GOVERNMENT OF INDIA
DEPARTMENT OF ATOMIC ENERGY
RAJYA SABHA
UNSTARRED QUESTION NO-3046
ANSWERED ON 19/03/2026
LCOE VIS-A-VIS NUCLEAR CAPACITY EXPANSION
3046. SHRI G. C. CHANDRASHEKHAR
Will the PRIME MINISTER be pleased to state:-
a) whether Government has analysed the Levelised Cost of Electricity (LCOE) of nuclear
power vis-à-vis solar, wind and thermal power, including capital cost, fuel cycle and
waste management components; and
b) the manner in which these cost comparisons would form future nuclear capacity
expansion decisions?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a) & (b) Such comparison would be improper as operating life of the all technologies are
substantially different. While solar and wind units have life of about 25 years or so and
thermal has a life of about 30-40 years, nuclear power plant has life of about 60 years.
Thus any attempted comparison of LCOE would not be appropriate.
Therefore, the tariff for the nuclear power plants is not determined on the basis of LCOE
method, but is determined based on the principle of multiyear tariff framework, on basis
of cost plus approach.
Further, the off-take of the nuclear power plant is not through the process of competitive
bidding, it is through the process of allotment to the states/union territories in the region,
as decided by the Ministry of Power, based on a laid down policy.
*****