Executive Summary:
This document addresses a parliamentary query regarding railway infrastructure and services in the Barmer-Jaisalmer Lok Sabha Constituency. It details the introduction of new train services, ongoing railway projects, and station modernization efforts in Rajasthan, including Barmer, Balotra, and Jaisalmer districts. It also addresses the challenges in project completion and the allocation of funds. The information provided is current up to July 25, 2025, with financial data extending to March 2025 and fund allocations for the financial year 2025-26.
Key Points / Main Content:
Train Services and Connectivity:
* Four new train services were introduced for Barmer and two for Jaisalmer between 2021-22 and July 25, 2025.
* Barmer, Balotra, and Jaisalmer are currently served by 28, 24, and 14 train services respectively, connecting them to major cities like Jaipur, Delhi, Mumbai, and others.
* Barmer is directly connected to Jaipur by 4 pairs of trains and to Delhi by 3 pairs of trains. Jaisalmer is directly connected to Jaipur and Delhi by 2 pairs of trains each.
* Introduction of new trains, including Vande Bharat, is ongoing, contingent on traffic justification, feasibility, and resource availability.
Railway Projects in Rajasthan:
* As of April 1, 2025, 28 railway projects (13 New Lines, 5 Gauge Conversion, and 10 Doubling) are in various stages of planning and implementation in Rajasthan, with a total length of 3,409 km and a cost of Rs 43,918 crore.
* 1,238 km of track has been commissioned, and Rs. 18,955 crore has been spent up to March 2025.
* Two specific projects in Barmer, Balotra, and Jaisalmer districts have been sanctioned: a new line between Ramdevra-Pokhran and doubling of the Luni-Samdari-Bhildi section.
* Surveys for 55 projects (23 new lines and 32 doubling) have been sanctioned in the last three years and the current financial year in Rajasthan.
Station Development and Modernization:
* 1337 railway stations including 85 stations in the state of Rajasthan have been identified for development under the Amrit Bharat Station Scheme.
* Phase I works at 8 stations in Rajasthan (Bundi, Deshnoke, Fatehpur Shekhawati, Gogameri, Govind Garh, Mandal Garh, Mandawar Mahwa Road and Rajgarh) have been completed under the Amrit Bharat Station Scheme.
* Development works are underway at Barmer, Jaisalmer, and Balotra stations, including structural improvements, platform enhancements, and new facilities.
* Allocation of 5,257 crore has been made for the financial year 2025-26 under Plan Head53 for the 5 railway zones covering Rajasthan.
Challenges and Project Timelines:
* Project completion depends on factors such as land acquisition, forest clearances, utility shifting, and statutory approvals.
* Exact timelines for project completion and new project sanctioning cannot be fixed due to various dependencies.
Impact Analysis:
Passengers, Tourists, and Soldiers:
* Impact: Improved rail connectivity to major cities, enhanced station amenities, and potentially reduced travel difficulties.
* Action Required: None specified.
State Government:
* Impact: Responsible for quick land acquisition and support for railway projects within the state.
* Action Required: Expedite land acquisition and provide necessary clearances for railway projects.
Railway Authorities (Zonal Railways):
* Impact: Responsible for project execution, monitoring, and fund allocation.
* Action Required: Continue project implementation, address challenges affecting project timelines, and efficiently allocate funds.
Residents of Barmer, Balotra, and Jaisalmer Districts:
* Impact: Potential for improved local economy and connectivity due to railway infrastructure development.
* Action Required: None specified.
Key Entities Referenced
Barmer-Jaisalmer Lok Sabha Constituency: A parliamentary constituency in Rajasthan, India, which is the focus of the question regarding railway facilities.
SHRI UMMEDA RAM BENIWAL: Member of Parliament who raised the unstarred question in Lok Sabha.
Ashwini Vaishnaw: The Minister of Railways, Information Broadcasting and Electronics Information Technology, responsible for answering the parliamentary question.
Vande Bharat Trains: A type of express train that the government is contemplating introducing on certain routes.
Rajasthan: The State in India where several railway projects are being planned and implemented.
NITI Aayog: A policy think tank of the Government of India, involved in the appraisal of railway projects.
Ministry of Finance: The ministry involved in approving railway projects.
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the development and modernization of railway stations.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1723
TO BE ANSWERED ON 30.07.2025
INTRODUCTION OF NEW EXPRESS/SUPERFAST AND VANDE BHARAT
TRAINS
†1723. SHRI UMMEDA RAM BENIWAL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Barmer-Jaisalmer Lok Sabha Constituency is still lagging
behind in terms of rail facilities due to which the passengers, tourists and
soldiers face difficulties;
(b) if so, whether any scheme is being implemented for laying tracks,
gauge conversion, electrification, modernisation of station or introduction
of new trains to connect the district of Barmer, Balotra, Jaisalmer and the
other areas, if so, the details thereof;
(c) whether the Government is contemplating to introduce new
express/superfast or Vande Bharat trains in view of the long pending
demands of additional long distance trains from Jaisalmer-Jodhpur,
Barmer-Jodhpur to Jaipur, Delhi or South India; and
(d) if so, the details of the said schemes, works and proposed, sanctioned
Budget progress made so far and the time by which it is likely to be
materialised?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Railway network straddles across State/District boundaries,
accordingly trains are introduced, as per network requirement, across
such boundaries. During 2021-2022 to 2025-2026 (till 25.07.2025), Indian
Railways have introduced 04 train services for Barmer and 02 train
services catering Jaisalmer station.
Accordingly, at present, Barmer, Balotra and Jaisalmer stations are being
served by 28 train services, 24 train services and 14 train services
respectively, which are providing connectivity of Barmer and Jaisalmer to
various destinations like Jaipur, Bikaner, Delhi, Jammu Tawi, Ambala,
Kathgodam, Rishikesh, Jalandhar, Ahmedabad, Vadodara, Mumbai,Yesvantpur, Howrah, etc.
Presently, 04 pairs and 03 Pairs of trains directly connect Barmer to
Jaipur and Delhi respectively. Similarly, Jaisalmer is directly connected
to Jaipur and Delhi by 02 pairs of train services each. Besides,
introduction of new train services, including Vande Bharat train services
is an ongoing process on Indian Railways subject to traffic justification,
operational feasibility, resource availability, etc.
Railway projects are surveyed/ sanctioned/executed Zonal Railway wise
and not State-wise/UT wise/District wise as the Railway projects may
span across State/UT/District boundaries.
Railway projects are sanctioned on the basis of remunerativeness, traffic
projections, last mile connectivity, missing links and alternate routes,
augmentation of congested/saturated lines, demands raised by State
Governments, Central Ministries, Members of Parliament, other public
representatives, Railway’s own operational requirement, socio-economic
considerations etc. depending upon throwforward of ongoing projects and
overall availability of funds.
As on 01.04.2025, 28 Railway projects (13 New Lines, 05 Gauge
Conversion and 10 Doubling), of total length of 3,409 Km costing Rs
43,918 cr. falling fully/partly in the State of Rajasthan are at various
stages of planning and implementation, out of which 1,238 Km length has
been commissioned and an expenditure of Rs. 18,955 cr. has been
incurred upto March 2025. The status of work is summarized as under:-
Plan Head No. of Total Length Expenditure upto
projects Length Commissioned March 2024 (Rs. in
(in Km) (in Km) Cr)
New Lines 13 981 196 5769
Gauge 5 1252 788 6829
Conversion
Doubling/ 10 1176 254 6357
Multitracking
Total 28 3,409 1,238 18,955
These 2 important projects falling fully/partly in the district of Barmer,
Balotra and Jaisalmer have been sanctioned:S.No. Project Cost (in cr.)
1. New Line between Ramdevra-Pokhran via 189
Bhairav Gufa and Kailash Tekri (13 Km)
2. Doubling of Luni-Samdari-Bhildi section 3086
The Electrification works of the above projects are also in progress.
Survey of total 55 projects (23 new line and 32 doubling) of total length
5,497 Km falling fully/partly in the State of Rajasthan including districts of
Barmer, Balotra and Jaisalmer have been sanctioned during last three
years (2022-23, 2023-24, 2024-25 and current Financial Year 2025-26).
The sanctioning of the project requires consultation with various stake-
holders including State Governments and necessary approvals viz.
appraisal of NITI Aayog, Ministry of Finance etc. As sanctioning of project
is a continuous and dynamic process, exact timelines cannot be fixed.
Completion of Railway project/s depends on various factors like quick
land acquisition by State Government, forest clearance by officials of
forest department, shifting of infringing utilities, statutory clearances
from various authorities, geological and topographical conditions of area,
law and order situation in the area of project/s site, number of working
months in a year for particular project site etc. All these factors affect the
completion time and cost of the project/s.
Development / Redevelopment / Upgradation / Modernisation of stations
on Indian Railways is a continuous and ongoing process and works in this
regard are undertaken as per requirement, subject to inter-se priority and
availability of funds. The priority for development / redevelopment /
upgradation / modernisation of stations is accorded to higher category of
station over lower category of station while sanctioning and executing
the works.
Ministry of Railways has launched Amrit Bharat Station Scheme for
development of stations on a continuous basis with a long-term approach.
It involves preparation of master plans and their implementation in
phases to improve the amenities at the stations like improvement of
station access, circulating areas, waiting halls, toilets, lift/escalators asnecessary, platform surfacing and cover over platform, cleanliness, free
Wi-Fi, kiosks for local products through schemes like ‘One Station One
Product’, better passenger information systems, executive lounges,
nominated spaces for business meetings, landscaping, etc. keeping in
view the necessity at each station.
The scheme also envisages improvement of building, integrating the
station with both sides of the city, multimodal integration, amenities for
Divyangjans, sustainable and environment friendly solutions, provision of
ballastless tracks, etc. as per necessity, phasing and feasibility and
creation of city centre at the station in the long term.
So far, 1337 railway stations including 85 stations in the state of
Rajasthan have been identified for development under Amrit Bharat
Station Scheme. The names of stations identified for development under
this scheme in the state of Rajasthan are as following:
State No. of Names of stations
Stations
Rajasthan 85 Abu Road, Ajmer, Alwar, Anupgarh, AsalpurJobner,
Balotra, Bandikui, Baran, Barmer, Bayana, Beawar,
Bharatpur, Bhawani Mandi, Bhilwara, Bijainagar,
Bikaner, Bundi, Chanderiya, Chhabra Gugor,
Chittorgarh Jn., Churu, Dakaniya Talav, Dausa,
Deeg, Degana, Deshnoke, Dholpur, Didwana,
Dungarpur, Falna, Fatehnagar, Fatehpur
Shekhawati, Gandhinagar Jaipur, Gangapur City,
Gogameri, Gotan, Govind Garh, Hanumangarh,
Hindaun City, Jaipur Jn, Jaisalmer, Jalor, Jawai
Bandh, Jhalawar City, Jhunjhunu, Jodhpur,
Kapasan, Khairthal, Kherli, Kota Jn, Lalgarh Jn,
Mandal Garh, Mandawar Mahwa Road, Marwar
Bhinmal, Marwar Jn, Mavli Jn, Merta Road Jn,
Nagaur, Naraina, Nim ka Thana, Nokha, Pali
Marwar, Phalodi Jn, Phulera Jn, Pindwara, Rai
singhnagar, Rajgarh, Ramdevra, Ramganj Mandi
Jn, Ranapratapnagar, Rani, Ratangarh Jn, Ren,
Ringas, Sadulpur, Sanganer, Sawai Madhopur,Shri Mahaveerji, Sikar, Sojat Road, Somesar, Sri
ganganagar, Sujangarh, Suratgarh, Udaipur City
Development works at railway stations under Amrit Bharat Station
Scheme in the state of Rajasthan have been taken up at a good pace. Till
now, phase – I works of 08 stations (Bundi, Deshnoke, Fatehpur
Shekhawati, Gogameri, Govind Garh, Mandal Garh, Mandawar Mahwa
Road and Rajgarh) in the state of Rajasthan have been completed under
this scheme. The works at other stations have also been taken up at good
pace and progress of some of the above stations is as given below:
● At Barmer station, the structural work of station building, waiting
hall, toilet blocks, platform raising, platform shelter and circulating
area have been completed. The finishing works of station building,
improvement of platform no. 1, construction of new Foot Over
Bridge and lift have been taken up.
● At Jaisalmer station, the works of station building including
departure and arrival block, air concourse, Foot Over Bridges,
platform shelter, improvement to platform surfacing, sub station
building and sewage treatment plant have been completed. The
works of development of circulating area, lift and escalator have
been taken up.
● At Balotra station, the structural work of station building, waiting
hall, toilet blocks, platform raising and platform shelter have been
completed. The works of improvement to circulating area,
construction of new Foot Over Bridge and lift have been taken up.
Development / Upgradation / Modernization of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation of funds for development
and maintenance of stations are maintained Zonal Railway-wise and not
work-wise or station-wise or state-wise. The state of Rajasthan is covered
under 05 (five) Railway zones, namely Northern Railway, North Central
Railway, North Western Railway, Western Railway and West Central
Railway. For these zones, allocation of ₹ 5,257 crore has been made forthe financial year 2025-26 under Plan Head-53 and expenditure (up to
June, 2025) of ₹ 1,024 crore has been incurred so far.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger movement,
speed restrictions due to works carried out in close proximity of tracks
and high voltage power lines, etc. and these factors affect the completion
time. Therefore, no time frame can be indicated at this stage.
*****