This document is a response to Unstarred Question No. 775 in the Lok Sabha, dated December 4th, 2025, regarding the maintenance of National Highway-27 (NH-27) in Bihar. It addresses concerns raised by Dr. Alok Kumar Suman about the incomplete and inadequate maintenance of the highway in the Gopalganj district. The response clarifies that maintenance is being handled through a Performance Based Maintenance Contract (PBMC) that commenced in July 2024.
**Key Points / Main Content**
* **Maintenance Contract:**
* The Gopalganj to Kotwa section of NH-27 maintenance is being executed through a Performance Based Maintenance Contract (PBMC).
* The PBMC is for a duration of five years and commenced in July 2024.
* **Scope of Work:**
* The maintenance contract encompasses initial rectification, routine maintenance, periodic maintenance, and emergency work within a specified timeline.
* Initial rectification work is currently underway in critical sections to ensure the road is traffic-worthy.
* Overlay/renewal work is proposed for the entire section in phases under the PBMC contractor.
* **Bridge Construction:**
* Construction of a bridge over the River Gandak is ongoing, causing traffic inconvenience.
* Efforts are being made to expedite the bridge's completion.
**Impact Analysis**
**Stakeholder: Residents and Commuters using NH-27 in Gopalganj, Bihar**
**Impact:**
* The performance based maintainence contract has the goal of improving the overall driving experience, enhancing safety and efficiency. However, the current construction of the bridge over River Gandak is causing traffic inconvenience.
**Action Required:**
* No direct action required, although the stakeholders can anticipate an improved NH-27 after project completion.
**Stakeholder: Ministry of Road Transport and Highways Officials**
**Impact:**
* The response highlights the action taken by the ministry to maintain the NH-27.
**Action Required:**
* Continued monitoring of the Performance Based Maintenance Contract (PBMC) to ensure timely completion of works.
Key Entities Referenced
NH-27: National Highway 27, the subject of the maintenance query.
Performance Based Maintenance Contract (PBMC): The contract used for the maintenance of the Gopalganj to Kotwa section of NH-27.
Ministry of Road Transport and Highways: The ministry responsible for answering the question regarding NH-27 maintenance.
Bihar: The state where the NH-27 maintenance is being questioned.
Gopalganj: The district in Bihar where the NH-27 maintenance issues are located.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 775
ANSWERED ON 4TH DECEMBER, 2025
MAINTENANCE OF NH-27 IN BIHAR
775. DR. ALOK KUMAR SUMAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether it is a fact that maintenance work of the National Highway-27 in
district Gopalganj of Bihar are still not completed since long time despite
repeated verbal as well as written communication to the officials of Ministry
concerned, if so, the reasons therefor;
(b) whether the stretch of NH-27 in district Gopalganj in Bihar is badly
maintained in comparison to Uttar Pradesh and other TRI districts, if so, the
reasons therefor;
(c) whether it is a fact that signage, pit, hole, ditch and plantation are not
properly maintained or completed at stretch of NH-27 in district Gopalganj of
Bihar, if so, the reasons therefor;
(d) whether the Government has taken any measures to direct the authority
concerned to ensure proper maintenance of stretch of NH-27 in District
Gopalganj of Bihar as per norms; and
(e) whether the Government has proposed for any contract for maintenance
of said stretch, if so, the details thereon?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (e) Maintenance of the Gopalganj to Kotwa section of NH-27 has been
taken up through Performance Based Maintenance Contract (PBMC) of five
years and commenced in July 2024. Scope of the maintenance contractincludes initial rectification, routine maintenance, periodic maintenance and
emergency work in the specified timeline.
Currently, initial rectification has been taken up in some critical sections
to keep the road in traffic worthy condition. For improving the riding quality,
overlay/renewal is proposed on the entire section in a phased manner within
the scope of PBMC Contractor. Further, construction of a Bridge over River
Gandak is under implementation causing inconvenience in seamless
movement of traffic. All efforts are being made for early completion of the
bridge.
*****