GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2934
TO BE ANSWERED ON 05.08.2026
INSTALLATION OF AUTOMATED TRAIN PROTECTION SYSTEM-KAVACH ON
TIRUNELVELI ROUTES
2934. SHRI ROBERT BRUCE C:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has undertaken/authorised the installation of
the automated train protection system 'Kavach' on the high-congestion
tracks connecting Chennai and the Tirunelveli junction and if so, the
details thereof;
(b) the details of total route in kilometers covered, funds
sanctioned/released and the physical progress achieved during each of
the last three years, year-wise;
(c) the details of reasons for the delay in rolling out this vital digital braking
safety infrastructure across these heavy-density Southern passenger
lines; and
(d) the further steps taken/proposed to be taken by the Government to fast-
track the deployment of Kavach on all major long-distance routes
serving Tirunelveli and the time-frame fixed therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d):
1. Kavach is an indigenously developed Automatic Train Protection (ATP)
system. Kavach is a highly technology intensive system, which
requires safety certification of highest order (SIL-4).
§ Page 1 of 42. Kavach aids the Loco Pilot in running of trains within specified speed
limits by automatic application of brakes in case Loco Pilot fails to do
so and also helps the trains to run safely during inclement weather.
3. The first field trials on the passenger trains were started in February
2016. Based on the experience gained and Independent Safety
Assessment of the system by Independent Safety Assessor (ISA), three
firms were approved in 2018-19, for supply of Kavach Ver 3.2.
4. Kavach was adopted as National ATP system in July, 2020.
5. Implementation of Kavach System involves following Key Activities:
a. Installation of Station Kavach at each and every station, block
section.
b. Installation of RFID Tags throughout the track length.
c. Installation of telecom Towers throughout the section.
d. Laying of Optical Fibre Cable along the track.
e. Provision of Loco Kavach on each and every Locomotive running on
Indian Railways.
6. Based on deployment of Kavach version 3.2 on 1,465 RKm on South
Central Railway and experience gained, further improvements were
made. Finally, Kavach specification version 4.0 was approved by RDSO
on 16.07.2024.
7. Kavach version 4.0 covers all the major features required for the
diverse railway network. This is a significant milestone in safety for
Indian Railways. Within a short period, IR has developed, tested and
started deploying Automatic Train Protection System.
8. Major improvement in Version 4.0 includes increased Location
Accuracy, Improved Information of Signal Aspects in bigger yards,
Station to Station Kavach interface on OFC and Direct Interface to
Page 2 of 4existing Electronic Interlocking System. With these improvements,
Kavach Ver.4.0. is planned for large scale deployment over Indian
Railways.
9. After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 2,633 Route Kilometres as on 31.07.26,
covering the high density Delhi- Mumbai and Delhi-Howrah routes as
below:
SN Section Progress (Route
Km)
(1) Delhi-Mumbai route: 1,423 Rkm
i Tilak Bridge - Junction cabin – Palwal – 1,327
Mathura –Kota-Nagda-Ratlam–Vadodara-
Virar section
ii Vadodara – Ahmedabad section 96
(2) Delhi – Howrah route: 1,210 Rkm
i. Chipyana - Tundla - Kanpur - Subedarganj 563
section
ii. Kanpur – Lucknow section 71
iii. Mirzapur - DDU (Excluding) section 64
iii. DDU(FOC)-Bhabua Road section 50
iv. Sasaram - Phesar section 43
v. Gaya -Sarmatarn- Nimiaghat section 159
vi. Chota Ambana - Bardhaman – Howrah 260
section
10. In addition, track side Kavach implementation work has been taken up
on 21,794 RKM covering all GQ,GD,HDN and identified sections of
Page 3 of 4Indian Railways. Also, Kavach work has been sanctioned in the
Chennai beach - Tirunelveli Junction section of about 650 Rkm.
11. The total Progress of key items of Kavach on Indian Railway sections
are as under:-
SN Item Progress
i Laying of Optical Fibre Cable 11,547 Km
ii Installation of Telecom 1,721 Nos.
Towers
iii Station Data Centre 1,009 station
iv Installation of Track side 7,726 RKm
equipment
v Provision of Kavach in Loco 6,290 Nos.
12. In addition, work for installation of Kavach in 7,190 Locomotives and
1,200 EMU/MEMU has been taken up.
13. Specialized training programmes on Kavach are being conducted at
centralized training institutes of Indian Railways to impart training to
all concerned officials. By now more than 94,000 technicians,
operators and engineers have been trained on Kavach technology. This
includes about 57,000 Loco Pilots & Assistant Loco Pilots. Courses
have been designed in collaboration with IRISET.
14. The funds utilized on Kavach works so far up to Jun'26 is Rs. 3,875
Crores. The allocation of funds during the year 2026-27 is Rs. 2,066
Crores. Kavach work is going at good pace in the entire country.
Requisite funds are made available as per the progress of works.
*****
Page 4 of 4