Executive Summary:
This document addresses railway-related requests and issues raised by public representatives, specifically concerning the Erode Lok Sabha Constituency. It outlines the mechanisms for addressing these concerns, details improvements and developments in railway infrastructure and services, and identifies factors affecting project timelines, including land acquisition delays. The information provided is current as of July 30, 2025, and April 1, 2025, for project-specific data.
Key Points / Main Content:
Addressing Requests and Issues:
* The Ministry of Railways receives requests for facilities, amenities, and services from various sources, including Members of Parliament and State Governments.
* These requests are examined, and action is taken based on feasibility and justification.
* A centralized compendium of requests is not maintained due to the continuous and dynamic nature of the process.
Infrastructure Development (ROBs/RUBs):
* Sanctioning and execution of Road Over Bridges (ROBs) and Road Under Bridges (RUBs) is ongoing, prioritized based on safety, mobility, and impact on road users.
* 4,148 ROBs/RUBs were constructed between 2004-14, and 13,426 between 2014-June 2025 (including 747 in Tamil Nadu).
* As of April 1, 2025, 4,402 ROBs/RUBs are sanctioned at a cost of Rs. 1,00,860 crore, including 235 in Tamil Nadu (Rs. 4,669 crore), in various stages of planning and execution.
* 13 ROBs/RUBs are sanctioned in Erode Constituency, including 3 against demanded LC locations.
Train Services:
* Erode, Kodumudi, Pasur, and Ingur stations in Erode Constituency are served by 174 train services, including 4 Vande Bharat services.
* Introduction/stoppage of trains and rationalization of timings are ongoing processes based on traffic justification and operational feasibility.
* Specific train introductions, extensions, and stoppages at Kodumudi are listed with effective dates.
Amrit Bharat Station Scheme:
* This scheme aims to develop stations continuously with a long-term approach, improving amenities and integrating stations with the city.
* 1,337 stations, including Erode Junction and 77 stations from Tamil Nadu, have been identified for development.
* Phase I works of 9 stations in Tamil Nadu have been completed.
* At Erode Junction, improvement work on circulating area, parking, and a new commercial building have been completed. Other works have been taken up.
Railway Projects in Tamil Nadu:
* As of April 1, 2025, 15 projects (9 New Line, 3 Gauge Conversion, and 3 Doubling) of total length 1,700 Km, costing ₹22,808 Crore are sanctioned, out of which 665 Km length has been commissioned and an expenditure of ₹7,591 Crore has been incurred upto March 2025.
* Budget allocation for infrastructure and safety works in Tamil Nadu has increased from ₹879 crore/year (2009-14) to ₹6,626 crore (2025-26).
* Surveys have been sanctioned for Jolarpettai-Erode-Coimbatore 3rd and 4th line (282 Km) and Erode-Karur Doubling (67 Km).
Land Acquisition Delays:
* Project execution is affected by delays in land acquisition.
* Out of 4315 Ha required, 1038 Ha (24%) has been acquired, leaving a balance of 3277 Ha (76%).
* Specific projects delayed due to land acquisition are listed, including Tindivanam-Tiruvannamalai new line and Attiputtu-Puttur New Line.
Impact Analysis:
Government of Tamil Nadu:
* Impact: Support is needed to expedite land acquisition for railway projects. Delays in land acquisition impede project progress and impact completion timelines and costs.
* Action Required: Expedite land acquisition processes and provide necessary support for railway projects.
Railway Authorities:
* Impact: Responsible for examining requests, prioritizing and executing infrastructure projects, and managing train services.
* Action Required: Continue to assess requests, prioritize projects based on established criteria, and address factors affecting project timelines, including coordination with the State Government.
Elected Representatives (Including Shri K E Prakash):
* Impact: Act as a conduit for relaying public concerns and requests related to railway services in their constituencies.
* Action Required: Continue to represent constituency-level railway issues and requests, and engage with railway authorities to facilitate improvements.
General Public/Rail Users:
* Impact: Benefit from improved railway infrastructure, enhanced amenities, and better train services. Delays in project completion and land acquisition can negatively impact these benefits.
* Action Required: Engage with elected representatives and relevant authorities to voice their needs and concerns regarding railway services.
Key Entities Referenced
Erode Lok Sabha Constituency: A parliamentary constituency in Tamil Nadu, represented by an elected Public Representative, from where requests regarding railway services are received.
Ashwini Vaishnaw: The Minister of Railways, Information Broadcasting and Electronics Information Technology.
Railway Board: A body that receives proposals, complaints, and suggestions related to railway facilities and services.
Indian Railways: The national railway system of India, responsible for the construction, maintenance, and operation of railway infrastructure and services.
Tamil Nadu: A state in southern India where several railway projects are underway and where land acquisition is crucial for project completion.
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the development and upgradation of railway stations on a continuous basis.
Erode Junction station: A railway station in Erode, Tamil Nadu, which has been identified for development under the Amrit Bharat Station Scheme.
NITI Aayog: A policy think tank of the Government of India, involved in the appraisal of railway projects.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 148
TO BE ANSWERED ON 30.07.2025
MECHANISM TO MONITOR RAILWAY ISSUES
*148. SHRI K E PRAKASH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether it is a fact that the Government has received requests from
the elected Public Representative from Erode Lok Sabha Constituency on
various issues relating to railway services being faced by the people there;
(b) if so, the details thereof along with the steps taken thereon;
(c) the reasons for delays in the current system for addressing such
constituency-specific requests; and
(d) whether the Government proposes to establish any separate
body/board/mechanism to systematically monitor/follow up on
constituency-level railway issues and requests made by the elected
representatives and if so, the details thereof ?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
******STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA
STARRED QUESTION NO. 148 TO BE ANSWERED ON 30.07.2025
(a) to (d): Proposals/requests/suggestions/representations, both formal
and informal for provision of various facilities/amenities/services for
passengers across the country are received on the basis of demands
raised by State Governments, Members of Parliament, elected
representatives, Railways’ own requirements, organizations/rail users etc.
at various levels including Railway Board, Zonal Railways, Division Office
etc. As receipt of such proposals/complaints/suggestions is a continuous
and dynamic process, centralized compendium of such requests is not
maintained. However, these are examined and action as found feasible and
justified is taken from time to time.
As far as Erode constituency is concerned, various representations
for provision of Road Over Bridge (ROB)/Road Under Bridge (RUBs),
Railway Waterway Bridge, stoppage of trains, etc. have been received.
ROBs/RUBs
Sanctioning and execution of works of Road Over Bridges/Road Under
Bridges (ROBs/RUBs) in lieu of Level Crossings (LCs) is a continuous and
ongoing process on Indian Railways. Such works are prioritized and taken
up on the basis of its impact on safety and mobility in train operations and
impact on road users.
Number of ROBs/RUBs constructed on Indian Railways during the
period 2004-14 vis a vis 2014-25 (June’25) is as under:
Period ROBs/RUBs constructed
2004-14 4,148
2014-25 13,426 (including 747 in the State of Tamil Nadu)
(June’25)As on 01.04.2025, 4,402 ROBs/RUBs are sanctioned at the cost of
Rs. 1,00,860 crore on Indian Railways including 235 (ROBs)/(RUBs) at the
cost of Rs. 4,669 crore in the State of Tamil Nadu, which are at various
stages of planning and execution.
Presently, 13 ROBs/RUBs are sanctioned in Erode Constituency
which includes 03 Nos. ROBs sanctioned against demanded LC locations.
Introduction/stoppage of trains
At present, Erode, Kodumudi, Pasur and Ingur, which are major
stations located in Erode Lok Sabha Constituency, are being served by
174 train services (including 4 Vande Bharat train services), 14, 8 and 6
train services respectively. Besides, provision of stoppage of trains and
rationalisation of timings of train services is an on-going process on Indian
Railways, subject to traffic justification, operational feasibility, etc.
Train introduced/extended, serving Erode
Item Train No. and Name With effect from
Introduction 18189/90 Tata Nagar – Ernakulam 28.01.2021
Express
Introduction 20643/44 Coimbatore – MGR Chennai 08.04.2023
Central Vande Bharat Express
Introduction 20641/42 Coimbatore – Bangalore Cantt. 30.12.2023
Vande Bharat Express
Introduction 17421/22 Tirupati – Kollam Express 15.03.2024
Extension 16845/46 Erode – Tirunelveli Express 24.01.2024
upto Sengottai
Stoppages of train services provided at Kodumudi
Item Train No. and Name With effect from
Stoppage 16188 Ernakulam – Karaikkal Express 18.07.2023
Stoppage 16235 Tuticorin – Mysuru Express 19.07.2023Provision of Infrastructure
Ministry of Railways has launched Amrit Bharat Station Scheme for
development of stations on a continuous basis with a long-term approach.
It involves preparation of master plans and their implementation in phases
to improve the amenities at the stations like improvement of station
access, circulating areas, waiting halls, toilets, lift/escalators as
necessary, platform surfacing and cover over platform, cleanliness, free
Wi-Fi, kiosks for local products through schemes like ‘One Station One
Product’, better passenger information systems, executive lounges,
nominated spaces for business meetings, landscaping, etc. keeping in
view the necessity at each station.
The scheme also envisages improvement of building, integrating
the station with both sides of the city, multimodal integration,
amenities for Divyangjans, sustainable and environment friendly
solutions, provision of ballastless tracks, etc. as per necessity,
phasing and feasibility and creation of city centre at the station in the
long term.
So far, 1,337 stations covering 77 stations from the state of
Tamil Nadu including Erode Junction station have been identified for
development under the Amrit Bharat Station Scheme. Development
works at railway stations under Amrit Bharat Station Scheme in the state
of Tamil Nadu have been taken up at a good pace. Till now, phase-I works
of 09 stations (Chidambaram, Kulitturai, Mannargudi, Polur, Samalpatti,
Srirangam, St.Thomas Mount, Tiruvannamalai, Vriddhachalam Jn) in the
state of Tamil Nadu have been completed under this scheme.At Erode Junction station, work of improvement of circulating
area, improvement of parking area and construction of new
commercial building has been completed. Work of improvement of
platforms, new platform shelter, 12 m Foot Over Bridge, lift and
escalators have been taken up.
Development/Upgradation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are undertaken
as per requirement, subject to inter-se priority and availability of funds.
The priority for development/upgradation of stations is accorded to higher
category of station over lower category of station while sanctioning and
executing the works.
Implementation of different projects in Southern Railway/Erode
Railway projects in Tamil Nadu are covered by Southern Railway
(SR), South Central Railway (SCR) and South Western Railway (SWR) zone
of Indian Railways. Zonal Railway wise details of Railway projects are
made available in public domain on Indian Railway’s website.
As on 01.04.2025, 15 projects (9 New Line, 03 Gauge Conversion and
03 Doubling) of total length 1,700 Km, costing ₹22,808 Crore, falling
fully/partly in the State of Tamil Nadu, are sanctioned, out of which 665 Km
length has been commissioned and an expenditure of ₹7,591 Crore has
been incurred upto March’ 2025. The summary is as under:-
Plan Head No. of Total Length Expenditure
projects Length Commissioned upto March 2025
(in Km) (in Km) (₹in Cr.)
New Line 9 812 24 1,337
Gauge Conversion 3 748 604 3,471
Doubling 3 140 37 2,783
/Multitracking
Total 15 1700 665 7,591Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2025-26 ₹ 6,626 crore (more than 7.5 times)
To further improve connectivity of Erode, following surveys have been
sanctioned for preparing the Detailed Project Report (DPR): -
(i) Jolarpettai – Erode – Coimbatore 3rd and 4th line (282 Km)
(ii) Erode – Karur Doubling (67 Km)
After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
Execution of important infrastructure projects falling fully/partly in the
State of Tamil Nadu are held up due to delay in land acquisition. Status of
land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4315 Ha
Land Acquired 1038 Ha ( 24%)
Balance Land to be acquired 3277 Ha ( 76%)
Support of the Government of Tamil Nadu is needed to expedite the
land acquisition. Details of some major projects which are delayed due to
land acquisition are as under:-S. Name of the project Total Land Balance
No. land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Tindivanam–Tiruvannamalai new 273 33 240
line (71 km)
2. Attiputtu – Puttur New Line (88 189 0 189
km)
3. Morappur – Dharmapuri (36 km) 93 42 51
4. Mannargudi-Pattukkottai (41 196 0 196
km)
5. Thanjavur-Pattukottai (52 km) 152 0 152
Government of India is geared up to execute projects, however
success depends upon the support of Government of Tamil Nadu.
Completion of Railway project/s depends on various factors like quick
land acquisition by State Government, forest clearance by officials of
forest department, shifting of infringing utilities, statutory clearances from
various authorities, geological and topographical conditions of area, law
and order situation in the area of project/s site, number of working months
in a year for particular project site etc. All these factors affect the
completion time and cost of the project/s.
*****