the details thereof?
ANSWER
MINISTER OF PORTS, SHIPPING AND WATERWAYS
(SHRI SARBANANDA SONOWAL)
(a) The measures undertaken by Inland Waterways Authority of India (IWAI), an
autonomous organization under the Ministry of Ports, Shipping and Waterways to
strengthen trade and connectivity through inland waterways in the North-Eastern
Region (NER) are :
Development and maintenance of National Waterway (NW) -2 (Brahmaputra
River ) and NW-16 (Barak River).
Development of permanent and floating terminals at Pandu, Jogighopa, Dhubri,
Neamati, Bogibeel, Karimganj and other locations.
Construction of floating terminals, community jetties and passenger facilities.
Fairway development and Conservancy Works in NW-2 & NW-16.
Installation of navigational aids and night navigation facilities on NW-2 and Day
Channel marks in NW-16.
Development of Inland Water Transport (IWT) infrastructure under the Central
Sector Scheme (CSS) in NER States.
Promotion of cargo movement through the Indo-Bangladesh Protocol (IBP)
Route and integration of waterways with road and rail networks.(b) Cargo transported on NW-2 includes coal, food grains, fertilizers, cement, fly ash,
POL products, stone aggregates, over-dimensional cargo (ODC) and other general
cargo. Cargo is also moved through the IBP Route connecting NER with
Haldia/Kolkata Ports.
The details of the cargo movement on NW-2 are given below:
Year 2021- 2022-23 2023-24 2024-25 2025-26
22
Cargo (in Million Ton) 0.43 0.63 0.59 0.90 1.29
(c) For the comprehensive development of IWT infrastructure in NER, various
projects have been undertaken by IWAI details of which are given at Annexure.Annexure
A. Major Completed Projects in NER:
Sl. Cost (₹
Project
No. Cr.)
1 Construction of High-Level Jetty at Pandu 43.89
2 Construction of Jetty and allied works for Dhubri Terminals 47
3 Development of IWT Terminal at MMLP Jogighopa 82.04
4 Construction of Cargo-cum-Tourist Terminal at Bogibeel 101
5 Floating Tourist Jetty at Bogibeel & Pandu 9.75
Renovation of Existing Shore Facilities at Badarpur and Karimganj
6 6.4
Terminal
7 Construction & Development of IWT Terminal at Sonamura 6.91
8 Customs & Immigration Building at Bogibeel 8.87
9 Customs & Immigration Building at Dhubri & Bogibeel 9.31
10 Construction of Boundary Wall at Jogighopa Terminal 12.33
11 Renovation of Heritage Building at Dibrugarh 6
Operational & Maintenance of other works including terminals and
12 508.3
fairway development (2014–2026)
13 Construction of Steel Gangway with Yoke System at Pandu 2.88
14 Approach Road to Pandu Jetty from NH-27 180
B. Major Ongoing Projects in NER :
Sl. Cost
Project Present Status
No. (₹ Cr.)
Fairway Development in NER
Work in progress
1 through DCI for NW-2 143
(Physical Progress: 67.70%)
(Bangladesh Border to Pandu)
Work in progress
[Physical Progress: 98.46 % for
2 Ship Repair Facility at Pandu 283.33 civil works and total project
completion 68% (Civil,
Mechanical and Electrical works)]Construction of Tourist Jetty at Work awarded to IPRCL on
3 Bishwanath Ghat & Cargo-cum- 158 Deposit Work basis. Tender
Cruise Terminal at Neamati Ghat under process.
Work awarded to IPRCL on
Development of RCoE at
4 207.65 Deposit Work basis.Tender under
Dibrugarh
process.
Construction of Building for
Work awarded to IPRCL on
Regional Office, MSDC, Guest
5 50 Deposit Work basis. Tender
House and Office Space for ITAT
under process.
at Fancy Bazar
Link Road connecting Pandu Work in progress
6 55
Terminal with Ship Repair Facility (Physical Progress: 27.00%)
Development & Maintenance of
Work in progress
7 Fairway in Bhanga–Badarpur 41.67
(Physical Progress: 67.70%)
(10.5 km) stretch through DCI
Construction of Berthing Pontoon
Work in progress
8 with Gangway at Badarpur 2.57
(Physical Progress: 72.50%)
Terminal
Construction of Crane Pontoon
Work in progress
9 with Gangway at Karimganj 4.42
(Physical Progress: 65.00%)
Terminal
Procurement of One Survey Work in progress
10 4.97
Vessel for NW-16 (Physical Progress: 60.00%)
Procurement of Three Amphibian
11 30 Tendering Stage
Dredgers for NW-16 & IBP Route
Procurement of Two (25×6 m)
Work in progress
12 Steel Pontoons for River 3.4
(Physical Progress: 90.00%)
Brahmaputra (NW-2)
Procurement of Two SDB
Work in progress
13 Vessels for River Brahmaputra 2.88
(Physical Progress: 55.00%)
(NW-2)
Project for Providing 10 Nos. RPL
Work in progress
14 Passenger Vessels for River 13.02
(Physical Progress: 55.00%)
Barak
Construction of All-weather
15 Approach Road from NH-15 to 0.43 DPR Stage
Bogibeel Terminal (DPR)
DPR for Construction of
16 Community Jetties on NW-30, 5.56 Tendering Stage
NW-32, NW-50, NW-57 & NW-95
*****