GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2828
TO BE ANSWERED ON 05.08.2026
KATGHORA–DONGARGARH NEW RAIL LINE PROJECT
†2828. SHRI SANTOSH PANDEY:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Katghora-Dongargarh new railway line project in
Chhattisgarh is currently pending at any level and if so, the details
thereof;
(b) whether this project is pending at Railway Board or any other level and
if so, the reasons therefor;
(c) the details of approvals, sanctions and clearances yet to be
obtained/pending for the implementation of the project;
(d) whether the Government has received any proposal from Chhattisgarh
Government regarding amendment in alignment or other aspects of the
project and if so, the action taken thereon;
(e) the current estimated cost of the project and whether any amendment
has been made to it since its initial approval; and
(f) the likely timeline for starting the construction work of the project and
granting the remaining approvals?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Katghora – Dongargarh New Broad Gauge Electrified Rail Line
Project (294Km.) has been sanctioned on debt (75%) - equity (25%) basis at
a cost of ₹ 5,950 Cr. The project is being executed by Chhattisgarh
Railway Corporation Limited (CRCL), a Joint Venture of Govt. of
Chhattisgarh (51%) and Ministry of Railways (49%).
Page 1 of 4
§There was issue of the alignment of the project earlier, therefore, the
project could not start. Now the issue has been resolved. In the recent
meeting between Hon’ble Chief Minister/Chhattisgarh and Minister of
Railways, it has been decided to take up the work as per the original
approved alignment.
CHHATTISGARH
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Chhattisgarh is as under:
Period Outlay
2009-2014 ₹311 Cr./year
2026-2027 ₹7,470 Cr. (approx. 24 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Chhattisgarh is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 32 Km 6.4 Km per year
2014-26 1,311 Km 109.29 Km per year (17 times)
Projects Sanctioned:
As on 01.04.2026, 36 projects (8 New Lines and 28 Doubling), of total
length of 2,398 Km, costing ₹48,202 crore falling fully/partly in the State of
Chhattisgarh are Sanctioned. The summary is as under:-
Page 2 of 4Category No. of Total Length Commissioned Total Exp upto
projects Length till March, 2026 (in March 2026
(in km) Km) (₹in cr.)
NL 8 887 262 7,535
DL 28 1,512 889 11,298
TOTAL 36 2,398 1,151 18,833
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
state of Chhattisgarh are as under:
S.No. Name of Project Cost (₹in
cr.)
1 Kharsia-Korichhapar New Line (43 Km) 851
2 Bilaspur-Urkura 3rd line (110 Km) 365
3 Salka Road-Khongsara doubling (26 Km) 181
4 Durg-Rajnandgaon Doubling (31 Km) 250
5 Khodri-Anuppur Doubling with flyover at Bilaspur 792
(72 Km)
6 Champa-Jharsuguda 3rd Line (152 Km) 1,227
7 Pendra Road-Annupur 3rd Line (50 Km) 394
8 Raipur-Titlagarh Doubling (203 Km) 1,171
9 Dallirajahra-Rowghat (95 Km) 1,628
Ongoing Projects:
Some of the major projects falling fully/partly in the State of Chhattisgarh
which have been taken up are as under:
S.N Name of Project Cost
(₹in cr.)
1 Kharsia-Dharamjaygarh New Line (122 Km) 3,407
Page 3 of 42 Gevra Road-Pendra Road New Line (135 Km) 3,724
3 Dharamjaigarh-Korba New Line (63 Km) 1,686
4 Chirimiri-Nagpur Halt New Line (17 Km) 670
5 Sardega-Bhalumunda New Line (37 Km) 1,282
6 Kharsia-Parmalkasa 5th and 6th line (278 Km) 7,854
7 Rowghat-Jagdalpur New Line (140 Km) 3,513
8 Kirandul-Jadgalpur Doubling (150 km) 1,780
9 Jagdalpur-Koraput Doubling (107 Km) 1,547
10 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
11 Gevra Rd-Pendra Rd Doubling (135 Km) 3,475
12 Rajnandgaon-Nagpur 3rd line (228 Km) 3,545
13 Raipur-Dhamtari&Abhanpur-Rajim gauge 3,250
conversion (67.20 Km)
14 Boridand-Ambikapur Doubling (80 Km) 1,577
15 Durg-Rajnandgaon 4th line (31 Km) 464
16 Gondia-Dongargarh 4th line (84 Km) 2,223
17 Baikunth-Urkura 4th line (26 Km) 426
18 Champa-Korba 3rd Line (42 Km) 755
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****