GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4213
TO BE ANSWERED ON 18.03.2026
MINIMAL ENVIRONMENTAL IMPACT AND RAILWAY PROJECT
4213. SHRI ARUN BHARTI:
SHRI MUKESHKUMAR CHANDRAKAANT DALAL:
SHRI RAJESH VERMA:
SMT. SHAMBHAVI:
DR. LATA WANKHEDE:
SHRI ATUL GARG:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the railway infrastructure project for which approval has
been sought from the Central Government including the scope of track
expansion, conversion or new line construction and its expected
benefits for connectivity, freight and passenger services particularly in
Bihar, Gujarat, Madhya Pradesh and Uttar Pradesh;
(b) the number of trees and extent of forest land likely to be affected by
the project and the current status of statutory clearances under the
Forest (Conservation) Act and other environmental regulations;
(c) the details of measures proposed to minimise environmental impact
including compensatory afforestation, biodiversity protection and other
mitigation strategies;
(d) the details of institutional mechanisms in place for monitoring
environmental compliance during the project’s execution; and
(e) the details of assessments conducted regarding the ecological, social
and operational impact of the project including alternative alignments
or methods to reduce forest loss?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Capacity enhancement of railway network has been taken up by
Indian Railways in a big way during last 11 years. The details of
..P/2
§-:2:-
commissioning/laying of new track across Indian Railways is given below:-
New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
The status of projects situated in Bihar, Gujarat, Madhya Pradesh and Uttar
Pradesh are as under:
Bihar
Railway Budget:
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the State of Bihar is as under:
Period Outlay
2009-14 1,132 Cr./year
2025-26 10,066 Cr. (Nearly 9 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Bihar during 2009-14 and 2014-25 is as under:-
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 318 Km 63.6 Km/year
2014-25 1,899 Km 172.6 Km/year (More than 2.5 times)
..P/3-:3:-
Projects sanctioned:
As on 01.04.2025, 52 projects (31 New Lines, 01 Gauge Conversions and 20
Doubling), of a total length of 4,663 km, costing ₹86,107 crore, falling
fully/partly in Bihar, are sanctioned, out of which 1,014 km length has been
commissioned and an expenditure of 29,353 crore has been incurred upto
March’ 2025. The summary is as under:-
Length Total Exp
No of Total Length
Commissioned upto
Category sanctioned NL/GC/DL
till Mar'25 Mar'25
Projects (in Km)
(in Km) ( in Crore)
New Lines 31 2,691 516 16,814
Gauge
1 69 52 544
Conversion
Doubling/Multi-
20 1,904 446 11,995
tracking
Total 52 4,663 1,014 29,353
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Details of some of the recently completed projects falling fully/partly in
Bihar are as under:-
SN. Project Cost
( in Crore)
1 Patna rail cum road Bridge (28 Km) 3,210
2 Munger rail cum road Bridge (15 km) 3,040
3 Kosi Bridge (22 km) 863
4 Daniawan-Biharsharif New Line (38 km) 354
5 Chandan-Banka New Line (40 km) 496
..P/4-:4:-
6 Rampurhat-Mandarhill New Line (130 km) 908
7 Maharajganj-Masrakh New Line (35 km) 412
8 Rajgir-Tilaiya & Natesar-lslampur New Line (67 726
km)
9 Mansi-Saharsa-Purnia Gauge Conversion (141 km) 752
10 Jaynagar-Narkatiaganj Gauge Conversion (260 km) 967
11 Kaptanganj-Chhapra Gauge Conversion ( 234 km) 819
12 Sakri-Nirmali & Saharasa-Forbesganj Gauge 2,113
Conversion (206 km)
13 Mansi-Saharsa, Saharsa-Purnia & Banmakhi- 752
Bihariganj Gauge Conversion (169 km)
14 Sahibganj-Pirpainti Doubling (23 km) 129
15 Maheshkunt-Thanabihpur Doubling (32 km) 115
16 Hajipur-Ramdayalu Nagar Doubling (48 km) 367
17 Pirpainti-Bhagalpur Doubling (51 km) 493
18 Bakhtiyarpur-Barh Doubling (19 km) 237
19 Kiul-Gaya Doubling (124 km) 2,462
20 Hajipur-Bachwara Doubling (72 km) 930
21 Darbhanga bypass (9 km) 253
22 Araria-Galgalia (Thakurganj) New Line (110 km) 2,132
23 Saraigarh Byepass Line (5 km) 79
24 Chhapra-Chhapra Kacheri 3rd Line (3 km) 33
Some of the projects falling fully/partly in the State of Bihar which have
been taken up are as under:
..P/5-:5:-
SN. Project Cost
( in Crore)
1 Sakri-Hasanpur new line (76 km) 735
2 Khagaria-Kusheshwarsthan New line (42 km) 1,511
3 Fatuha-lslampur new line (167 km) 2,882
4 Koderma-Tilaiya new line (65 km) 1,980
5 Hajipur-Sagauli new line (151 km) 2,702
6 Araria-Supaul new line (96 km) 1,925
7 Kursela-Bihariganj new line (58 km) 194
8 Bikramshila-Katareah new line (26 km) 2,171
9 Jhajha-Batia new line (20 km) 588
10 Pirpainti-Jassidih new line (97 km) 2,611
11 Chhitauni-Tumkuhi Road new line (59 km) 1,731
12 Jalalgarh-Kishanganj new line (51 km) 360
13 Jogbani-Biratnagar (Nepal) new line (19 km) 402
14 Darbhanga-Kusheshwarasthan new line (70 km) 367
15 Motihari-Sitamarhi new line (77 km) 1,007
16 Sitamarhi-Nirmali new line (189 km) 2,833
17 Nawada-Laxmipur new line (137 km) 3,121
18 Ara-Bhabua Road new line (150 km) 2,397
19 Gaya-Daltonganj new line (137 km) 2,861
20 Muzaffarpur-Darbhanga new line (69 km) 282
21 Muzaffarpur-Janakpur Road new line (67 km) 228
22 Dehri on Sone-Banjari new line (35 km) 111
23 Chhapra-Muzzafarpur new line (78 km) 1,894
..P/6-:6:-
SN. Project Cost
( in Crore)
24 Bihta-Aurangabad new line (120 km) 2,995
25 Gaya-Chatra and Gaya-Natesar new line (135 km) 4,543
26 Deogarh-Sultanganj new line incl.Banka-Barahat and 665
Banka-Bhitiah Road (154 km)
27 Sultanganj-Katuria new line (77 km) 291
28 Bariarpur-Mananpur new line (68 km) 251
29 Hathua-Bhatni new line (80 km) 318
30 Aurangabad Terminal-Anugrah Narayan Road new line 441
(13 km)
31 Nawadah-Pawapuri New line (25 km) 492
32 Jaynagar-Bijalpura Gauge conversion (69 km) 790
33 Dhanbad-Sonnagar 3rd line (291 km) 7,906
34 Samastipur-Darbhanga Doubling (38 km) 826
35 Rampur Dumra-Tal-Rajendra Pul-Additional bridge and 2,535
Doubling (14 km)
36 Sagauli-Valmikinagar Doubling (110 km) 1,456
37 Gaya Bye pass for Manpur (2 km) 30
38 Muzaffarpur-Sugauli Doubling (101 km) 1,586
39 Barauni-Bachwara 3rd & 4th line (32 km) 486
40 Sonenagar bye pass (Chiralapothu to Bagha 224
Bishunpur) (10 km)
41 Narkatiaganj-Darbhanga & Sitamarhi-Muzaffarpur 4,080
Doubling (256 km)
42 Chhapra-Ballia Patch Doubling (65 km) 1,046
43 Gorakhpur-Valmikinagar Doubling (96 km) 1,121
..P/7-:7:-
SN. Project Cost
( in Crore)
44 Katihar-Kumedpur and Katihar-Mukuria Doubling (65 943
km)
45 Bhadaura Station and Karma Station Surface Triangle 200
Line (11 km)
46 ROR at Sasaram connecting GC to Ara-Sasaram Line (9 470
km)
47 Ara Bye pass Line to be connected from Jagjivan Halt 119
to existing ARA-Sasaram line through link cabin (Y-
Connectivity at Ara) (3 km)
48 Son Nagar-Andal Multitracking (749 km) 12,334
49 Bulb line at Nabinagar (Ankorha) (17 km) 612
50 Punarakh- Barh-Bhaktiyarpur New 4th line & balance 422
3rd line (28 km)
51 Sanjaygram to Dhachna By Pass line (2 km) 34
52 Aluabari Road-Thakurganj Doubling (20 km) 327
53 Aluabari Road-New Jalpaiguri 3rd & 4th Line (57 km) 1,630
54 Bhagalpur-Jamalpur 3rd Line (53 km) 1,156
55 Bhagalpur-Dumka-Rampurh at Doubling (177 km) 3,169
56 Bakhtiyarpur-Rajgir-Tilaiya Doubling (104 km) 2,192
57 Bakthiyarpur-Fatuha 3rd and 4th line (24 km) 931
Gujarat
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Gujarat is as under:
..P/8-:8:-
Period Outlay
2009-14 ₹ 589 crore/year
2025-26 ₹ 17,155 crore (More than 29 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Gujarat during 2009-14 and 2014-25 is as under:
Period New Track Average Commissioning of new
Commissioned tracks
2009-14 660 Km 132 Km/year
2014-25 2,764 Km 251 Km/yr (nearly 2 times)
Projects sanctioned:
As on 01.04.2025, 36 Railway projects (6 New Lines, 17 Gauge Conversion
and 13 Doubling), of a total length of 2,564 Km, costing ₹30,275 crore,
falling fully/partly in the State of Gujarat have been sanctioned. The
summary is as under:-
Category No. of Total Length Total Expenditure
sanctioned length commissioned upto Mar'25
projects (Km) upto Mar'25 (₹ in Crore)
(Km)
New Lines 6 532 105 5,494
Gauge
17 1,379 718 6,213
Conversion
Doubling /
13 653 40 1,158
Multitracking
Total 36 2,564 863 12,865
..P/9-:9:-
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Details of some of the completed projects falling fully/partly in the State of
Gujarat are as under:
S.No. Name of Project Cost
(₹ in Crore)
1 Mahesana-Taranga Hill Gauge Conversion (210 891
Km)
2 Himmatnagar-Khedbrahma Gauge Conversion 482
(55 Km)
3 Ahmedabad-Botad Gauge Conversion (170 Km) 1,810
4 Dhasa-Jetalsar Gauge Conversion (104 Km) 1,024
5 Ahmedabad-Mahesana Gauge Conversion (69 874
Km)
6 Katosan-Chanasma Gauge Conversion (38 Km) 484
7 Kalol-Kadi-Katosan Gauge Conversion (37 Km) 347
8 Vijapur-Ambliyasan Gauge Conversion (42 Km) 415
9 Dabhoi-Chandod with extension up to Kevadiya 1,018
Gauge Conversion (50 Km)
10 Viramgam-Samakhiali Doubling (182 Km) 1,492
11 Palanpur-Samakhayali Doubling (247 Km) 2,538
12 Mahesana-PalanpurDoubling (65 Km) 537
13 Surendranagar-Rajkot Doubling (116 Km) 1,425
14 Anand-GodharaDoubling (79 Km) 692
15 Vatva-Ahmedabad 3rd Line (8 Km) 61
16 Viramgram-Surendranagar Doubling (65 Km) 382
17 Udhna-Jalgaon Doubling (307 Km) 2,448
..P/10-:10:-
Details of some of the projects falling fully/partly in the State of Gujarat
which have been taken up are as under:
S. No. Project Cost
(₹ in Crore)
1 Naliya-Jakhau Port New Line (25 Km) 410
2 Miyagam Karjan-Choranda-Malsar Gauge Conversion 450
(37 Km)
3 Jambusar-Kavi Gauge Conversion (26 Km) 318
4 Kosamba-Umarpada Gauge Conversion (70 Km) 468
5 Khijadiya-Amreli Gauge Conversion (17 Km) 178
6 Barejadi-Nandej (Geratpur)- Sanand 4th Line (38 Km) 962
7 Samakhiali-Gandhidham Quadrupling (53 Km) 1,430
8 Vishvamitri-Dabhoi Doubling (33 Km) 394
9 Taranga Hill- Ambaji-Abu Road New Line (116 Km) 2,798
10 Sabarmati D Cabin- Sarkhej Doubling (21 Km) 323
11 Deshalpar-Hajipir-Luna and Vayor-Lakhpat New Line 2526
(145 Km)
12 Vadodara-Ratlam 3rd & 4th Line (259 Km) 8,387
13 Rajkot-Kanalus Doubling (111 Km) 1,081
Bullet Train project:
The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is the
only HSR Project under execution. The Project is passing through the
States of Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli
with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora,
Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
..P/11-:11:-
Entire land (1,389.5 Ha.) for MAHSR project has been acquired. All
Statutory Clearances have been obtained. All 1,651 utilities have been
shifted. The delay in land acquisition in the State of Maharashtra has
impacted the project till 2021. The land acquisition picked up in 2022 in
Maharashtra.
The progress of various major items so far is as under:
Gujarat (352 KM):
Item Progress
Foundation 352 kms.
Piers 352 kms.
Girder Casting 342 kms.
Girder Launching 331 kms.
Track Bed Construction 152 kms.
OHE Masts Erection 121 kms.
Maharashtra (156KM):
Item Progress
Foundation 84 kms.
Piers 75 kms.
Girder Casting 12 kms.
Girder Launching 5 kms.
Out of total 12 stations, foundation works has been completed at 8 stations
(Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and
Sabarmati). In Maharashtra section, foundation work is in progress at 3
stations (Thane, Virar, Boisar) and excavation work at BKC station is near
completion and Casting of base slab started.
..P/12-:12:-
17 river bridges have been completed. Work is in advance stage for 4 major
river bridges (Narmada, Mahi, Tapti and Sabarmati) in Gujarat & in progress
in 4 river bridges in Maharashtra. Work on Depots (Thane, Surat and
Sabarmati) is in full swing.
Civil works at Bandra Kurla Complex (BKC) are progressing satisfactorily.
Excavation works have achieved about 91% progress, and concreting
works are at various stages, with 100% completion of the basement slab at
Level-4. The work of the under-sea tunnel (approximately 21 km) has
commenced, out of which 4.8 km of tunnel between Ghansoli and Shilphata
in Maharashtra has been completed.
To ensure seamless passenger connectivity, the Government has planned
multi-modal integration of Bullet Train stations with the existing Mumbai
suburban railway network and upcoming metro lines. The integration
includes passenger connectivity with Metro Line-2B and Metro Line-3
through convenient pedestrian access at BKC station.
Bullet train project is a very complex and technology intensive Project.
Exact timelines for the completion of the project can be reasonably
ascertained after the completion of all associated works of Civil
Structures, Track, Electrical, Signaling & Telecommunication and supply of
Trainsets.
Madhya Pradesh
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for Infrastructure projects and safety works, falling fully/partly in
the State of Madhya Pradesh is as under:
..P/13-:13:-
Period Outlay
2009-14 ₹632 crore/year
2025-26 ₹14,745 crore (More than 23 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Madhya Pradesh during 2009-14 and 2014-25 is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 145 Km 29 Km/year
2014-25 2,651 Km 241 Km/year (More than 8 times)
Projects sanctioned:
As on 01.04.2025, 24 Railway projects (08 New Lines, 02 Gauge Conversion
and 14 Doubling), of total length of 4,740 Km costing ₹89,542 crore falling
fully/partly in the State of Madhya Pradesh are sanctioned. The summary is
as under:
Category No. of Total Length Length Total Exp upto
projects (in Km) Commissioned Mar'25 (₹ in Cr)
(in Km)
New Lines 8 1,914 544 15,069
Gauge
2 809 430 6,766
Conversion
Doubling /
14 2,017 1,118 19,566
Multitracking
Total 24 4,740 2,093 41,401
..P/14-:14:-
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Details of some of the recently completed projects falling fully/partly in the
State of Madhya Pradesh are as under:
S.No. Name of Project Cost
(₹ in Crores)
1. Anuppur-Katni 3rd line (165 Km) 2,311
2. Pendra Road-Anuppur 3rd line (50 Km) 394
3. Khodri-Anuppur Doubling with flyover at Bilaspur (72 792
Km)
4. Bhopal-Bina 3rd line (145 km) 1,075
5. Bina-Kota Doubling (283 km) 2,477
6. Jabalpur-Gondia Gauge Conversion including 2,005
Balaghat-Katangi (300 Km)
7. Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
8. Chhindwara-Mandla Fort Gauge Conversion (182 Km) 1,268
9. Ghat Pindari-Balkheda Doubling (6 Km) 29
10. Guna-Ruthiyai Doubling (20 Km) 175
11. Jukhei Chord line, Bye Passing the Katni Yard (2 Km) 12
12. Sontalai-Bagratawa Doubling (7 Km) 110
13. Itarsi-Budhni 3rd line (25 Km) 286
14. Teegaon-Chichonda Ghat Section 3rd line (17 Km) 176
15. Barkhera-Bhopal 3rd line (41 km) 473
16. Nagda-Ujjain Doubling of Gambhir Bridge (2 Km) 28
17. Nimach-Chittaurgarh Doubling (56 Km) 560
..P/15-:15:-
S.No. Name of Project Cost
(₹ in
Crores)
18. Budhni-Barkhera 3rd line (27 Km) 1,703
19. Indore-Dewas-Ujjain Doubling (79 Km) 757
20. Powerkheda-Jujharpur Rail flyover (16 Km) 443
21. Guna- Etawah New Line (348 Km) 683
22. Ramna-Singrauli doubling (160 Km) 2,436
23. Karaila Road- ShaktinagarDoubling(32 Km) 763
24. Malkhedi-Mahadeokhedi Doubling (12 Km) 59
Some of the projects falling fully/partly in the State of Madhya Pradesh
which have been taken up are as under:
S.No. Project Cost
(₹ in Crores)
1. Shahdol-Singhpur 4th Line (6 Km) (passing through
54
Shahdol constituency)
2. Katni- Grade separator / Bypass (35 Km) 2,300
3. Katni- Singrauli Doubling (257 Km) 4,377
4. Lalitpur-Satna, Rewa-Singrauli & Mahoba-
8,914
Khajuraho New Line (541 Km)
5. Ramganjmandi-Bhopal New Line (277 Km) 5,073
6. Indore-Budni New Line (198 Km) 7,474
7. Nimach-Badi Sadri New Line (48 Km) 495
8. Gwalior-Sheopurkalan Gauge Conversion with
2,913
extension to Kota (284 Km)
9. Itarsi- Nagpur 3rd line (280 Km) 2,450
..P/16-:16:-
S.No. Project Cost
(₹ in Crores)
10. Jhansi-Bina 3rd line (153 Km) 2,002
11. Mathura-Jhansi 3rd line (274 Km) 5,924
12. Jhansi-Kairar-Manikpur&Khirar-Bhimsen Doubling 4,330
(431 Km)
13. Satna-Rewa Doubling (50 Km) 590
14. Ruthiyai Bye Pass line (3 Km) 54
15. Guna Bye Pass line (2 Km) 179
16. Ujjain Fly Over (2 Km) 100
17. Manmad - Indore New Line (360 Km) 18,529
18. Bhusawal-Khandwa 3rd & 4th Line (131 Km) 3,285
19. Dahod-Indore New Line (205 Km) 9,746
20. Nimach-Ratlam Doubling (133 Km) 1,096
21. Chhota Udepur-Dhar New Line (147 Km) 1,794
22. Ratlam-Nagda 3rd and 4th line (41 Km) 964
23. Vadodara-Ratlam 3rd and 4th line (259 Km) 8,387
24. Ratlam-Khandwa Gauge Conversion (299 Km) 7,265
25. Bina-Itarsi 4th Line (237 km) 4,329
26. Itarsi-Nagpur 4th Line (297 Km) 5,010
Uttar Pradesh:
Railway Budget:
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Uttar Pradesh is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2025-26 ₹19,858 crore (Nearly 18 times)
..P/17-:17:-
Track construction:
The details of constructing new tracks falling fully/partly in the State of
Uttar Pradesh during 2009-14 and 2014-25 is as under:
New Track
Period Average Commissioning of new tracks
Commissioned
2009-14 996 Km 199 Km/year
2014-25 5,272 Km 479 Km per year (More than 2 times)
Projects sanctioned:
As on 01.04.2025, 49 projects (10 New Line, 02 Gauge Conversion and 37
Doubling) of 3,807 Km length, costing ₹62,360 crore falling fully/partly in
the State of Uttar Pradesh are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto Mar'25
(km) (km) ( in Cr.)
New Line 10 1,227 340 10,517
Gauge Conversion 02 67 - 281
Doubling/Multitracking 37 2,513 983 19,813
Total 49 3,807 1,323 30,611
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Uttar Pradesh are as under:
Cost
S. No. Project
( in Cr.)
1 Etawah-Mainpuri New Line (58 Km) 313
Bahraich-Nanpara-Nepal Ganj Gauge Conversion (56
2 342
Km)
..P/18-:18:-
Cost
S. No. Project
( in Cr.)
3 Ballia-Ghazipur city Doubling (65 Km) 650
4 Ghazipur city-Tarighat New Line (17 Km) 1,766
5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863
6 Gonda-Bahraich Gauge Conversion (60 Km) 318
7 Barabanki-Akbarpur Doubling (161 Km) 1,700
Kaptanganj-Thawe-Chhapra Gauge Conversion (234
8 819
Km)
9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589
10 Indara-Dohrighat Gauge Conversion (34 Km) 213
11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1,634
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Lahota-Bhadoi Doubling (39 Km) 184
14 Meerut-Muzaffarnagar Doubling (55 Km) 430
15 Phaphamau-Prayagraj Doubling (14 Km) 212
16 Muzaffarnagar–Tapri Doubling (52 Km) 525
17 Utretia-Raibareilly Doubling (66 Km) 662
18 Raibareilly-Amethi Doubling (60 Km) 668
19 Alamnagar-Utretia Doubling (20 Km) 358
20 Bhimsen—Jhansi Doubling (206 Km) 2,620
Domingarh-Gorakhpur-Kusumhi - 3rd Line and
21 508
Gorakhpur-Nakaha Jungle Doubling (21 Km)
22 Malhaur-Daliganj Doubling (13 Km) 183
23 Ruma Chakeri- Chandari 3rd Line (13 Km) 177
Bareilly-Pilibhit-Tanakpur Gauge Conversion (102
24 313
Km)
..P/19-:19:-
Cost
S. No. Project
( in Cr.)
25 Rosa-Sitapur Cantt-Burhwal Doubling (181 Km) 2,094
26 Jaunpur- Akbarpur (Tanda) Doubling (77 Km) 676
27 Ramna- Renukut-Singrauli Doubling (160 Km) 2,436
28 Janghai- Phaphamau Doubling (47 Km) 414
29 Varanasi-Madhosingh-Prayagraj Doubling (120 Km) 2,018
30 Karaila Road- Shaktinagar Doubling (32 Km) 763
31 Deoband (Muzzafarnagar)-Roorkee (27 Km) 1,289
32 Agra-Etawah New Line(110 Km) 427
33 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1,778
Ongoing projects:
Some of the projects falling fully/partly in the State of Uttar Pradesh which
have been taken up are as under:
SN. Project Cost
( in Cr.)
1 Barabanki-Burhwal 3rd Line (27 Km) 426
2 Burhwal- Gonda Kacheri 4th line (56 Km) 796
3 Burhwal-Gonda 3rd Line (62 Km) 1,118
4 Bahraich- Khalilabad New Line (240 Km) 4,940
5 Katra-Ayodhya Dham Doubling (10 Km) 466
6 Pt. Deen Dayal Upadhyaya- Prayagraj 3rd Line (150 Km) 2,649
7 Billi-Chunar Doubling (102 Km) 1,424
8 Chhapra-Ballia Doubling (65 km) 1,046
9 Unchhar-Amethi New Line (66 Km) 1,229
..P/20-:20:-
SN. Project Cost
( in Cr.)
10 Etah-Kasganj New Line ( 29 Km) 389
11 Gorakhpur- Valmikinagar Doubling (96 Km) 1,121
12 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th Line (15 2,464
Km)
13 Jhansi-Khairar-Manikpur & Khairar-Bhimsen Doubling 4,330
(431 Km)
14 Sahjanwa-Dohrighat New Line (81 Km) 1,320
15 Kuberpur-Yamuna Bridge 3rd line (10 Km) 170
16 Prayagraj (Iradatganj)-Manikpur 3rd Line (84 km) 1,508
17 Dilkusha-Malhaur 3rd Line (8 km) 164
18 Bypass/Chord line at Ayodhya Cantt. (between Salarpur- 97
Masodha) (6 Km)
19 Didarganj - Shahganj - Bilwai Chord line (6 km) 137
20 Varanasi Shivpur 3rd line (6 Km) 76
21 Jaunpur Jn.- Zafarabad Doubling (6 Km) 177
22 Bhatni - Aurnihar Doubling (117 km) 2,529
23 Mathura-Jhansi 3rd line (274 km) 5,924
24 Agra Fort and Bandikui Doubling (150 km) 988
25 Janghai-Pratapgarh- Amethi Doubling (87 km) 1,197
26 Barabanki-Malhaur - 3rd & 4th Line (33 km) 407
27 Phaphamau-Unchahar Doubling (72 km) 971
28 Aunrihar - Varanasi City 3rd Line (31 Km) 76
Railway Infrastructure projects enable socio-economic development of the
region including:
Better connectivity of the region with other parts of the country
..P/21-:21:-
Faster movement of goods and services
Improving logistics efficiency and reduction in transportation cost.
Enhance line capacity
Increase in direct and indirect employment opportunities for the
people of the region
Reduced operational bottlenecks
Development of tourism industry and increase in industrial activities
in the region.
Railways are environment friendly and energy-efficient mode of
transportation, yielding substantially lower CO2 emissions. Reduction in
CO2 emissions in transportation by railways as compared to transportation
by road is as under (Ref:- NITI Aayog Report titled “Fast Tracking Freight in
India, June 2021”):
Mode of transportation CO2 emission for transportation of 1
tonne for 1 Km
Road 101 gm
Rail 11.5 gm (about 89% less)
Shifting of one MT of freight from road to rail reduces the carbon emission
by about 5.37 Crore Kg. During the period from 2014 to 2025, about 562 MT
freight has shifted to railways which corresponds to reduction in carbon
emission amounting to 3,018 crore kg.
As per the extant policy guidelines, Railway projects are exempted from
environmental clearance. However, forestry/wild life clearances are taken
from Ministry of Environment, Forest and Climate Change (MoEF&CC),
wherever the diversion of forest land is involved.
..P/22-:22:-
Electric traction is more environment friendly and energy efficient.
Accordingly, electrification of railway network on Indian Railways has been
taken up in mission mode. So far, 99.4% of Broad Gauge (BG) network has
been electrified. The electrification in remaining network has been taken
up. Electrification carried out during 2014-25 and before 2014 is as under:
Period Route Kilometre
Before 2014 (about 60 years) 21,801
2014-25 46,900
All Railway infrastructure projects requiring diversion of forest land are
processed in accordance with the provisions of the Forest (Conservation)
Act, 1980 and approval of the Ministry of Environment, Forest and Climate
Change (MoEF&CC) is obtained, wherever required.
Further, Indian Railways has instituted several mechanisms to minimize
environmental impacts during construction and operation of projects,
which inter alia include: Afforestation in coordination with State Forest
Departments where forest land is involved, adoption of eco-friendly
construction practices, including proper disposal of construction debris,
slope stabilization, and protection of natural drainage, provision of wildlife
crossings, animal underpasses/overpasses and other mitigation measures
in environmentally sensitive areas, wherever required and continuous
monitoring of environmental safeguards during project implementation by
concerned railway authorities.
*****