GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO - 3772
ANSWERED ON – 25/03/2026
MAINTENANCE AND QUALITY AUDITS OF NATIONAL HIGHWAY
3772 SHRI A. D. SINGH:
Will the Minister of Road Transport and Highways be pleased to state:
(a) whether regular audits are conducted to ensure the quality of highways and bridges;
(b) the details of any deficieny detected and actions taken against defaulting contractors; and
(c) whether Government propose to introduce new technologies such as drones or sensors for
quality monitoring?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The Government in the Ministry of Road Transport and Highways is primarily
responsible for development and maintenance of National Highways (NHs). All efforts are made
to ensure that the NHs and bridges are constructed as per stipulated quality standards specified in
the Indian Roads Congress (IRC) specifications and codes. To ensure that highway construction
adheres to stipulated quality standards, Consultants (Authority’s Engineer/ Independent
Engineers- AE/IE) are appointed by the executing agencies for day-to-day supervision of works
at site. Officials of executing agencies undertake inspections from time to time and ensure
adherence of conformity of quality of the work done by the Concessionaires/Contractors with
stipulated requirements.
The Government has additionally taken the following initiatives for improvement of
quality control systems in implementation of NHs works: -
i. Adoption of Automated & Intelligent /Machine-aided Construction (AI-MC) in
NH projects;
ii. Assessment of road conditions through Network Survey Vehicle (NSV) mandated
for all NHs and Expressway works at the time of completion and every six months thereafter,which is monitored through electronic platform. NSV system for road condition assessment has
been revamped using analytics for enforcement of contractual provisions during Operation and
Maintenance (O&M) through dedicated central cell;
iii. Operationalization of a centralized system called NHAI One App for Monitoring
and rectification of highway defects which enables geo-tagging of defects along with
photographs;
iv. Analysis of High-Resolution Imagery collected from Drone Surveys in Drone
Analytics Monitoring System (DAMS) integrated with Artificial Intelligence/ Machine Learning
algorithms for periodic evaluation of progress and quality of ongoing NHs works from time to
time;
v. Deployment of Mobile Quality Control Vans (MQCVs) equipped with Non-
Destructive Testing Equipment on pilot basis in four States, namely in Gujarat, Rajasthan,
Odisha and Karnataka, for diagnostic assessments of overall health and quality of works from
time to time during project implementation phases;
vi. Deployment of Third Party Quality Auditors for independent quality audits of
NH works on a case-to-case basis.
Deficiencies observed, if any, are brought to the notice of the Concessionaires/
Contractors for taking up necessary corrective/ remedial actions as stipulated in technical
schedules of the Contract/ Concession Agreement or within a reasonable period as decided by
the executing agency / AE/ IE. Actions against defaulting agencies are taken up as per the
provisions of the Contract/ Concession agreement in cases of deficiencies/ damages, such as
termination of contract agreement, levying of penalties/ liquidated damages, debarment/
blacklisting, declaring as non-performers etc.
As per information provided by the executing agencies of the NHs, major deficiencies in
NH stretches in the last three years and current year have been reported for 67 projects /
stretches. State / Union Territory (UT) – wise details of major deficiencies in NH stretches in the
last three years and current year along with status of its rectification works and action taken
against contractors, concessionaires, consultants etc. are annexed.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (c) OF RAJYA SABHA
UNSTARRED QUESTION NO. 3772 ANSWERED ON 25.03.2026 ASKED BY SHRI A. D.
SINGH REGARDING MAINTENANCE AND QUALITY AUDITS OF NATIONAL
HIGHWAY
State / Union Territory (UT) – wise details of major deficiencies in NH stretches in the last three
years and current year along with status of its rectification works and action taken against
contractors, concessionaires, consultants etc.:
S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Permanent solution to Slip
Zones on Papu – Yupia – Hoj
– Potin section of NH-713A &
NH-13 at Km 31.000 (Hoj Rectification of defective work
Arunachal Market), Km 38.300 (Yabi initiated by the Contractor.
1 2024 RE wall Collapsed
Pradesh Village), Km 39.000 Penalty of 5% of contract
(Waterfall), Km 39.700 (Appa value imposed on Contractor.
Crusher) and Km 40.300
(Crusher Point) in the state of
Arunachal Pradesh
Six-laning of Vijayawada
bypass from Chinna Autupalli
Concessionaire commenced
(Design Ch.0+000) to
the rectification work based on
Gollapudi (Design Ch.
recommendation /suggestion
30+000) in Vijayawada – Defects in the construction
2 2024 of RE wall Expert.
Gundugolanu Section of NH- of RE wall.
Rs.10,99,235/- was recovered
16 in the State of Andhra
as damages from
Pradesh under Bharatmala
Concessionaire.
Pariyojana on Hybrid Annuity
Mode
Andhra
Pradesh
6 laning of existing 4-lane road
from Kalaparru (Design Km
1050.680) to Chinna Avutupalli
Contractor rectified defects at
(Design Km 1076.480) of NH-
his own cost.
5 including 6-lane Hanuman Defects in the construction
3 2025
Junction Bypass from (Existing of RE wall. Show-cause notices issued to
Km 1055.680 to Km 1060.800) Contractor as per Contractual
(Design Ch.0.000 to Ch.6.720) provisions.
(Total Design Length: 27.40
Km) in the State of Andhra
Pradesh under NHDP Phase-S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
V under Bharatmala
Pariyojana on EPC Mode
(Package-2)
Four Laning of Simaria-
Khagaria Section of NH-31
from Km. 206.050 to Km. Issues reported by CRRI
Repair works taken up by
266.282 (Design Chainage) in quality of Concrete of
4 2023 Contractor as recommended
and (Existing Chainage Km. superstructure in bridge at
in CRRI report
209.945 to Km. 270.000 of Km 264.946
NH-31) in the State of Bihar on
EPC Mode
Varanasi - Mohania (GTRIP/5;
Package - IV A): 4L of existing
Major deficiencies in Damages of INR 25 Cr
5 2L section from km. 65 to km. 2023
structural elements imposed on Contractor
317 of NH-2 in UP and Bihar
on NH-2
Bihar
Project Manager & Bridge
Engineer of the
Falling of concrete from
Chhapra-Hajipur Section of Concessionaire were
the deck slab of Major
NH-19 (New NH-31) suspended. Reconstruction
6 2023 Bridge at km 145+280 and
Falling of Concrete from completed by concessionaire
the Deck Slab of ROB at at their own cost.
Ch 157+860.
Umagaon-Saharsa PKG-IV
Chief Project Manager &
Engineer (Launching) of
(Kosi Bridge & approach
7 2024 A girder collapsed during Contractor suspended.
Road)
construction.
4-Laning of Simga-Sargaon
Section of NH-200 (New NH- Cracks in Cement Rectifications initiated at cost
8 2024
130) from Km 48+580 to Km Concrete Panels of EPC Contractor.
91+026
Chhattisgarh
Rehabilitation & Upgradation
The work is in Defect Liability
2-lane with paved shoulders Damage in slab of Minor
9 2025 Period and taken up by
configuration of Bilaspur bridge
Contractor at his own cost.
Urdawal section in km 241.553
to 312.60 = 71.0476 kmS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
(Masanialala to Rengapali) on
NH 200 (New NH 49)
(Package-III)(Borai river MNB
at km 217.358)
Some portion of deck slab Arbitration notice issued to
fallen down with Contractor for recovery of
Flyover and underpass at
10 2024 settlement of the damages. Process of
Hero Honda Chowk NH 48
bituminous surface (MCW-Rectification and repair works
01) on RHS at Ch. 36+350 initiated.
Authority has imposed
damages amounting to
Rs.48,61,243/- on the
contractor for delayed
maintenance. Rectification of
Delhi-Vadodara Expressway
11 2024 Rutting rutting has been taken up by
Pkg. 2
Contractor and majority of the
Haryana
rutted portion has been
rectified.
Authority has imposed
damages amounting to Rs.
42,95,049/- on the contractor
Delhi-Vadodara Expressway for delayed maintenance.
12 2024 Rutting
Pkg. 3 Rectification of rutting has
been taken up by Contractor
and majority of the rutted
portion has been rectified.
Penalty of ₹2.8 crore has
been imposed on the
Contractor along with a
Ruts, cracks and surface
recommendation for
deformation/ Distress was
debarment up to one year or
Sanchore-Santalpur Package- observed recently after
Gujarat 13 2025 until successful rectification,
4 rains in June month 2025,
whichever is later. Contractor
severe rutting at some
has taken up repair/
locations.
restoration works. The Project
Director of NHAI was
suspended.S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Four Laning of Mahulia-
Baharagora-JH/WB Border
Section of NH- 33 (from
Km.277+ 500 to Km.333+500)
Cracked PQC panels, Rs. 1.55 Cr penalty imposed
Jharkhand 14 & NH-06 (from Km.199+200 to 2024
Potholes on Contractor.
Km.183+587) (Length of
71.61Km) in the State of
Jharkhand on EPC Pattern
under NHDP Phase –III.
Concessionaire has taken up
Two/Four Laning of BRT Tiger Km 337+670 to
repair/ restoration works as
15 Reserve Boundary to 2025 Km337+680 RE Block of
per recommendation of report
Bengalore Section of NH-948 length 10 mts collapsed
submitted by IISC Bangalore.
Karnataka
Four laning of Goa-Karnataka 2024 Incident of collapse of
Border to Kundapur section of three spans of Kaali
NH-66 (formerly NH-17) from Bridge. Inadequate slope Contractor debarred for 1
16
Km. 93.700 to Km. 283.300 in stability works. month on Aug 2024.
the State of Karnataka
Distress in pile foundation
NH Connectivity to ICTT at
was observed at Bridge Penalty of Rs. 30.74 Cr was
17 Vallarpdam from Kalamassery 2025
no. 07 & 08 Ch. 7+960 imposed on Contractor
to Vallarpadam NH 966A
and Ch. 9+067 (BHS)
Damages in the pile
foundation Ch. 398+400
and 398+989 (RHS)
Kerala
Sub-standard work (Minor Concessionaire debarred for 1
Bridge works, backfill year. Rectification works
18 Kodugallur to Edappally NH 66 2025
material for RS Wall, Poor taken up at cost of
safety precautions, contractor.
delayed grouting of
girders, bulging of
bearing) or poor quality
(Defective RE Panels)
Chengala-Neeleshwaram Authority has suspended the
19 2025
Section of NH-66
Soil nailing collapsed
Concessionaire and its
promoter from future bidding
incident occurred at Ch.S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
58+035 to Ch. 58+100 for 01-month period.
(RHS) on 16.06.2025 with Debarment also issued to
no casualties. Concessionaire. Senior
Bridge Engineer of AE
removed from site.
Unprotected soil slip in the Rectification work carried out
Neeleshwaram-Thaliparambha cut section with debris and traffic restored with
20 2025
Section of NH-66 deposition on precautionary barricading in
carriageways. median portion.
NHAI - Six laning from start of
Valanchery bypass to
Debarment of Contractor and
Kappirikkad section of NH –
Independent Engineering firm
66 (old NH-17) from Design
from participating in
Ch. 298+500 (Ex. km 304.250)
21 RE wall collapsed ongoing/future bidding for 01
to Design Chainage 335+850
2025 month period or completion of
(Ex. km 349.260) in the state
investigation by the expert
of Kerala on Hybrid Annuity
Committee whichever is later.
Mode under Bharatmala
Pariyojana
Penalty of Rs. 15.35 Lakhs
Collapse of 4 PSC Girders imposed. Bridge Engineer &
22 Thuravoor-paravoor 2025
during constructions Team Leader of AE were
Terminated.
Six Laning of Start of Kollam Failure/Collapse of
Bypass to Kadambattukonam scaffolding of Minor Bridge Penalty of Rs. 9.55 lakhs
23 2025
from Km.486+000 to (under construction) at imposed on Concessionaire
Km.517+800 of NH-47 (New Km.Ch. 497+370(RHS)
NH-66) in the State of Kerala
on Hybrid Annuity Mode under Failure of RE Wall Ch. Rectification initiated by
24 2025
BharatmalaPariyojna 504+400 to 504+500(LHS) Concessionaire.
Toppling of two PSC
girders at span P-202-P-
6L Elevated Corridor along 203
with development of existing 4 Contractor and AE debarred
25 lane road at ground level from 2025 from future bidding for 1
Aroor to Thuravoor Thekku month.
Failure on part of AE to
section of NH 66
review efficacy of material
being used in launching
and not ensuringS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
application of approved
launching scheme.
Soil nailing collapse At
Rectification initiated by
26 Azhiyur-Vengalam 2024 Km:191(LHS) and
Concessionaire.
Km:193(RHS
Rectification works initiated by
27 Ramanattukara-Valanchery 2025 Defects in RE wall
Contractor at his own cost.
Retaining wall sliding and Damaged portion dismantled
Thaliparamba-
28 2026 defects in ground and rectification works
Muzhapilangadu
improvement works. initiated by Concessionaire.
Penalty of Rs. 119 Cr
Madhya 4-laning of Bhopal-Bioara Premature failure of imposed on Contractor.
29 2025
Pradesh section of NH-46 pavement. Rectification work initiated at
the cost of Contractor.
Balance work for 4-laning of
Panel cracking, poor riding
Panvel to Indapur section from Contractor has taken up
30 2024 quality, bumps, poor
km.0.0 to km.42.3 of NH-66 - rectification works.
diversions etc.
EPC
The Performance BG of
Contractor is forfeited.
31 Mehkar-Ajispur Road 2024 Cracked panels
Process initiated for
rectification of damages.
Maharashtra
Contractor has initiated
32 Bhokar-Sarsam 2024 Cracked panels actions for rectification of
damages.
Contractor has initiated
33 Sillod-Fardapur 2024 Cracked panels actions for rectification of
damages.S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Rehabilitation and upgradation
& NH-66 (Erstwhile NH-17)
form km 241+300 to 281+300
Contractor has initiated
(Arawali to Kante Section) to Depression & cracks in
34 actions for rectification of
four lane with paved shoulder PQC
2025 damages.
in the state of Maharashtra
under NHDP-IV on Hybrid
Annuity Mode.
Rehabilitation & Upgradation
of NH-66 (Old NH17) from Km
281+300 to Km 332+200
PQC cracks and Contractor has replaced
35 (Kante to Waked section) to 2024
settlement. cracked panels.
four lanes in the state of
Maharashtra under NHDP-IV
on Hybrid Annuity Mode.
Rehabilitation and up-
gradation of NH-66 (Old NH-
17) form km 332/200 to km Contractor has initiated
36 367/200 (Watul to Talgaon 2024 Full depth Cracks in PQC actions for rectification of
Section) to four lanes in the damages.
State of Maharashtra under
NHDP-IV on EPC Mode.
Rehabilitatyion & up gradation
for Talere Gaganbawada
Kolhapur Road (NH-166G)
stretches start from Ch. 6/00
Km. to Ch. 11/00 Km. and Ch.
Contractor has initiated
19/300 Km. (Start of Karul
37 2025 Cracks in PQC actions for rectification of
Ghat) to 35/300 Km. (End of
damages.
Gaganbawada) of NH-166G to
2 lane paved shoulder/2 lane
configuration lane, length
21.00 Km. in the state of
Mahrashtra on EPC Mode.S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Rehabilitation and Up-
gradation to Two lanes with
Rectification of damages
paved shoulder from Karad to
38 2024 Cracked panels taken up at risk and cost of
Tasgaon NH 266 from Km.
Contractor.
0/00 to 58/830 in the State of
Maharashtra on EPC mode
Upgradation to two lane with Post construction defects
paved shoulder are observed in the Rigid IIT Bombay has been
from Salaikhurd to Tiroda Km Pavement i.e. formation of appointed for Technical
39 120/100 to 163/200 (Design 2024 Longitudinal & Lateral Investigation of defects and
Km 44/00 to 87/00) of NH cracks, Opening of Central suggestion of remedial
753 on EPC Mode in the state Joints, Settlement of measures.
of Maharashtra Panels etc.
Penalty imposed on each
contractor amounting to Rs.
Delhi Vadodara Expressway 50 Lakhs for non-rectification
40 2024
NE-4 Pkg.06 of defects in the stipulated
time frame as per provision of
contract agreement.
Rutting, Raincuts,
Delhi Vadodara Expressway
41 2024 potholes & settlement
NE-4 Pkg.07
Delhi Vadodara Expressway
42 2024
NE-4 Pkg.08
Rajasthan
Delhi Vadodara Expressway
43 2024
NE-4 Pkg.09
Construction of 6-lane access-
controlled Greenfield highway (i) Damage of Rs. 50.00
from km 28+70 to Km. 53+0 of Lakhs imposed upon the
Sangariya (near Chautala)- Deficiencies in riding Contractor.
44 Rasisar (near Bikaner) section 2024 quality and settlement at (ii) Two key personnel of
of NH-754K as a part of some locations observed Authority Engineer team were
Amritsar-Jamnagar Economic terminated due to poor
Corridor in the State of supervision.
Rajasthan under Bharatmala
Pariyojana -Phase-I (AJ/SR-S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Package-2)
Penalty of Rs. 1.00 Cr.
imposed and warning for
debarment action for any
future instances upon the
Contractor was issued.
Construction of 6-lane access
controlled Greenfield highway Debarment of fabrication team
from km 53+000 to Km. and Designer team issued for
88+000 of Sangariya (near the period of 02 years in NHAI
Failure of the nose
Chautala)-Rasisar (near works.
structure while launching
45 Bikaner) section of NH-754K 2024
of 83 mtr single span truss
as a part of Amritsar- Penalty of Rs. 20 Lakhs and
bridge
Jamnagar Economic Corridor warning for debarment action
in the State of Rajasthan for any future instances upon
under Bharatmala Pariyojana- the Authority Engineer.
Phase-I (AJ/SR-Package-3)
Debarment of Senior bridge
Engineer deployed by the
Authority Engineer issued for
a period of 2 years in NHAI
works.
Damages amounting to Rs.
1.06 Cr. imposed for delayed
maintenance. Also, IIT
Delhi-Vadodara Expressway Rutting & settlement of
46 2024 Kharagpur has been engaged
Pkg. 4 approach
for detailed study for
permanent rectification of
defects.
Damages amounting to Rs.
88.32 lakhs imposed for
delayed maintenance. Bulging
of RE wall has been rectified
Rutting, settlement of
Delhi-Vadodara Expressway as per suggestions of CRRI.
47 2024 approach & bulging of RE
Pkg. 5 Majority of the rutting has
wall
been rectified. Further, in
addition to above, IIT
Kharagpur has been engaged
for detailed study for
permanent rectification ofS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
defects.
Delhi-Vadodara Greenfield
Stretch is operational
Alignment (NH-148N) (Pkg-16)
w.e.f. 30.11.2023 and at
(Ch. 427.300 to Ch.452.420) EPC Contractor has rectified
48 2024 some locations the
[Major bridge over Takli river damages. R
settlements observed in
near Nayagaon Jageer village
approaches of structure
to Rajasthan/MP Border]
Construction of proposed 2-
Post-completion, structural
lane ROB and its approaches
defects have been Contract has been
in lieu of existing level
observed in the deck slab terminated. Debarment of
49 crossing no. C-64 at km. 2024
of the ROB due to contractor taken up. Bid for
172.990 on Jodhpur–Ajmer
honeycombing caused by rectification works invited.
Road on NH-65 in District
poor workmanship.
Nagaur Rajasthan
The RE wall blocks portion
4-laning of Sethiyathope -
of the A2 (Thanjavur) side
50 Cholpauram section from Km 2025 approach (LHS side) have The rectification work
65.960 to Km 116.440 been disconnected from completed by the
the geo grid and fallen Concessionaire at their own
down. cost.
The RE wall panel portion
of the A1 (Thanjavur) side
4-laning of Thanjavur - Trichy Based on report of Expert
approach (LHS side) have
51 section from Km 80.000 to Km 2023 Committee,
been disconnected from
136.490 restoration work using soil
the geo grid and fallen
nailing completed by
down.
Contractor.
Construction of 4 lane green The project is under
Cracks observed over
Uttar Pradesh 52 field highway from km 35.00 to 2025 construction, the repair and
DBM due to percolation of
49.155 of NH-731A with paved rectification work taken up by
rain water in some
shoulder on Hybrid Annuity the concessionaire at its ownS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Mode in the State of Uttar stretches. cost.
Pradesh.
Contractor has initiated
Cracks in PQC Panel in
53 Lucknow Ring Road Pkg-3A 2024 process for rectification of
length of 2.886 Km.
damages.
Contractor has initiated
Uttar Pradesh 4L of Haridwar-Nagina section
54 2023 PQC panel cracks process for rectification of
& Uttarakhand of NH-74
damages.
Construction, Operation and
Maintenance of 2-Lane Bi- Rectification measures taken
Directional Silkyara Bend up by the EPC contractors at
Barkot Tunnel with escape its own cost.
Collapse at cavity in under
passage including approaches
Uttarakhand 55 2023 construction Silkyara
on Dharasu–Yamunotri
Tunnel.
section between Ch. 25.400 Actions as per the
Km and Ch. 51.000 Km falling Investigation Committee
along NH-134 (OLD NH-94) in Report initiated.
the state of Uttarakhand
i) Rectification works initiated
Construction of 4-Laning of by Contractor. Amount of Rs.
Puruliya Bypass Section from 20.00 Lakh withheld from
Cracks have developed in
Km. 84.030 to Km. 94.345 of Contractor's bill.
56 2025 the newly constructed
NH-32 (length 10.315 Km) in
PQC.
the State of West Bengal on ii) Key personal of AE has
EPC Mode been debarred for a period of
one year.
West Bengal
Four laning with paved
shoulders of NH-6 from
Chichra to Kharagpur Km
185.150 to Km 134.400 Rectification works completed
57 2023 Cracks in PQC panels
including rehabilitation of at cost of EPC Contractor.
existing four lane from Km
134.400 to Km 129.600 in the
state of West BengalS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Failure of membrane pad
of Pot – PTFE bearing on
P2 of Ahiron Bridge (Ch.
257+440 LHS MJB-truss).
Also, a level difference up
Four laning of Berhampore – Rs. 26.19 lacs penalty
to 90mm had been
58 Farakka Section of NH-12 (old 2024 imposed on Concessionaire.
observed between
NH-34) Rectification work completed.
expansion joint of deck-I
and deck-II along with
missing of some
anchoring bolts of
connecting gusset plates.
Crack at the bottom of the
deck slab at km 325+060
of the Mahananda Bridge
(LHS). The crack was
located under the fast lane
Four laning of Farakka – between span P1 & P2
Raiganj Section of NH-12 (old (PSC Girder).
NH-34) Rectification work initiated by
59 2024 At RHS Pier 4 of MJB at
Concessionaire.
325+223, piles are
exposed and heavy
reinforcement were
exposed. Exposed
reinforcement were
corroded.
Rectification initiated by
Four laning of Berhampore –
60 2025 Rutting, Potholes, Cracks Concessionaire at his own
Farakka Section of NH-12 (old
cost.
NH-34)
Six Laning of National Corridor
NH-19 from Palsit to Dankuni
Toll has been suspended. 2
(up to NH-6 Connector) from
61 2026 Collapse of RE Wall key personnel of IE and
km 588.870 to km 652.700 in
Concessionaire suspended.
the state of West Bengal
under Bharatmala Pariyojana
to be executed on BOT (Toll)S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
basis.
1. For Faulty Design at Km
96+326, penalty imposed of
1. Faulty Design in Bridge
Rs.30 Lakhs on the
at km. 96+326:
Concessionaire and Rs.5
Lakhs on the Independent
Engineer. Team Leader of IE
2. Bridge at km. 79+614: and Key Personnel of
Concessionaire suspended.
The span A1-P1 had
dislodged from the pier P2
due to breaking of the
2. For Bridge at km. 79+614:
cantilever
Penalty of Rs.5 crore imposed
Chandikhole-Bhadrak Section Portion of the pier cap and
Odisha 62 2023 on the Contractor and Penalty
of NH-16 had fallen on the ground.
of Rs.20 lakh imposed on the
Supervision Consultant.
Appearance of wide
cracks (up to 3-4mm) in
Debarment of DPR Consultant
the pier cap on grid “P2”.
for 1 year.
Damages of deck slab and
The cost of entire remedial
girders of the dislodged
measures / reconstruction
span.
recovered from the
Concessionaire.
Construction of 6-lane
Standalone Flyovers at
Bongaigaon, Chapaguri,
Falling of one PSC Girder
Pathsala, Simlaguri Chowk Penalty imposed on
at Baihata Flyover (Span
Assam 63 and Baihata Junctions on 2024 Contractor. Contractor
P1-P2), resulting in the
stretches of NH-31 & NH-31C debarred for 4 months.
death of one person.
[new NH-27 (EW)] in the State
of Assam under Bharatmala
Pariyojana on EPC basisS. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Two Lane with paved
shoulders configuration in
Jowai-Meghalaya Assam
Penalty of Rs. 20,00,000/-
Border Section of NH - 44 Slippage of Bituminous
imposed on Contractor and
Meghalaya 64 from Km 69.200 to Km 2025 concrete for a length of
rectification work carried out
173.200 (design Ch 171.455 ) approximate 10-15 mtrs
by Contractor at his own cost.
in the state of Meghalaya
Construction of Dwarka
Expressway Package-1, from
Shiv Murti Intersection at Km P8-P9 of flyover part of
20 of NH-8 till road under Shiv Murti interchange on Remedial measures
Delhi 65 2023
Bridge (RUB) near Dwarka Dwarka Expressway completed by Contractor.
Sector-21(From Km -0.600 to toppled.
5.300) in the state of Delhi on
EPC mode
Rehabilitation of km 181.00 to
Km 206.00 section in
Andaman Trunk Road of NH-4
Distress, sinking of
to Intermediate Lane with hard
66 2024 pavement at various Rectification works completed.
shoulder in the union Territory
locations.
of Andaman & Nicobar islands
(Total length 25.00 km) on
Andaman & EPC Mode” (Package-VII)
Nicobar
Islands Construction of 4 Nos. of
The EPC contractor has
Minor Bridges at Km 21.717, Punching in Deck Slab
carried out the necessary
Km 23.150, Km 88.300, Km (LHS) of the minor bridge
rectifications at their own
92.100 of NH- 223 (New NH- across BD Nallah at Km
67 2024 expense including
4) connecting South Andaman 88+300 and other quality
replacement of slab as
and Baratang Island in the issues including bad
recommended by CRRI-CSIR
Union Territory of Andaman & workmanship.
report.
Nicobar Islands on EPC mode.
*****