Executive Summary:
This document provides the Ministry of Railways' response to questions regarding railway projects and infrastructure development in the Jaunpur district and the Purvanchal region of Uttar Pradesh. It details the status of level crossing replacements with ROBs/RUBs, new train services, line surveys, pending projects, electrification, and station upgrades. The information reflects data up to April 1, 2025, with updates on progress through June and July 2025.
Key Points / Main Content:
Level Crossings and Over/Under Bridges:
* 14 ROBs/RUBs are sanctioned in lieu of level crossings in Jaunpur district at a cost of ₹409 crore; projects are in various planning and execution stages.
* Many ROB/RUB projects are executed on a dual-entity basis, with Railway handling the railway portion and the State agency managing approaches.
* As of April 1, 2025, 4,402 ROBs/RUBs are sanctioned across Indian Railways at a cost of ₹1,00,860 crore, including 736 in Uttar Pradesh.
Electrification:
* Approximately 99% of the Broad Gauge network on Indian Railways has been electrified.
* The entire existing Broad Gauge railway network in Uttar Pradesh, including Jaunpur District, has been electrified.
New Lines, Doubling, and Gauge Conversion:
* During 2022-2026, 111 surveys (33 New Line, 76 Doubling, and 2 Gauge Conversion) totaling 6271 km have been sanctioned in Uttar Pradesh.
* As of April 1, 2025, 49 Railway projects (10 New Line, 2 Gauge Conversion, and 37 Doubling) of 3,808 Km costing ₹62,360 crore are sanctioned in Uttar Pradesh, with ₹30,611 crore spent up to March 2025 and 1,323 Km commissioned.
Budget Allocation:
* The budget allocation for infrastructure and safety works in Uttar Pradesh is ₹19,858 crore for 2025-26, nearly 18 times the 2009-14 allocation.
Train Services:
* Between 2023-24 and July 31, 2025, 22 new train services were introduced, including 14 Vande Bharat trains serving stations like Gorakhpur, Varanasi, and Ayodhya.
Station Redevelopment (Amrit Bharat Station Scheme):
* 1337 stations, including 157 in Uttar Pradesh, have been identified for development under the Amrit Bharat Station Scheme.
* Phase-I works at 20 stations in Uttar Pradesh have been completed under this scheme.
* Development/redevelopment/upgradation/modernisation of stations is a continuous and ongoing process.
Impact Analysis:
Stakeholders: Railway Passengers
Impact: Enhanced connectivity, improved amenities at stations, and increased safety due to upgraded infrastructure.
Action Required: Utilize new train services and provide feedback on station improvements.
Stakeholders: Residents of Jaunpur District and Purvanchal Region
Impact: Better transportation infrastructure, reduced traffic congestion at level crossings, and increased economic activity due to improved connectivity.
Action Required: Monitor progress of infrastructure projects and engage with local authorities regarding any concerns.
Stakeholders: Indian Railways and Government of Uttar Pradesh
Impact: Responsibility for executing and overseeing railway projects, managing budgets, and ensuring timely completion of works.
Action Required: Coordinate on land acquisition, clearances, and project execution; allocate funds effectively; and monitor project progress.
Key Entities Referenced
Jaunpur District, Uttar Pradesh: A district in Uttar Pradesh, India, which is the focus of the railway projects and level crossing related queries in the document.
Purvanchal Region, Uttar Pradesh: A region in Uttar Pradesh, India, mentioned in the context of new train introductions, line surveys, and railway projects.
Road Over Bridges (ROBs): Infrastructure projects to replace level crossings, aimed at improving safety and traffic flow, frequently mentioned in the context of Jaunpur district.
Road Under Bridges (RUBs): Infrastructure projects similar to ROBs, also intended to replace level crossings, and frequently mentioned in Jaunpur district.
Indian Railways: The primary organization responsible for the railway infrastructure projects, train operations, and policies discussed in the document.
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the development and modernization of railway stations across India.
Ashwini Vaishnaw: The Minister of Railways, Information Broadcasting and Electronics Information Technology, who provided the answers to the parliamentary questions.
Vande Bharat Express: A type of express train service being introduced by Indian Railways to improve connectivity, with several routes mentioned in the document.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO.2913
TO BE ANSWERED ON 06.08.2025
LEVEL CROSSINGS IN JAUNPUR DISTRICT
2913. ADV PRIYA SAROJ:
Will the Minister of RAILWAYS be pleased to state:
(a) the total number of level crossings in Jaunpur district where
Road Over Bridges (ROBs) or Road Under Bridges (RUBs) have
been sanctioned but construction work has not yet
commenced;
(b) the details of any new express or passenger trains that have
been introduced or are proposed to be introduced to connect
the Purvanchal region of Uttar Pradesh with major cities and
commercial hubs across the Country during the last three
years;
(c) the number of new line surveys and projects currently in
progress or under planning in Purvanchal region of Uttar
Pradesh along with their total length and projected cost;
(d) the details of all railway projects including new lines, doubling,
electrification, station upgradation and overbridges that are
currently pending beyond their original scheduled completion
date in Jaunpur District of Uttar Pradesh; and
(e) the reasons for delay in these projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) : 14 Nos. ROBs/RUBs are sanctioned in lieu of LCs at the
cost of ₹ 409 crore in Jaunpur district which are at various stages
of planning and execution. The details are as under:-SN Location ROB/ Cost Remarks
RUB/ (in ₹
FOB Cr.)
1 LC No. 30 near ROB 37 This work is being executed on dual
Jalalganj entity basis i.e., Railway portion by
railway and approaches by State agency.
Contract has been awarded.
2 LC No. 42A on ROB 37 This work is being executed on dual
Jaunpur- entity basis i.e., Railway portion by
railway and approaches by State agency.
Zafrabad section
The work of preparation of GAD has been
taken up.
3 LC No. 64-B near ROB 37 This work is being executed on dual
Badsahpur entity basis i.e., Railway portion by
railway and approaches by State agency.
The work of preparation of GAD has been
taken up.
4 LC No. 43 on ROB 38 This work is being executed on dual
Jaunpur- entity basis i.e., Railway portion by
Zafrabad section railway and approaches by State agency.
GAD has been approved.
5 LC No. 23/C ROB 46 This work is being executed on dual
Srikrishna Nagar entity basis i.e., Railway portion by
railway and approaches by State agency.
GAD has been approved. Contract has
been awarded. Geo-technical
investigation has been completed.
6 LC No. 9 at ROB 70 Contract has been awarded.
Jaunpur city
7 LC No. 38 A on ROB 68 The work of preparation of GAD has been
Jaunpur- taken up.
Zafrabad
8 LC No. 57A on RUB 6 GAD has been approved. Detailed
Zafrabad- Estimate has been sanctioned.
Ayodhya section
9 LC No. 44/C on RUB 6 GAD has been approved. Detailed
Zafrabad- Estimate has been sanctioned.
Ayodhya section
10 LC No. 61 on RUB 6 The work of preparation of GAD has beenZafrabad- taken up.
Ayodhya section
11 LC No. 51 on ROB 40.00 This LC is situated on National Highway.
Pandit Deen This work has been taken up by
Dayal Upadhyaya MoRTH/NHAI on single entity basis.
Junction -
Pratapgarh
Junction -
Lucknow
12 LC No. 11 on RUB 6 GAD has been approved. Detailed
Aunrihar Estimate has been sanctioned. Contract
Junction- has been awarded. Box has been casted.
Jaunpur
Junction
13 LC No. 24 on RUB 6 The work of preparation of GAD has been
Aunrihar taken up.
Junction-
Jaunpur
Junction
14 LC No. 40 on RUB 6 The work of preparation of GAD has been
Aunrihar taken up.
Junction-
Jaunpur
Junction
Sanctioning of works of Road over Bridge (ROB)/Road Under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and
dynamic process of Indian Railways. Such works are prioritised and
taken up on the basis of its impact on safety in train operations,
mobility of trains & impact for road users and feasibility etc.
Nos. of ROBs/ RUBs constructed on Indian Railways during the
period 2004-14 vis a vis 2014-25 (June’25) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.2014-25 (June’25) 13,426 Nos. (including 1649 Nos. in
the State of Uttar Pradesh)
As on 01.04.2025, 4,402 Nos. ROBs/ RUBs are sanctioned at
the cost of ₹ 1,00,860 Cr on Indian Railways including 736 Nos.
Road Over Bridge (ROB)/Road Under Bridge (RUB) at the cost of
₹14,022 crore in the State of Uttar Pradesh, which are at various
stages of planning and execution.
Electrification:
Electrification of railway network on Indian Railways has been
taken up in mission mode. So far, about 99% of Broad Gauge (BG)
network has been electrified. The electrification in remaining
network has been taken up. Electrification carried out during 2014-
25 and before 2014 is as under:
Period Route Kilometer
Before 2004 (about 60 years) 21,801
2014-25 46,900
In Uttar Pradesh, entire existing Broad Gauge railway network
has been electrified including Jaunpur District. All new
line/multitracking projects are being sanctioned and constructed
with electrification.
New Line/ Doubling/ Gauge conversion projects:
During the last three years i.e. 2022-23, 2023-24, 2024-25 and
the current FY 2025-26, 111 surveys (33 New Line, 76 Doubling and
2 Gauge Conversion) of a total length of 6271 km have been
sanctioned falling fully/partly in the state of Uttar Pradesh including
Purvanchal region.As on 01.04.2025, 49 Railway projects (10 New Line, 02 Gauge
Conversion and 37 Doubling), of total length of 3,808 Km costing
₹62,360 crore falling fully/partly in the State of Uttar Pradesh
including Purvanchal region and Jaunpur district are sanctioned,
out of which 1,323 Km length has been commissioned and an
expenditure of ₹30,611 crore has been incurred upto March 2025.
The status of work is summarized as under:-
Plan Head No. of Total Length Expenditure
projects Length Commission upto March
(in Km) ed (in Km) 2025
(₹in Cr)
New Lines 10 1227 340 10517
Gauge
2 67 0 281
Conversion
Doubling /
37 2513 983 19813
Multitracking
Total 49 3808 1323 30611
Budget allocation for Infrastructure projects and safety works,
falling fully/ partly in Uttar Pradesh including Purvanchal region and
Jaunpur district is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2025-26 ₹ 19,858 Cr. (nearly 18 times)
Details of some of the recently completed projects, falling
fully/partly in the State of Uttar Pradesh including Purvanchal and
Jaunpur district, are as under:
S.No Name of Project Cost (cr.)
1 Agra-Etawah New Line (110 Km) 4272 Guna-Etawah New Line (348 Km) 683
3 Etawah-Mainpuri New Line (58 Km) 313
4 Ghazipur city-Tarighat New Line (17 Km) 1766
5 Kanpur-Bareilly Gauge Conversion (545 Km) 1790
6 Bareilly-Tanakpur Gauge Conversion (102 Km) 313
7 Gonda-Bahraich Gauge Conversion (60 Km) 318
8 Pilibhit-Shahjahanpur Gauge Conversion (83 589
Km)
9 Indara-Dohrighat Gauge Conversion (34 Km) 213
10 Lucknow-Pilibhit Gauge Conversion (263 Km) 1634
11 Utretia-Zafrabad Doubling (148 Km) 890
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Meerut-Muzaffarnagar Doubling (55 Km) 430
14 Muzaffarnagar – Tapri Doubling (52 Km) 525
15 Mathura-Palwal 4th line (80 Km) 669
16 Utretia-Raibareilly Doubling (66 Km) 662
17 Raibareilly-Amethi Doubling (60 Km) 668
18 Bhimsen—Jhansi Doubling (206 Km) 2620
19 Ballia-Gazipur city Doubling (65 Km) 650
20 Aunrihar-Jaunpur Doubling (60 Km) 405
21 Barabanki-Akbarpur Doubling (161 Km) 1700
22 Rosa-Burhwal Doubling (181 Km) 2094
23 Jaunpur- Akbarpur Doubling (77 Km) 676
24 Ramna-Singrauli Doubling (160 Km) 2436
25 Janghai- Phaphamau Doubling (47 Km) 414
26 Varanasi-Allahabad Doubling (120 Km) 2018Some of the main projects, falling fully/partly in the State of
Uttar Pradesh including Purvanchal and Jaunpur district, which
have been taken up, are as under:
S. No Name of Project Cost (Cr)
1 Sahjanwa-Dohrighat New Line (81 Km) 1320
2 Bahraich & Khalilabad new Line (240 Km) 4940
3 Unchhar-Amethi Doubling (66 Km) 1229
4 Mughalsarai-Allahabad, 3rd line (150 Km) 2649
5 Billi- Chunar Doubling (102 Km) 1424
6 Chhapra-Ballia Doubling (65 km) 937
7 Varanasi- Allahabad Doubling (120 Km) 2018
8 Domingarh- Kusumhi - 3rd line (21km) 508
9 Burhwal Gonda 3rd line (62 Km) 800
10 Phephna-Indara, Mau-Shahganj Doubling (150 1529
Km)
11 Bhatni-Aurnihar doubling (125 Kms) 2529
12 Gorakhpur- Valmikinagar Doubling (96 Km) 1121
13 Janghai- Amethi Doubling (87 Km) 719
14 Janghai- Phaphamau Doubling (47 Km) 414
Trains:
As the Railway network straddles across State/regional
boundaries, trains are introduced as per network requirement
across such boundaries. However, in its constant endeavour to
provide/improve connectivity for the passengers, Indian Railways,
between the period 2023-24 and 2025-26 (till 31.07.2025) have, on
originating/terminating basis, introduced the following 22 train
services including 14 Vande Bharat train services serving the
stations like Gorakhpur, Varanasi, Ayodhya, Mau etc.
1. 26501/26502 Patliputra-Gorakhpur Vande Bharat Express
2. 20175/20176 Banaras-Agra Cantt. Vande Bharat Express
3. 22499/22500 Deoghar-Varanasi Vande Bharat Express4. 20887/20888 Ranchi-Varanasi Vande Bharat Express
5. 22425/22426 Ayodhya Cantt-Anand Vihar (T) Vande Bharat
Express
6. 22415/22416 Varanasi-New Delhi Vande Bharat Express
7. 22549/22550 Gorakhpur-Prayagraj Vande Bharat Express
8. 18629/18630 Ranchi-Gorakhpur Express
9. 16367/16368 Kanniyakumari-Banaras Kashi Tamil Sangmam
Express
10. 15181/15182 Mau-Lokmanya Tilak (T) Express
11. 12945/12946 Veraval-Banaras Express
Moreover, it has also been decided to introduce 12527/12528
Azamgarh-Anand Vihar (T) Express.
Station redevelopment:
Ministry of Railways has launched Amrit Bharat Station
Scheme for development of stations on a continuous basis with a
long-term approach. It involves preparation of master plans and
their implementation in phases to improve the amenities at the
stations like improvement of station access, circulating areas,
waiting halls, toilets, lift/escalators as necessary, platform
surfacing and cover over platform, cleanliness, free Wi-Fi, kiosks
for local products through schemes like ‘One Station One Product’,
better passenger information systems, executive lounges,
nominated spaces for business meetings, landscaping, etc.
keeping in view the necessity at each station.
The scheme also envisages improvement of building,
integrating the station with both sides of the city, multimodal
integration, amenities for Divyangjans, sustainable and
environment friendly solutions, provision of ballastless tracks, etc.as per necessity, phasing and feasibility and creation of city centre
at the station in the long term.
So far, 1337 stations, including 157 stations located in the
state of Uttar Pradesh, have been identified for development under
this scheme. Development works at railway stations across the
country under Amrit Bharat Station Scheme have been taken up at a
good pace. Till now, phase-I works of 20 stations (Ayodhya Dham,
Balrampur, Bareilly City, Bijnor, Fatehabad, Gola Gokarnath,
Gomtinagar, Govardhan, Govindpuri, Hathras City, Idgah Agra Jn,
Izzatnagar, Mailani, Pokhrayan, Ramghat Halt, Saharanpur Jn.,
Siddharth nagar, Suraimanpur, Swaminarayan Chappia, Ujhani) in
the state of Uttar Pradesh have been completed under this scheme.
The works at other stations have also been taken up at good pace
and progress of some of above stations is as given below:
At Shahganj Junction station, the works of 6 m Foot Over Bridge
and boundary wall in circulating area have been taken up.
At Jaunpur Junction station, structural work of new station
building, platform shelter and toilet block have been taken up.
At Jaunpur City station, work of platform shelters have been
taken up.
At Mariahu station, the works of station building, circulating
area, toilet, waiting hall, lighting and Divyangjan facilities have
been taken up.
At Badshahpur station, the works of station building, platform
shelter, circulating area, toilet, waiting hall, lighting and
Divyangjan facilities have been taken up.
At Sri Krishna Nagar station, the works of station building,
platform shelter, circulating area, toilet, waiting hall, lighting
and Divyangjan facilities have been taken up.Further development / redevelopment / upgradation /
modernisation of stations on Indian Railways is a continuous and
ongoing process and works in this regard are undertaken as per
requirement, subject to inter-se priority and availability of funds.
The priority for development / redevelopment / upgradation /
modernisation of stations is accorded to higher category of station
over lower category of station while sanctioning and executing the
works.
Development / upgradation of railway stations is complex in
nature involving safety of passengers & trains and requires various
statutory clearances such as fire clearance, heritage, tree cutting,
airport clearance etc. The progress also gets affected due to
brownfield related challenges such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipe lines,
power/signal cables, etc.), infringements, operation of trains
without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage
power lines, etc. and these factors affect the completion time.
Therefore, no time frame can be indicated at this stage.
Development / upgradation / modernisation of stations
including under Amrit Bharat Station Scheme is generally funded
under Plan Head-53 ‘Customer Amenities’. The details of allocation
and expenditure under Plan Head-53 are maintained Zonal Railway-
wise and not work-wise, or station wise or state-wise. The state of
Uttar Pradesh is covered under the jurisdiction of five railway
zones, namely East Central Railway, North Central Railway,
Northern Railway, North Eastern Railway, and West Central
Railway. For these zones, an allocation of ₹ 4,357 crore has been
made for the financial year 2025-26, out of which an expenditure(up to June, 2025) of ₹ 877 crore has been incurred so far.
Completion of Railway project/s including ROBs/RUBs depends
on various factors like quick land acquisition by State Government,
forest clearance by officials of forest department, shifting of
infringing utilities, statutory clearances from various authorities,
geological and topographical conditions of area, law and order
situation in the area of project/s site, number of working months in
a year for particular project site etc. All these factors affect the
completion time and cost of the project/s.
*****