See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO - 6221
ANSWERED ON 02TH APRIL 2026
MAINTENANCE AND REPAIR OF NATIONAL HIGHWAYS
6221. DR. KIRSAN NAMDEO:
SMT. JYOTSNA CHARANDAS MAHANT:
SHRI KISHORI LAL:
SHRI BENNY BEHANAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the length of National Highways constructed since financial year
2018-19, along with total construction expenditure and the amount
spent on their maintenance and repair during the five years of
completion, year-wise and State-wise;
(b) the number of accidents and fatalities on National Highways
since 2021 where potholes, surface defects or incomplete
construction were recorded as contributing factors, year-wise and
State-wise;
(c) whether any contractor has been penalised or blacklisted due to
premature road deterioration or poor-quality construction and if so,
the details thereof, State-wise;
(d) the details of National Highways passing through or constructed
in Amethi district of Uttar Pradesh since financial year 2018-19,
including the length constructed or upgraded, funds allocated and
utilised, maintenance expenditure and the number of accidents
reported on these stretches during the said period; and
(e) whether the Government has reviewed cost escalations in
Bharatmala projects due to delays in land acquisition and the extent
of such escalations, project-wise and if so, the details thereof?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) The State / Union Territory (UT)-wise and year-wise details of
length of National Highways (NHs) constructed since financial year
2018-19 and expenditure incurred towards development &
maintenance of NHs during the last five years is at Annexure-I and
Annexure-II respectively.
(b) The Government publishes report on “Road Accidents in
India” based on data received from States / UTs. As per the report,
total number of road accidents on NHs due to all kinds of causes
are as follows: -
Year Total No. of Road Tota No. of Road
Accidents on NHs fatalities on NHs
2021 1,28,825 56,007
2022 1,51,997 61,038
2023 1,50,177 63,112
2024 1,50,958 64,772
(c) The Government in the Ministry of Road Transport and
Highways is primarily responsible for development and maintenance
of NHs. As per information provided by the executing agencies of
the NHs, major deficiencies in NH stretches during the last three
years and the current year have been reported for 67 projects /
stretches. The State / UT wise details of major deficiencies in NH
stretches during the last three years and the current year along
with status of its rectification works and action taken against
contractors/ concessionaires’ consultants are at Annexure-III.
Actions against defaulting agencies are taken up as per the
provisions of the Contract/ Concession agreement in cases of
deficiencies / damages, such as termination of contract agreement,
levying of penalties/ liquidated damages, debarment / blacklisting,
declaring as non-performers etc.
(d) 377 km length of NHs passing through Amethi district of Uttar
Pradesh has been developed / upgraded since FY 2018–19 through
various projects. Allocation of funds for development and
maintenance of NHs are made State / Agency wise and not projectwise. State-wise & year-wise details of expenditure incurred
towards development & maintenance of NHs during last five years
is given at Annexure-II.
344 road accidents have been reported on NHs passing
through Amethi district since 2021 (data based on electronic
Detailed Accident Report is implemented since 2021).
(e) As per the latest available information, 85 under construction
NHs projects including projects under Bharatmala Pariyojana are
delayed by more than three years, attributable to various issues
such as, bottlenecks relating to land acquisition, statutory
clearances / permissions, utility shifting, encroachment removal,
law & order issues, financial crunch affecting implementation
capacity of concessionaire / contractor, poor performance of
contractor / concessionaire, and Force Majeure events, such as,
Covid-19 pandemic, Change of Law, etc.
The Government has undertaken various initiatives to prevent
recurrence of delays and cost escalations. These include
streamlining and expediting land acquisition and compensation
using “BhoomiRashi” portal integrated with Public Finance
Management System (PFMS) and GIS-based Land Acquisition Plan,
revamping “Parivesh” Portal, to facilitate faster forest and
environmental clearances, enabling online approval of General
Arrangement of Drawings (GAD) of Road Over Bridge/ Road Under
Bridge (ROB/ RUB), and leveraging the mechanism of review and
resolution of bottlenecks / hindrances in ongoing projects, in active
collaboration with the State Governments and other stakeholders.
Government has also launched a web portal for Railway related
clearances with defined timelines for various approvals.
The Government has put in place a strong framework using
multiple mechanisms for monitoring project progress. Regular
review meetings are conducted at various levels with stakeholders
to assess project progress, and critical projects, such as those
delayed by more than three years or pending for award/
appointment. Cost escalation is not incurred in all delayed projects.
If delay is not attributable to the Contractor, escalation is paid as
per contract conditions, which may or may not result in additional
cost, depending upon final value of price escalation determined on
actual completion of project. If delay is attributable to theContractor, damages are imposed and there is no additional cost
due to delay.
Many State Governments conduct coordination meetings led
by the Chief Secretary to resolve issues affecting project execution.
Projects where issues remain unresolved are escalated for further
review through the Project Monitoring Group. As a result of the
above, no. of projects delayed by more than 3 years has come down
from 152 in April 2024 to 79 in March 2026.ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF LOK SABHA
UNSTARRED QUESTION NO. 6221 ANSWERED ON 02.04.2026
ASKED BY DR. KIRSAN NAMDEO, SMT. JYOTSNA CHARANDAS
MAHANT, SHRI KISHORI LAL AND SHRI BENNY BEHANAN
REGARDING MAINTENANCE AND REPAIR OF NATIONAL HIGHWAYS
The State/UT wise details of length (km) of NHs constructed since
financial year 2018-19
2025-
Sr. 2018- 2019- 2020- 2021- 2022- 2023- 2024-
State/UT 26 (till
No. 19 20 21 22 23 24 25
feb)
Andhra
1 438 587 515 347 438 799 757 665
Pradesh
Arunachal
2 157 94 135 206 320 262 152 58
Pradesh
3 Assam 323 247 567 318 310 272 344 244
4 Bihar 333 197 691 576 488 497 465 249
5 Chhattisgarh 397 198 247 320 243 251 308 233
6 Goa 11 30 49 65 16 11 27 6
7 Gujarat 303 292 361 249 658 622 500 420
8 Haryana 226 220 406 290 358 300 287 75
Himachal
9 157 76 89 146 139 251 166 121
Pradesh
10 Jharkhand 287 298 358 298 245 248 202 125
11 Karnataka 779 500 425 419 393 741 477 348
12 Kerala 121 186 344 76 171 282 193 54
Madhya
13 829 714 877 871 667 792 894 674
Pradesh
14 Maharashtra 2293 2422 2870 1534 1087 1463 1203 937
15 Manipur 318 304 224 221 269 202 216 68
16 Meghalaya 13 0 36 26 98 162 154 47
17 Mizoram 59 42 169 239 205 209 126 44
18 Nagaland 34 68 197 254 236 159 230 108
19 Odisha 534 441 683 544 410 357 330 223
20 Punjab 209 344 188 150 274 409 227 186
21 Rajasthan 728 1018 825 722 715 868 794 5822025-
Sr. 2018- 2019- 2020- 2021- 2022- 2023- 2024-
State/UT 26 (till
No. 19 20 21 22 23 24 25
feb)
22 Sikkim 83 29 39 45 49 78 58 6
23 Tamil Nadu 356 204 447 470 690 814 613 390
24 Telangana 370 340 227 236 172 513 416 185
25 Tripura 41 5 78 181 204 47 51 21
Uttar
26 882 694 917 824 642 939 906 855
Pradesh
27 Uttarakhand 237 357 577 354 219 216 148 80
28 West Bengal 127 174 400 169 284 190 121 47
Andaman &
29 Nicobar 61 65 113 39 25 11 18 10
Islands
Dadra &
Nagar Haveli
30 0 0 3 0 0 0 0 6
and Daman
& Diu
31 Delhi 42 38 20 5 43 53 10 6
Jammu &
32 95 46 234 263 217 243 214 124
Kashmir
33 Ladakh 0 4 7 0 51 81 50 17
34 Puducherry 12 3 7 0 0 11 0 0ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PART (a) & (d) OF LOK
SABHA UNSTARRED QUESTION NO. 6221 ANSWERED ON 02.04.2026
ASKED BY DR. KIRSAN NAMDEO, SMT. JYOTSNA CHARANDAS
MAHANT, SHRI KISHORI LAL AND SHRI BENNY BEHANAN
REGARDING MAINTENANCE AND REPAIR OF NATIONAL HIGHWAYS
The State / UT - wise details of expenditure incurred towards
development and maintenance of NHs during the last five years
(Amount in ₹ Crore)
Sr.
State/UT 2020-21 2021-22 2022-23 2023-24 2024-25
No.
1 Andhra Pradesh 4,281 5,890 6,957 11,440 11,756
Arunachal
2 2,512 2,718 3,140 2,649 3,599
Pradesh
3 Assam 3,753 3,150 4,557 9,137 7,207
4 Bihar 6,716 9,174 9,347 10,749 8,840
5 Chhattisgarh 2,224 1,936 2,468 4,255 2,280
6 Goa 734 615 673 620 651
7 Gujarat 7,533 10,710 9,831 10,900 8,091
8 Haryana 10,651 7,203 3,924 6,062 4,344
Himachal
9 2,033 3,164 4,534 5,175 3,994
Pradesh
10 Jharkhand 2,627 2,853 3,127 4,599 5,169
11 Karnataka 5,838 7,681 6,763 12,695 10,819
12 Kerala 12,831 10,136 3,994 10,419 5,082
Madhya
13 8,250 9,006 6,210 7,447 7,799
Pradesh
14 Maharashtra 20,844 18,655 18,355 19,867 18,512
15 Manipur 978 2,142 2,737 2,598 2,011
16 Meghalaya 861 819 684 1,803 1,697
17 Mizoram 1,238 2,054 3,218 2,189 2,091
18 Nagaland 2,382 1,943 1,666 1,414 1,600
19 Odisha 5,336 4,510 4,643 5,948 5,786
20 Punjab 3,301 7,179 10,093 12,419 7,898
21 Rajasthan 7,340 11,353 9,719 8,874 6,301Sr.
State/UT 2020-21 2021-22 2022-23 2023-24 2024-25
No.
22 Sikkim 1,053 811 1,008 684 441
23 Tamil Nadu 4,868 4,305 8,230 9,925 9,068
24 Telangana 2,907 3,458 3,622 6,117 7,496
25 Tripura 1,026 1,085 1,156 1,546 767
26 Uttar Pradesh 18,768 13,944 21,453 28,114 20,665
27 Uttarakhand 2,800 2,112 3,219 4,545 3,835
28 West Bengal 2,658 3,642 3,053 3,543 2,240
Andaman &
29 349 246 143 96 204
Nicobar Islands
30 Chandigarh 2 6 1 0 0
Dadra & Nagar
31 Haveli and 43 30 26 2 46
Daman & Diu
Delhi /
32 -1,482 3,961 7,164 3,223 2,840
Headquarters
Jammu &
33 2,932 6,817 7,370 10,528 10,204
Kashmir
34 Ladakh 24 352 574 658 768
35 Puducherry 21 1 61 35 23
[Negative figure against State/UT during the year indicates transfer
of project/expenditure from that State/UT to other State/UT]ANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PART (c) OF LOK SABHA
UNSTARRED QUESTION NO. 6221 ANSWERED ON 02.04.2026
ASKED BY DR. KIRSAN NAMDEO, SMT. JYOTSNA CHARANDAS
MAHANT, SHRI KISHORI LAL AND SHRI BENNY BEHANAN
REGARDING MAINTENANCE AND REPAIR OF NATIONAL HIGHWAYS
The State / Union Territory (UT) – wise details of major deficiencies
in NH stretches in the last three years and current year along with
status of its rectification works and action taken against
contractors / concessionaires / consultants
Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Permanent
solution to Slip
Zones on Papu –
Yupia – Hoj –
Potin section of
NH-713A & NH-
Rectification of
13 at Km 31.000
defective work
(Hoj Market),
initiated by the
Arunach Km 38.300
RE wall Contractor.
al 1 (Yabi Village), 2024
Collapsed Penalty of 5% of
Pradesh Km 39.000
contract value
(Waterfall), Km
imposed on
39.700 (Appa
Contractor.
Crusher) and
Km 40.300
(Crusher Point)
in the state of
Arunachal
PradeshYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Six-laning of
Vijayawada
bypass from
Chinna
Autupalli
Concessionaire
(Design
commenced the
Ch.0+000) to
rectification work
Gollapudi
based on
(Design Ch.
Defects in the recommendation
30+000) in
2 2024 construction of /suggestion of RE
Vijayawada –
RE wall. wall Expert.
Gundugolanu
Rs.10,99,235/-
Section of NH-
was recovered as
16 in the State
damages from
of Andhra
Concessionaire.
Pradesh under
Andhra Bharatmala
Pradesh Pariyojana on
Hybrid Annuity
Mode
6 laning of
existing 4-lane
road from
Contractor
Kalaparru
rectified defects
(Design Km
at his own cost.
1050.680) to
Defects in the
Chinna Show-cause
3 2025 construction of
Avutupalli notices issued to
RE wall.
(Design Km Contractor as per
1076.480) of Contractual
NH-5 including provisions.
6-lane Hanuman
Junction
Bypass fromYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
(Existing Km
1055.680 to Km
1060.800)
(Design
Ch.0.000 to
Ch.6.720) (Total
Design Length:
27.40 Km) in
the State of
Andhra Pradesh
under NHDP
Phase-V under
Bharatmala
Pariyojana on
EPC Mode
(Package-2)
Four Laning of
Simaria-
Khagaria
Section of NH-
31 from Km. Issues reported
206.050 to Km. by CRRI in Repair works
266.282 (Design quality of taken up by
4 Chainage) and 2023 Concrete of Contractor as
Bihar (Existing superstructure recommended in
Chainage Km. in bridge at Km CRRI report
209.945 to Km. 264.946
270.000 of NH-
31) in the State
of Bihar on EPC
Mode
Varanasi - Major Damages of INR
5 2023
Mohania deficiencies in 25 Cr imposed onYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
(GTRIP/5; structural Contractor
Package - IV A): elements
4L of existing
2L section from
km. 65 to km.
317 of NH-2 in
UP and Bihar on
NH-2
Project Manager
Falling of
& Bridge
concrete from
Engineer of the
the deck slab of
Chhapra-Hajipur Concessionaire
Major Bridge at
Section of NH- were suspended.
km 145+280
6 2023
19 (New NH-31) Reconstruction
and Falling of
completed by
Concrete from
concessionaire at
the Deck Slab
their own cost.
of ROB at Ch
157+860.
Chief Project
Umagaon-
Manager &
Saharsa PKG-IV
A girder Engineer
collapsed (Launching) of
7 (Kosi Bridge & 2024
during Contractor
approach Road)
construction. suspended.
4-Laning of
Simga-Sargaon
Cracks in Rectifications
Section of NH-
Chhattisg Cement initiated at cost
8 200 (New NH- 2024
arh Concrete of EPC
130) from Km
Panels Contractor.
48+580 to Km
91+026Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Rehabilitation &
Upgradation 2-
lane with paved
shoulders
configuration of
Bilaspur
Urdawal section
The work is in
in km 241.553
Defect Liability
to 312.60 = Damage in slab
9 2025 Period and taken
71.0476 km of Minor bridge
up by Contractor
(Masanialala to
at his own cost.
Rengapali) on
NH 200 (New
NH 49)
(Package-
III)(Borai river
MNB at km
217.358)
Arbitration notice
Some portion of
issued to
deck slab fallen
Contractor for
Flyover and down with
recovery of
underpass at settlement of
10 2024 damages.
Hero Honda the bituminous
Process of
Chowk NH 48 surface (MCW-
Rectification and
01) on RHS at
Haryana repair works
Ch. 36+350
initiated.
Authority has
imposed
Delhi-Vadodara
damages
11 Expressway 2024 Rutting
amounting to
Pkg. 2
Rs.48,61,243/- on
the contractor forYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
delayed
maintenance.
Rectification of
rutting has been
taken up by
Contractor and
majority of the
rutted portion has
been rectified.
Authority has
imposed
damages
amounting to Rs.
42,95,049/- on the
contractor for
Delhi-Vadodara delayed
202
12 Expressway Rutting maintenance.
4
Pkg. 3 Rectification of
rutting has been
taken up by
Contractor and
majority of the
rutted portion has
been rectified.
Ruts, cracks Penalty of ₹2.8
and surface crore has been
deformation/ imposed on the
Sanchore-
Distress was Contractor along
Gujarat 13 Santalpur 2025
observed with a
Package-4
recently after recommendation
rains in June for debarment up
month 2025, to one year orYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
severe rutting until successful
at some rectification,
locations. whichever is
later. Contractor
has taken up
repair/
restoration
works. The
Project Director
of NHAI was
suspended.
Four Laning of
Mahulia-
Baharagora-
JH/WB Border
Section of NH-
33 (from
Km.277+ 500 to
Km.333+500) &
Cracked PQC Rs. 1.55 Cr
Jharkhan NH-06 (from
14 2024 panels, penalty imposed
d Km.199+200 to
Potholes on Contractor.
Km.183+587)
(Length of
71.61Km) in the
State of
Jharkhand on
EPC Pattern
under NHDP
Phase –III.Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Concessionaire
Two/Four has taken up
Laning of BRT Km 337+670 to repair/
Tiger Reserve Km337+680 RE restoration works
15 Boundary to 2025 Block of length as per
Bengalore 10 mts recommendation
Section of NH- collapsed of report
948 submitted by IISC
Bangalore.
Karnatak
a Four laning of 2024
Goa-Karnataka
Incident of
Border to
collapse of
Kundapur
three spans of
Contractor
section of NH-
Kaali Bridge.
debarred for 1
16 66 (formerly NH-
Inadequate
month on Aug
17) from Km.
slope stability
2024.
93.700 to Km.
works.
283.300 in the
State of
Karnataka
NH Connectivity Distress in pile
to ICTT at foundation was
Penalty of Rs.
Vallarpdam observed at
30.74 Cr was
17 from 2025 Bridge no. 07 &
imposed on
Kalamassery to 08 Ch. 7+960
Kerala Contractor
Vallarpadam NH and Ch. 9+067
966A (BHS)
Concessionaire
Damages in the
debarred for 1
Kodugallur to pile foundation
year.
18 Edappally NH 2025 Ch. 398+400
Rectification
66 and 398+989
works taken up
(RHS)
at cost ofYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Sub-standard contractor.
work (Minor
Bridge works,
backfill
material for RS
Wall, Poor
safety
precautions,
delayed
grouting of
girders, bulging
of bearing) or
poor quality
(Defective RE
Panels)
Authority has
suspended the
Concessionaire
and its promoter
Soil nailing
from future
collapsed
Chengala- bidding for 01-
incident
Neeleshwaram month period.
occurred at Ch.
19 2025
Section of NH- Debarment also
58+035 to Ch.
66 issued to
58+100 (RHS)
Concessionaire.
on 16.06.2025
Senior Bridge
with no
Engineer of AE
casualties.
removed from
site.
Neeleshwaram-
Unprotected Rectification
Thaliparambha
soil slip in the work carried out
20 2025
Section of NH-
cut section and traffic
66
with debris restored withYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
deposition on precautionary
carriageways. barricading in
median portion.
NHAI - Six
laning from
start of
Valanchery
Debarment of
bypass to
Contractor and
Kappirikkad
Independent
section of NH –
Engineering firm
66 (old NH-17)
from participating
from Design Ch.
in ongoing/future
298+500 (Ex.
RE wall bidding for 01
21 km 304.250) to
collapsed month period or
2025
Design
completion of
Chainage
investigation by
335+850 (Ex.
the expert
km 349.260) in
Committee
the state of
whichever is
Kerala on
later.
Hybrid Annuity
Mode under
Bharatmala
Pariyojana
Penalty of Rs.
Collapse of 4 15.35 Lakhs
Thuravoor- PSC Girders imposed. Bridge
22 2025
paravoor during Engineer & Team
constructions Leader of AE
were Terminated.
Six Laning of Failure/Collapse Penalty of Rs.
23 2025
Start of Kollam of scaffolding of 9.55 lakhs
Bypass to Minor Bridge imposed onYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Kadambattukon (under Concessionaire
am from construction) at
Km.486+000 to Km.Ch.
Km.517+800 of 497+370(RHS)
NH-47 (New NH-
66) in the State
Failure of RE
of Kerala on
Rectification
Wall Ch.
Hybrid Annuity
24 2025 initiated by
504+400 to
Mode under
Concessionaire.
504+500(LHS)
BharatmalaPari
yojna
Toppling of two
PSC girders at
span P-202-P-
203
6L Elevated
Corridor along
with
Failure on part
development of Contractor and
of AE to review
existing 4 lane AE debarred from
25 2025 efficacy of
road at ground future bidding for
material being
level from Aroor 1 month.
used in
to Thuravoor
launching and
Thekku section
not ensuring
of NH 66
application of
approved
launching
scheme.
Soil nailing
collapse At Rectification
Azhiyur-
26 2024 Km:191(LHS) initiated by
Vengalam
and Concessionaire.
Km:193(RHSYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Rectification
Ramanattukara- Defects in RE works initiated by
27 2025
Valanchery wall Contractor at his
own cost.
Retaining wall
Damaged portion
sliding and
dismantled and
Thaliparamba- defects in
28 2026 rectification
Muzhapilangadu ground
works initiated by
improvement
Concessionaire.
works.
Penalty of Rs.
119 Cr imposed
4-laning of
Premature on Contractor.
Madhya Bhopal-Bioara
29 2025 failure of Rectification
Pradesh section of NH-
pavement. work initiated at
46
the cost of
Contractor.
Balance work
for 4-laning of Panel cracking,
Contractor has
Panvel to poor riding
taken up
30 Indapur section 2024 quality, bumps,
rectification
from km.0.0 to poor diversions
works.
km.42.3 of NH- etc.
Maharash 66 - EPC
tra
The Performance
BG of Contractor
Mehkar-Ajispur is forfeited.
31 2024 Cracked panels
Road Process initiated
for rectification
of damages.Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Contractor has
initiated actions
32 Bhokar-Sarsam 2024 Cracked panels
for rectification
of damages.
Contractor has
initiated actions
33 Sillod-Fardapur 2024 Cracked panels
for rectification
of damages.
Rehabilitation
and upgradation
& NH-66
(Erstwhile NH-
17) form km
241+300 to
281+300
Contractor has
(Arawali to
Depression & initiated actions
34 Kante Section)
cracks in PQC for rectification
2025
to four lane
of damages.
with paved
shoulder in the
state of
Maharashtra
under NHDP-IV
on Hybrid
Annuity Mode.
Rehabilitation &
Upgradation of
NH-66 (Old
Contractor has
202 PQC cracks and
NH17) from Km
35 replaced cracked
4 settlement.
281+300 to Km
panels.
332+200 (Kante
to Waked
section) to fourYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
lanes in the
state of
Maharashtra
under NHDP-IV
on Hybrid
Annuity Mode.
Rehabilitation
and up-
gradation of NH-
66 (Old NH-17)
form km
332/200 to km Contractor has
Full
367/200 (Watul initiated actions
36 2024 depth Cracks i
to Talgaon for rectification
n PQC
Section) to four of damages.
lanes in the
State of
Maharashtra
under NHDP-IV
on EPC Mode.
Rehabilitatyion
& up gradation
for Talere
Gaganbawada
Kolhapur Road
Contractor has
(NH-166G)
initiated actions
37 2025 Cracks in PQC
stretches start
for rectification
from Ch. 6/00
of damages.
Km. to Ch.
11/00 Km. and
Ch. 19/300 Km.
(Start of Karul
Ghat) to 35/300Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Km. (End of
Gaganbawada)
of NH-166G to 2
lane paved
shoulder/2 lane
configuration
lane, length
21.00 Km. in the
state of
Mahrashtra on
EPC Mode.
Rehabilitation
and Up-
gradation to
Two lanes with
Rectification of
paved shoulder
damages taken
from Karad to
38 2024 Cracked panels up at risk and
Tasgaon NH
cost of
266 from Km.
Contractor.
0/00 to 58/830
in the State of
Maharashtra on
EPC mode
Upgradation to Post
IIT Bombay has
two lane with construction d
been appointed
paved shoulder efects are
for Technical
from Salaikhur observed in the
Investigation of
d to Tiroda Km Rigid Pavement
39 2024
defects and
120/100 i.e. formation of
suggestion of
to 163/200 Longitudinal &
remedial
(Design Km Lateral cracks,
measures.
44/00 to Opening of
87/00) of NH Central Joints,Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
753 on EPC Settlement of
Mode in the Panels etc.
state of
Maharashtra
Penalty imposed
on each
contractor
amounting to Rs.
50 Lakhs for non-
Delhi Vadodara
rectification of
40 Expressway NE- 2024
defects in the
4 Pkg.06
stipulated time
frame as per
provision of
Rutting,
contract
Raincuts,
agreement.
potholes &
Rajastha
settlement
n Delhi Vadodara
41 Expressway NE- 2024
4 Pkg.07
Delhi Vadodara
42 Expressway NE- 2024
4 Pkg.08
Delhi Vadodara
43 Expressway NE- 2024
4 Pkg.09
Construction of Deficiencies in (i) Damage of Rs.
6-lane access- riding quality 50.00 Lakhs
44 2024
controlled and settlement imposed upon the
Greenfield at some Contractor.Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
highway from locations (ii) Two key
km 28+70 to observed personnel of
Km. 53+0 of Authority
Sangariya (near Engineer team
Chautala)- were terminated
Rasisar (near due to poor
Bikaner) supervision.
section of NH-
754K as a part
of Amritsar-
Jamnagar
Economic
Corridor in the
State of
Rajasthan under
Bharatmala
Pariyojana -
Phase-I (AJ/SR-
Package-2)
Construction of
Penalty of Rs.
6-lane access
1.00 Cr. imposed
controlled
and warning for
Greenfield
debarment action
highway from
Failure of the for any future
km 53+000 to
nose structure instances upon
Km.
while launching the Contractor
45 2024
88+000 of San
of 83 mtr single was issued.
gariya (near
span truss
Debarment of
Chautala)-
bridge
fabrication team
Rasisar (near
and Designer
Bikaner)
team issued for
section of NH-
the period of 02
754K as a part
years in NHAI
of Amritsar-Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Jamnagar works.
Economic
Penalty of Rs. 20
Corridor in the
Lakhs and
State of
warning for
Rajasthan under
debarment action
Bharatmala
for any future
Pariyojana-
instances upon
Phase-I (AJ/SR-
the Authority
Package-3)
Engineer.
Debarment of
Senior bridge
Engineer
deployed by the
Authority
Engineer issued
for a period of 2
years in NHAI
works.
Damages
amounting to Rs.
1.06 Cr. imposed
for delayed
maintenance.
Delhi-Vadodara Rutting &
Also, IIT
46 Expressway 2024 settlement of
Kharagpur has
Pkg. 4 approach
been engaged for
detailed study for
permanent
rectification of
defects.Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Damages
amounting to Rs.
88.32 lakhs
imposed for
delayed
maintenance.
Bulging of RE
wall has been
Rutting, rectified as per
Delhi-Vadodara settlement of suggestions of
47 Expressway 2024 approach & CRRI. Majority of
Pkg. 5 bulging of RE the rutting has
wall been rectified.
Further, in
addition to above,
IIT Kharagpur has
been engaged for
detailed study for
permanent
rectification of
defects.
Delhi-Vadodara
Greenfield Stretch is
Alignment (NH- operational
148N) (Pkg-16) w.e.f.
(Ch. 427.300 to 30.11.2023 and
EPC Contractor
Ch.452.420) at some
48 2024 has rectified
[Major bridge locations the
damages. R
over Takli river settlements
near Nayagaon observed in
Jageer village approaches of
to Rajasthan/MP structure
Border]Year Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Construction of
proposed 2-lane Post-
ROB and its completion,
Contract has
approaches in structural
been
lieu of existing defects have
terminated. Deba
level crossing been observed
rment of
49 no. C-64 at km. 2024 in the deck slab
contractor taken
172.990 on of the ROB due
up. Bid for
Jodhpur–Ajmer to
rectification
Road on NH-65 honeycombing
works invited.
in District caused by poor
Nagaur workmanship.
Rajasthan
The RE wall
blocks portion
4-laning of
of the A2
Sethiyathope -
(Thanjavur) side
Cholpauram The rectification
50 2025
approach (LHS
section from work completed
side) have been
Km 65.960 to by the
disconnected
Km 116.440 Concessionaire
from the geo
at their own cost.
grid and fallen
down.
The RE wall
panel portion of
Based on report
4-laning of
the A1
of Expert
Thanjavur -
(Thanjavur) side
Committee,
51 Trichy section 2023
approach (LHS
restoration work
from Km 80.000
side) have been
using soil nailing
to Km 136.490
disconnected
completed by
from the geo
Contractor.
grid and fallenYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
down.
Construction of
4 lane green
The project is
field highway
Cracks under
from km 35.00
observed over construction, the
to 49.155 of NH-
DBM due to repair and
52 731A with 2025
percolation of rectification work
paved shoulder
rain water in taken up by the
Uttar
on Hybrid
some stretches. concessionaire at
Pradesh
Annuity Mode in
its own cost.
the State of
Uttar Pradesh.
Contractor has
Cracks in PQC
Lucknow Ring initiated process
53 2024 Panel in length
Road Pkg-3A for rectification
of 2.886 Km.
of damages.
Uttar
Contractor has
Pradesh 4L of Haridwar-
PQC panel initiated process
& 54 Nagina section 2023
cracks for rectification
Uttarakh of NH-74
of damages.
and
Construction, Rectification
Operation and measures taken
Collapse at
Maintenance of up by the EPC
Uttarakh cavity in under
2-Lane Bi- contractors at its
55 2023
and construction
Directional own cost.
Silkyara Tunnel.
Silkyara Bend
Barkot Tunnel
with escape Actions as perYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
passage the Investigation
including Committee
approaches on Report initiated.
Dharasu–
Yamunotri
section
between Ch.
25.400 Km and
Ch. 51.000 Km
falling along
NH-134 (OLD
NH-94) in the
state of
Uttarakhand
i) Rectification
Construction of works initiated by
4-Laning of Contractor.
Puruliya Bypass Amount of Rs.
Section from Cracks have 20.00 Lakh
Km. 84.030 to developed in withheld from
56 Km. 94.345 of 2025 the newly Contractor's bill.
NH-32 (length constructed
10.315 Km) in PQC. ii) Key personal
West
the State of of AE has been
Bengal
West Bengal on debarred for a
EPC Mode period of one
year.
Four laning with
Rectification
paved shoulders
Cracks in PQC works completed
of NH-6 from
57 2023
panels at cost of EPC
Chichra to
Contractor.
Kharagpur Km
185.150 to KmYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
134.400
including
rehabilitation of
existing four
lane from Km
134.400 to Km
129.600 in the
state of West
Bengal
Failure of
membrane pad
of Pot – PTFE
bearing on P2
of Ahiron Bridge
(Ch. 257+440
LHS MJB-truss).
Also, a level Rs. 26.19 lacs
Four laning of
difference up to penalty imposed
Berhampore –
90mm had been on
58 Farakka Section 2024
observed Concessionaire.
of NH-12 (old
between Rectification
NH-34)
expansion joint work completed.
of deck-I and
deck-II along
with missing of
some anchoring
bolts of
connecting
gusset plates.
Four laning of Crack at the
Rectification
Farakka – bottom of the
59 2024 work initiated by
Raiganj Section deck slab at km
Concessionaire.
of NH-12 (old 325+060 of theYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
NH-34) Mahananda
Bridge (LHS).
The crack was
located under
the fast lane
between span
P1 & P2 (PSC
Girder).
At RHS Pier 4 of
MJB at
325+223, piles
are exposed
and heavy
reinforcement
were exposed.
Exposed
reinforcement
were corroded.
Four laning of Rectification
Rutting,
Berhampore –
initiated by
60 2025 Potholes,
Farakka Section
Concessionaire
Cracks
of NH-12 (old
at his own cost.
NH-34)
Six Laning of
National
Toll has been
Corridor NH-19
suspended. 2 key
from Palsit to
Collapse of RE personnel of IE
61 2026
Dankuni (up to
Wall and
NH-6
Concessionaire
Connector) from
suspended.
km 588.870 to
km 652.700 inYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
the state of
West Bengal
under
Bharatmala
Pariyojana to be
executed on
BOT (Toll)
basis.
1. Faulty Design 1. For Faulty
in Bridge at km. Design at Km
96+326: 96+326, penalty
imposed of Rs.30
Lakhs on the
2. Bridge at km. Concessionaire
79+614: and Rs.5 Lakhs
on the
The span A1-P1
Independent
had dislodged
Engineer. Team
from the pier P2
Leader of IE and
Chandikhole- due to breaking
Key Personnel of
Bhadrak of the
Odisha 62 2023 Concessionaire
Section of NH- cantilever
suspended.
16
Portion of the
pier cap and
had fallen on 2. For Bridge at
the ground. km. 79+614:
Penalty of Rs.5
crore imposed on
Appearance of
the Contractor
wide cracks (up
and Penalty of
to 3-4mm) in
Rs.20 lakh
the pier cap on
imposed on the
grid “P2”.
SupervisionYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
Consultant.
Damages of
deck slab and
Debarment of
girders of the
DPR Consultant
dislodged span.
for 1 year.
The cost of entire
remedial
measures /
reconstruction
recovered from
the
Concessionaire.
Construction of
6-lane
Standalone
Flyovers at
Bongaigaon,
Chapaguri,
Falling of one
Pathsala,
PSC Girder at Penalty imposed
Simlaguri
Baihata Flyover on Contractor.
Chowk and
Assam 63 2024 (Span P1-P2), Contractor
Baihata
resulting in the debarred for 4
Junctions on
death of one months.
stretches of NH-
person.
31 & NH-31C
[new NH-27
(EW)] in the
State of Assam
under
Bharatmala
Pariyojana onYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
EPC basis
Two Lane with
paved shoulders
configuration in
Jowai-
Penalty of Rs.
Meghalaya
Slippage of 20,00,000/-
Assam Border
Bituminous imposed on
Section of NH -
Meghalay concrete for a Contractor and
64 2025
44 from Km
a length of rectification work
69.200 to Km
approximate carried out by
173.200 (design
10-15 mtrs Contractor at his
Ch 171.455 ) in
own cost.
the state of
Meghalaya
Construction of
Dwarka
Expressway
Package-1, from
P8-P9 of flyover
Shiv Murti
part of Shiv
Remedial
Intersection at
Murti
measures
Km 20 of NH-8
Delhi 65 2023 interchange on
completed by
till road under
Dwarka
Contractor.
Bridge (RUB)
Expressway
near Dwarka
toppled.
Sector-21(From
Km -0.600 to
5.300) in the
state of DelhiYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
on EPC mode
Rehabilitation
of km 181.00 to
Km 206.00
section in
Andaman Trunk
Road of NH-4 to
Distress,
Intermediate
sinking of
Lane with hard Rectification
66 2024 pavement at
shoulder in the works completed.
various
union Territory
locations.
of Andaman &
Nicobar islands
(Total length
Andaman
25.00 km) on
&
EPC Mode”
Nicobar
(Package-VII)
Islands
Construction of
The EPC
4 Nos. of Minor
Punching in contractor has
Bridges at Km
Deck Slab (LHS) carried out the
21.717, Km
of the minor necessary
23.150, Km
bridge across rectifications at
88.300, Km
BD Nallah at their own
67 2024
92.100 of NH-
Km 88+300 and expense
223 (New NH-4)
other quality including
connecting
issues including replacement of
South Andaman
bad slab as
and Baratang
workmanship. recommended by
Island in the
CRRI-CSIR report.
Union TerritoryYear Details of
S.
State/ Name of the of Major
Action Taken
No
UT Project incid damages /
.
ent defects
of Andaman &
Nicobar Islands
on EPC mode.
*****