Parliament Question: Metro Rail Projects in Uttar Pradesh

Issued by Ministry of Housing and Urban Affairs · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary:** This document summarizes the status of metro rail projects in Uttar Pradesh as of August 7, 2025, in response to Lok Sabha Unstarred Question No. 3113. It details the operational length and ridership of existing metro networks in Lucknow, Kanpur, Agra, Noida, and Ghaziabad. It also covers the status of ongoing and planned metro projects, including timelines and cost information, and considerations for new project approvals. **Key Points / Main Content:** * **Current Operational Metro Length and Ridership (as of August 7, 2025):** * Lucknow: 22.878 km, 78,000 average daily ridership. * Kanpur: 15.00 km operational (out of 32.38 km total), ridership not specified for operational section. * Agra: 6.00 km operational (out of 29.4 km total), ridership not specified for operational section. * Noida: 29.707 km, 59,648 average daily ridership. * Delhi Metro (Noida): 17.761 km, 5,67,896 footfalls. * Delhi Metro (Ghaziabad): 11.9 km, 1,89,858 footfalls. * Delhi-Meerut RRTS (Ghaziabad): 40.6 km operational, ridership not specified for operational section. * Delhi-Meerut RRTS (Meerut): 3.6 km operational (out of 28.05 km total), ridership not specified for operational section. * **Ongoing Metro Projects:** * Lucknow Metro Phase 1B (Charbagh to Vasantkunj): Proposal received for 11.165 km at a cost of Rs. 5,801.05 Crore, with a projected completion period of 5 years from the date of sanction. * Kanpur Metro Rail Project: 32.38 km at a cost of Rs. 11,076.48 Crore, already sanctioned, no cost overruns reported. * Agra Metro Rail Project: 29.4 km at a cost of Rs. 8,379.62 Crore, already sanctioned, no cost overruns reported. * **Planned/Proposed Metro Projects:** * Urban planning is a State subject, and State Governments are responsible for planning urban transport infrastructure. * Meerut Metro: 21.15 km, integral part of the Delhi-Meerut RRTS project. * Lucknow-Kanpur RRTS: Not part of the National Capital Region (NCR), where RRTS projects are prioritized. * Gorakhpur Metro: Proposed, but metro project approvals depend on factors like population size, traffic, development plans, feasibility, and resource availability. **Impact Analysis:** * **Government of Uttar Pradesh:** * *Impact:* Responsible for planning and initiating urban transport infrastructure projects, including metros and RRTS. Responsible for Lucknow-Kanpur RRTS project which is not part of NCR. * *Action Required:* Continue planning and initiating urban transport infrastructure projects. * **Uttar Pradesh Metro Rail Corporation Limited (UPMRCL):** * *Impact:* Implementing agency for metro projects in Lucknow, Kanpur, and Agra. * *Action Required:* Continue implementing the metro projects in Lucknow, Kanpur and Agra. * **Ministry of Housing and Urban Affairs (Government of India):** * *Impact:* Responsible for approving and prioritizing metro project proposals based on various factors. * *Action Required:* Review the proposal for Lucknow Metro Phase 1B and prioritize metro projects based on feasibility and resource availability.

Key Entities Referenced

Uttar Pradesh: A state in India where the mentioned metro rail projects are located. Lucknow: The capital city of Uttar Pradesh, with ongoing metro rail projects and operational metro lines. Kanpur: A city in Uttar Pradesh with sanctioned metro rail projects. Agra: A city in Uttar Pradesh with sanctioned metro rail projects. Noida: A city in Uttar Pradesh with operational metro lines and connections to the Delhi Metro. Ghaziabad: A city in Uttar Pradesh connected to Delhi via the Delhi Metro and part of the Delhi Meerut RRTS project. Lucknow-Kanpur Regional Rapid Transit System (RRTS): A planned rapid transit system project connecting Lucknow and Kanpur in Uttar Pradesh. Delhi Meerut RRTS: A sanctioned Regional Rapid Transit System project connecting Delhi and Meerut.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF HOUSING AND URBAN AFFAIRS LOK SABHA UNSTARRED QUESTION NO. 3113 TO BE ANSWERED ON AUGUST 07, 2025 METRO RAIL PROJECTS IN UTTAR PRADESH NO. 3113. SMT. DIMPLE YADAV: Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state: (a) the current operational length of metro networks in Uttar Pradesh (Lucknow, Kanpur, Agra, Noida and Ghaziabad) along with the average daily ridership, city-wise; (b) the status and projected timelines for completion of ongoing metro phases including Lucknow Phase-2, Kanpur corridors and Agra Phase-2 along with details of cost overruns or delays, if any; and (c) the new metro or rapid transit projects currently under planning or Detailed Project Report (DPR) stage in Uttar Pradesh including the Lucknow-Kanpur Regional Rapid Transit System (RRTS), Meerut Metro and Gorakhpur Metro along with their expected commencement dates? ANSWER THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS (SHRI TOKHAN SAHU) (a): The details of current operational length of metro and RRTS networks in Uttar Pradesh along with average daily ridership are given in Annexure-I. (b): This ministry has received proposal for Lucknow metro Phase-1B from Charbagh to Vasantkunj of 11.165 route Km at a cost of Rs. 5,801.05 Crore with projected completion period of 5 years from date of sanction. The Kanpur Metro Rail Project of 32.38 route Km at a cost Rs.11,076.48 Crore and Agra Metro Rail Project of 29.4 route Km at a cost of Rs.8,379.62 Crore have already been sanctioned. UP Metro Rail Corporation Limited (UPMRCL), which is implementing agency for metro projects in Lucknow, Kanpur and Agra has informed that there is no cost overrun in these projects. …2/--2- (c): ‘Urban planning’ is a State subject, therefore, the respective State Governments are responsible for planning, initiating and developing urban transport infrastructure including metro and Regional Rapid Transit system Projects (RRTS). Meerut metro rail system of 21.15 Km is integral part of already sanctioned Delhi- Meerut RRTS project. As per extant policy, RRTS project are planned for implementation only in NCR. Lucknow- Kanpur is not a part of NCR. Metro projects including that of Gorakhpur are cost intensive requiring extensive examination at different level in Central Government. Metro project proposals of different cities are prioritized for approval based on many factors like size of population, peak hour traffic, development plans etc. Further, the approval of such proposal is always dependent upon feasibility of proposal and availability of resources to ensure long term sustainability of such projects. *****Annexure I ANNEXURE REFERRED TO IN REPLY TO PART (a) OF THE LOK SABHA QUESTION NO. 3113 FOR ANSWER ON 07.08.2025 REGARDING METRO RAIL PROJECTS IN UTTAR PRADESH ASKED BY SMT. DIMPLE YADAV THE DETAILS OF CURRENT OPERATIONAL LENGTH OF METRO NETWORKS IN UTTAR PRADESH, AVERAGE DAILY RIDERSHIP, CITY- WISE: S. Name of Metro Rail State City Total Operational Average Daily No. Project Length (in Length (in Kms) Ridership Kms) Lucknow Metro Rail Uttar Pradesh Lucknow 22.878 22.878 78,000 Project Kanpur Metro Rail Kanpur 32.38 15.00 Only partial section Project is operational Agra Metro Rail Agra 29.4 6.00 Only partial section Project is operational Noida Metro Rail Noida 29.707 29.707 59,648 Project Delhi Metro Noida 17.761 17.761 5,67,896 (footfalls) Corridors in Noida Delhi Metro Ghaziabad 11.9 11.9 1,89,858 (footfalls) Corridors in Ghaziabad Delhi Meerut (RRTS) Ghaziabad 40.6 40.6 Only partial section is operational Meerut 28.05 3.6 Total 212.676 147.446