GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1714
TO BE ANSWERED ON 29.07.2026
MODERNISATION OF RAILWAY INFRASTRUCTURE IN BIHAR, JHARKHAND,
CHHATTISGARH AND DELHI/NCR
1714. SHRI KALI CHARAN SINGH:
Will the Minister of RAILWAYS be pleased to state:
(a) the progress made under the Amrit Bharat Station Scheme (ABSS)
during the last one year including the number of stations sanctioned,
taken up for redevelopment, completed and inaugurated, State/UT and
station-wise;
(b) the details of projects in Bihar, Jharkhand, Chhattisgarh and Delhi/NCR,
including estimated cost, funds allocated and utilised, physical and
financial progress, present status and expected completion date,
station-wise;
(c) the measures taken/being taken by the Government to provide modern
passenger amenities, universal accessibility for persons with
disabilities, digital information systems, Wi-Fi, lifts, escalators,
improved waiting halls, parking, multimodal integration, green building
features and renewable energy facilities;
(d) whether the Government has assessed the impact of the said Scheme
on passenger convenience, tourism, regional connectivity, employment
and local economic development and if so, the details thereof; and
(e) the details of works completed, under execution and proposed in the
said States/UT and station-wise?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
§ Page 1 of 32The scheme involves preparation of master plans and their implementation
in phases to improve the stations of Indian Railways. The master planning,
keeping in view the necessity of each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
So far, 1,340 stations have been identified for development under Amrit
Bharat Station Scheme out of which, 98 stations are located in Bihar, 57
stations are located in Jharkhand, 32 stations are located in Chhattisgarh
and 13 stations are located in Delhi. The names of stations identified for
Page 2 of 32development under Amrit Bharat Station Scheme in Bihar, Jharkhand,
Chhattisgarh and Delhi are as following:
State No. of Names of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, Bapudham
Motihari, Barahiya, Barauni, Barh, Barsoi Jn,
Begusarai, Bettiah, Bhabua Road, Bhagalpur,
Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj,
Buxar, Chakia, Chausa, Chhapra, Dalsingh
Sarai, Darbhanga, Dauram Madhepura, Dehri
On Sone, Dholi, Dighwara, Dumraon, Durgauti,
Ekma, Fatuha, Gaya, Ghorasahan, Guraru,
Hajipur Jn, Jamalpur Jn, Jamui, Janakpur
Road, Jaynagar, Jehanabad, Jhanjharpur,
Kahalgaon, Karhagola Road, Katihar Jn,
Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai Jn,
Madhubani, Maheshkhunt, Mairwa, Mansi Jn,
Masrakh, Mokama, Motipur, Munger
(Monghyr), Muzaffarpur Jn, Nabinagar Road,
Narkatiaganj Jn, Naugachia, Nawadah,
Paharpur, Patliputra, Patna Jn, Piro, Pirpainti,
Rafiganj, Raghunathpur, Rajendra Nagar
Terminal (Patna), Rajgir, Ram Dayalu Nagar,
Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur
Kamal, Sakri, Salauna, Salmari, Samastipur,
Sasaram, Shahpur Patoree, Shivanarayanpur,
Page 3 of 32State No. of Names of Stations
Stations
Simri Bakhtiyarpur, Simultala, Sitamarhi,
Siwan, Sonpur Jn., Sultanganj, Supaul,
Taregna, Thakurganj, Thawe
Jharkhand 57 Balsiring, Bano, Barajamda Jn, Barkakana,
Basukinath, Bhaga, Bokaro Steel City,
Chaibasa, Chakradharpur, Chandil,
Chandrapura, Daltonganj, Dangoaposi,
Deoghar, Dhanbad, Dumka, Gamharia,
Gangaghat, Garhwa Road, Garhwa Town,
Ghatsila, Giridih, Godda, Govindpur Road,
Haidar Nagar, Hatia, Hazaribagh Road,
Jamtara, Japla, Jasidih Jn, Katrasgarh,
Koderma Jn, Kumardubi, Latehar, Lohardaga,
Madhupur Jn, Manoharpur, Muhammad Ganj,
Muri Jn, N.S.C.B. Jn Gomoh, Nagar Untari,
Namkom, Orga, Pakur, Parasnath, Piska,
Rajkharswan, Rajmahal, Ramgarh Cantt,
Ranchi Jn, Sahibganj, Sankarpur, Silli, Sini,
Tatanagar, Tatisilwai, Vidyasagar
Chhattisgarh 32 Akaltara, Ambikapur, Baikunthpur Road,
Balod, Baradwar, Belha, Bhanupratappur,
Bhatapara, Bhilai, Bhilai Nagar, Bhilai Power
House, Bilaspur, Champa, Dallirajhara,
Dongargarh, Durg, Hathbandh, Jagdalpur,
Janjgir Naila, Korba, Mahasamund, Mandir
Hasaud, Marauda, Nipania, Pendra Road,
Raigarh, Raipur Jn, Raj Nandgaon, Sarona,
Page 4 of 32State No. of Names of Stations
Stations
Tilda-Neora, Urkura, Uslapur
Delhi 13 Adarshnagar Delhi, Anand Vihar, Bijwasan,
Delhi, Delhi Cantt., Delhi Safdarjung, Delhi
Sarai Rohilla, Delhi Shahadra, Hazrat
Nizamuddin, Narela, New Delhi, Sabzi Mandi,
Tilak Bridge
Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Bihar, Jharkhand, Chhattisgarh and Delhi have been taken up at a good
pace. Details of stations completed in Bihar, Jharkhand and Chhattisgarh
are as under:
State No. of Name of stations
stations
Bihar 8 Banmankhi, Dauram Madhepura, Kahalgaon,
Pirpainti, Sabaur, Shivanarayanpur, Simultala,
Thawe
Jharkhand 15 Chaibasa, Chandil, Giridih, Godda, Govindpur
Road, Katrasgarh, Lohardaga, Madhupur Junction,
Muri Junction, Pakur, Piska, Rajmahal, Ramgarh
Cantonment, Sahibganj, Sankarpur
Chhattisgarh 10 Ambikapur, Balod, Bhanupratappur, Bhilai,
Champa, Dallirajhara, Dongargarh, Raj Nandgaon,
Sarona, Urkura
Page 5 of 32The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Bihar:
Gaya station: The work of new second entry arrival building has been
completed. The works of new second entry departure building, main
entry new arrival and departure building, new platform no. 8, new
platform shelters, air concourse and improvement of circulating area
have been taken up.
Luckeesarai Junction station: The works of new main entry station
building, extension of foot over bridge and improvement of circulating
area have been completed. The work of installation of lift for existing
foot over bridge has been taken up.
Fatuha station: The works of extension of platform no. 6,
improvement of second entry circulating area and approach road
have been completed. The work of new station building, lifts and
escalator have been taken up.
Anugraha Narayan Road station: The works of extension and
surfacing of platform no. 1/2 & 3/4 and new toilet block have been
completed. The works of improvement of station building,
improvement of circulating area, entry/exit gate, new water booths,
platform shelter and new 6 m wide foot over bridge have been taken
up.
Dehri On Sone station: The works of new booking office, new foot
over bridge with lifts, improvement of circulating area, new toilet
block, new water booth and new platform shelter have been taken up.
Page 6 of 32Jharkhand:
Ranchi Junction station: The works of new station building at second
entry, new platform no. 6 and structural work of extended 6 m wide foot
over bridge have been completed. The finishing works of new station
building at second entry and 6 m wide foot over bridge extension, the
work of entrance porch, new platform shelters on new platform no. 6,
improvement of circulating area and parking at second entry, new 6 m
wide foot over bridge, underground water tanks and sewage treatment
plant have been taken up.
Japla station: The works of improvement of station building,
improvement of circulating area and boundary wall have been
completed. The works of new platform shelter, new toilet block,
additional water booths and new foot over bridge have been taken up.
Daltonganj station: The works of raising and surfacing of platform no. 1,
2 & 3, improvement of station building, improvement of circulating area,
parking, approach road, new boundary wall, toilet block have been
completed. The works of entrance porch, new platform shelter and 12 m
foot over bridge have been taken up.
Nagar Untari station: The works of improvement of circulating area,
parking, approach road and new platform shelter have been completed.
The works of improvement of station building, improvement of platform
surface and 12 m foot over bridge have been taken up.
Latehar station: The works of improvement of station building,
improvement of circulating area, parking, approach road, new boundary
Page 7 of 32wall, porch, new waiting hall, toilet block, improvement of platform
surface have been completed. The works of 12 m Foot Over Bridge and
new platform shelter have been taken up.
Chhattisgarh:
Bilaspur station: The foundation works of new North-East side station
building and new South-West side station building have been
completed. The works of superstructure of new North-East side
station building, new South-West side station building, residential
quarters, substation building and service buildings have been taken
up.
Akaltara station: The works of improvement of station building,
improvement of circulating area, parking, waiting halls, booking
counter, platform shelters, new toilet, landscaping, installation of
CCTV and signages have been completed. The work of 12 m wide foot
over bridge has been taken up.
Korba station: The works of improvement of station building, waiting
halls, booking counter, improvement of circulating area, parking,
platform shelters, landscaping, installation of CCTV and signages
have been completed. The work of 12 m wide foot over bridge has
been taken up.
Jagdalpur station: The works of new station building, 12 m wide foot
over bridge, improvement of platform surface, improvement of
circulating area, toilets, platform shelters and waiting hall have been
completed. The works of lifts, signages and installation of Coach
Indication Boards have been taken up.
Page 8 of 32 Mahasamund station: The structural works of new station building,
improvement of platform surface and platform shelters have been
completed. The finishing works of new station building, improvement
of circulating area and 12 m wide foot over bridge have been taken
up.
Delhi:
Bijwasan station: The structural work of station building, air
concourse, electrical substation and water treatment plant have been
completed. The works of platform shelters, sewage treatment plant,
rainwater harvesting, lifts, escalator, waiting lounge, air-concourse
flooring and finishing works of station building have been taken up.
Safdarjung station: The work of station building, structural work of air
concourse and office building have been completed. The works of
foot over bridge, finishing work of office building and electrical work
of station building have been taken up.
Delhi Cantonment station: The works of East side station building,
elevated road all around the station, multi-level car parking (G+5),
departure concourse, North and South side arrival blocks, platform
refurbishing and overhead water tank have been taken up.
New Delhi station: The works of holding area on Ajmeri Gate side for
rush management and shifting of passenger facilities have been
completed. The works of elevated road network along Asaf Ali Road
and Basant Road, double basement on Paharganj side, tree
Page 9 of 32transplantation, compensatory plantation and diversion of the sewer
barrel at Chelmsford Road have been taken up.
Sabzi Mandi station: The works of new station building, 12 m wide
foot over bridge, platform shelter, improvement of platform surface,
toilets, improvement of parking amenities for Divyangjan,
improvement of circulating area and lift have been taken up.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
Indian Railways is committed to make its railway stations accessible for
Persons with Disabilities (Divyangjans) and passengers with reduced
mobility as part of “Sugamya Bharat Mission” or ‘Accessible India
Campaign’ of Government of India. In compliance of the Rights of Persons
with Disabilities Act, 2016, “Guidelines on accessibility of Indian Railway
stations and facilities at stations for differently abled persons
(Divyangjans) and passengers with reduced mobility” have been circulated
and notified in the Gazette of India. The guidelines include provisions of
facilities for Divyangjans and passengers with reduced mobility such as
entrance ramps, accessible parking, low height ticket counters/help
booths, toilets, drinking water booths, subways/foot over bridges with
Page 10 of 32ramps/lifts, standard signages including Braille signages and tactile
pathways for visual impairment, etc. which have been taken up for
implementation in a phased manner and on the principles of reasonable
accommodation.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways, including amenities for Divyangjan, lift,
escalator, waiting hall, parking etc., is a continuous and ongoing process
and works in this regard are undertaken as per requirement, subject to
inter-se priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise.
Bihar is covered under the jurisdiction of four railway zones, namely,
Eastern Railway, East Central Railway, North Eastern Railway and
Northeast Frontier Railway. For these zones, an allocation of ₹ 1,543 crore
has been made for the financial year 2026-27, out of which an expenditure
(up to June, 2026) of ₹ 677 crore has been incurred so far.
Jharkhand is covered under the jurisdiction of three railway zones, namely,
East Central Railway, Eastern Railway and South Eastern Railway. For
these zones, an allocation of ₹ 1,199 crore has been made for the financial
year 2026-27, out of which an expenditure (up to June, 2026) of ₹ 526 crore
has been incurred so far.
Page 11 of 32Chhattisgarh is covered under the jurisdiction of two railway zones,
namely, South East Central Railway and East Coast Railway. For these
zones, an allocation of ₹ 1,132 crore has been made for the financial year
2026-27, out of which an expenditure (up to June, 2026) of ₹ 486 crore has
been incurred so far.
Delhi is covered under the jurisdiction of Northern Railway. For the zone, an
allocation of ₹ 2,078 crore has been made for the financial year 2026-27,
out of which an expenditure (up to June, 2026) of ₹ 452 crore has been
incurred so far.
Amrit Bharat Station Scheme also envisages improvement in various
passenger amenities at the stations which enhance the passenger
convenience. Further, Development of stations into city centres envisages
enhanced economic activities at and around the stations apart from
improved travel experience. Further, development/upgradation of railway
stations has a positive impact on tourism in the surrounding areas.
Employment:
Recruitment done in Indian Railways during 2004-05 to 2013-14 vis-à-vis
during 2014-15 to 2025-26 is given as under: -
Period Recruitments
2004-2005 to 2013-2014 4.11 lakh
2014-2015 to 2026-2027 (upto 5.56 lakh
30.06.2026)
Occurrence and filling up of vacancies are continuous processes on Indian
Railways considering its size, spatial distribution and criticality of
Page 12 of 32operation. Adequate and suitable manpower is provided to cater to the
regular operations, changes in technology, mechanisations and innovative
practices. The vacancies are filled up primarily by placement of indents by
Railways with Recruitment agencies as per operational and technological
requirements.
The RRB examinations are quite technical in nature entailing large scale
mobilization of men and resources and training of manpower. Railway
overcame all these challenges and successfully conducted the recruitment
in a transparent manner following all laid down guidelines.
Further, as system improvement, the Ministry of Railways has introduced a
system of publishing the Annual Calendar from 2024 for recruitment to
various categories of Group ‘C’ posts. The introduction of the Annual
Calendar is benefitting the aspirants in the following manner:
More opportunities for candidates;
Opportunities to those becoming eligible every year;
Certainty of exams;
Faster Recruitment process, Training and Appointments
Presently, recruitment against 1,61,889 vacancies of non-gazetted
personnel has been taken up on Indian Railways as per Annual Calendar
2024, 2025 and 2026.
During January to December 2024, ten Centralized Employment
Notifications (CENs) for 92,116 vacancies were notified for filling up of
posts of Assistant Loco Pilots (ALPs), Technicians, Sub-Inspectors,
Constables in Railway Protection Force (RPF), Junior Engineers (JEs)/
Depot Material Superintendent (DMS)/ Chemical & Metallurgical Assistant
Page 13 of 32(CMA), Paramedical Categories, Non-Technical Popular Categories
(Graduate), Non-Technical Popular Categories (Under-Graduate), Ministerial
& Isolated Categories and Level-1 categories such as Assistants, Track
Maintainers and Pointsman.
First stage/Single stage Computer Based Tests (CBTs) for 92116 posts have
been completed. Details are as under:-
Exam Candidates Cities Languages
1st Stage CBT for the post of 18,40,347 156 15
ALP (18,799 vacancies)
CBT for the post of Technician 26,99,892 139 15
(14,298 vacancies)
1st Stage CBT for the post of 11,01,266 146 15
JE/DMS/CMA (7,951 vacancies)
CBT for the post of RPF-SI (452 15,35,635 143 15
vacancies)
CBT for the post of RPF- 45,30,288 147 15
Constable (4,208 vacancies)
CBT for Paramedical 7,08,321 143 15
Categories (1,376 vacancies)
1st Stage CBT for Non- 58,41,774 141 15
Technical Popular Categories
(Graduate) (8,113 vacancies)
1st Stage CBT for Non- 63,27,473 157 15
Technical Popular Categories
(Under Graduate) (3,445
vacancies)
CBT for Ministerial & Isolated 4,46,013 139 15
Page 14 of 32Exam Candidates Cities Languages
categories (1,036 vacancies)
CBT for Level-1 posts (32438 1,08,28,261 152 15
vacancies)
Total Candidates 3,58,59,270
2nd stage CBTs for the posts of ALP, JE/DMS/CMA and Non-Technical
Popular Categories (Graduate & Under-Graduate) have also been
completed. Details are as under:
Exam Candidates Cities Languages
2nd Stage CBT for the post of ALP 2,66,363 112 15
(18,799 vacancies)
2nd Stage CBT for the post of 1,17,339 118 15
JE/DMS/CMA (7,951 vacancies)
2nd Stage CBT for Non-Technical 1,21,931 129 15
Popular Categories (Graduate)
(8,113 vacancies)
2nd Stage CBT for Non-Technical 51,978 79 15
Popular Categories (Under-
Graduate) (3445 vacancies)
Total Candidates 5,57,611
Computer Based Aptitude Test (CBAT) for the posts of ALP and Non-
Technical Popular Categories (Graduate) and Computer Based Skill Tests
for the posts of Non-Technical Popular Categories (Graduate and Under
Graduate) and Ministerial & Isolated Categories have also been completed.
Details are as under:
Page 15 of 32Exam Candidates Cities Languages
CBAT for the post of ALP 1,32,044 84 2
Translation Test for Ministerial and 1,233 8 2
Isolated Categories
CBAT for the post of Non-Technical 13,616 38 2
Popular Categories (Graduate)
Computer Based Typing Skill Test 30,341 58 2
(CBTST) for the posts of Non-Technical
Popular Categories (Graduate)
CBTST for the post of Non-Technical 13,145 44 2
Popular Categories(Under Graduate)
Total Candidates 1,90,379
During 2026-2027 (upto 30.06.2026) panels for more than 3,300 candidates
for various posts including the posts of Technicians, Junior Engineers,
Paramedical Categories, Ministerial & Isolated categories and Assistant
Loco Pilots have been finalised. Majority of them are in safety categories.
In addition, as per Annual Calendar for the year 2025, nine Centralized
Employment Notifications (CENs) for 51970 vacancies have also been
issued. Details are as under:-
CEN No. Post Name No. of Vacancies notified Month of
Notification
01/2025 Assistant Loco Pilots 10,970 March-2025
02/2025 Technician 6,238 June-2025
03/2025 Paramedical Categories 434 July-2025
04/2025 Section Controller 368 August-
2025
Page 16 of 32CEN No. Post Name No. of Vacancies notified Month of
Notification
05/2025 Junior Engineers (JEs)/ 2,585 October-
Depot Material 2025
Superintendent (DMS)/
Chemical &
Metallurgical Assistant
(CMA)
06/2025 Non-Technical Popular 5,810 October-
Categories (Graduate) 2025
07/2025 Non-Technical Popular 3,058 October-
Categories (Under- 2025
Graduate)
08/2025 Isolated Categories 312 December-
2025
09/2025 Level-1 posts 22,195 December-
2025
Total 51,970
First stage/Single stage Computer Based Tests (CBTs) for 29,775 posts
have been completed. Details are as under:-
Exam Candidates Cities Languages
CBT for the post of Section Controller 4,33,748 131 15
(368 vacancies)
1st Stage CBT for the post of ALP 10,03,719 141 15
(10970 vacancies)
1st Stage CBT for the post of 5,74,351 133 15
JE/DMS/CMA (2585 vacancies)
Page 17 of 32Exam Candidates Cities Languages
CBT for the post of Technician (6238 8,41,525 117 15
vacancies)
CBT for Paramedical Categories (434 3,19,396 106 15
vacancies)
1st Stage CBT for Non-Technical 25,89,851 142 15
Popular Categories (Graduate) (5810
vacancies)
1st Stage CBT for Non-Technical 32,95,980 142 15
Popular Categories (Under Graduate)
(3058 vacancies)
CBT for Isolated categories (312 37,774 34 15
vacancies)
Total Candidates 90,96,344
2nd stage CBTs for the posts of JE/DMS/CMA and Non-Technical Popular
Categories (Graduate) have also been completed. Details are as under:
Exam Candidates Cities Languages
2nd Stage CBT for the post of 39,034 90 15
JE/DMS/CMA (2585 vacancies)
2nd Stage CBT for Non-Technical 87,317 98 15
Popular Categories (Graduate) (5810
vacancies)
Total Candidates 1,26,351
Computer Based Aptitude Test (CBAT) for the posts of Section Controller
has also been completed. Details are as under:
Page 18 of 32Exam Candidates Cities Languages
CBAT for the post of 2,989 24 2
Section Controller ( 368
vacancies)
Further, as per Annual Calendar for the year 2026, three Centralized
Employment Notifications (CENs) for 17,803 vacancies have been issued.
Details are as under:
CEN No. Post Name No. of Vacancies notified Month of
Notification
01/2026 Assistant Loco 11,127 March-2026
Pilots
02/2026 Technician 6,557 May-2026
03/2026 Section 119 June-2026
Controller
Renewable Energy facilities:
Adequate lighting arrangements are provided at the railway stations as per
norms/policy guidelines. Further, escalators and lifts at railway stations are
provided as per extant policy depending upon techno-economic feasibility
and inter-se priority of the stations. So far, 1,794 escalators at 443 railway
stations and 2,159 lifts at 791 railway stations have been provided over
Indian Railways.
As on June 2026, about 1,161 MW of solar and about 103 MW of wing power
plant have been installed over Indian Railway.
Page 19 of 32Digital Information Systems:
Under Amrit Bharat Station Scheme, a range of passenger amenities,
including Coach Guidance Systems (CGSs), Electronic Train Indication
Boards (TIBs) and Public Address (PA) System are planned to be provided
at stations across Indian Railways.
Railway Projects:
Railway projects are surveyed/sanctioned/executed Zonal Railway wise and
not State-wise/District wise as the Railway projects may span across
State/district boundaries.
Bihar:
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects falling fully/partly in the Bihar is as
under:-
Period Outlay
2009-14 ₹1,132 Cr./year
2026-27 ₹10,379 Cr. (More than 9 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Bihar is as under:-
Page 20 of 32Period New Track Average Commissioning of new tracks
Commissioned
2009-14 318 Km 63.6 Km/year
2014-26 2,034 Km 169.5 Km/year (More than 2.5 times)
Projects sanctioned:
As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26
Doubling), covering a total length of 5,067 km, costing ₹96,651 crore,
falling fully/partly in Bihar are sanctioned. The summary is as under:-
Category No of Total Length Length Total Exp
sanctioned (in Km) Commissioned upto Mar'26
Projects till Mar'26 (₹ in Cr)
(in Km)
New Lines 32 2,616 533 14,806
Gauge 1 69 52 544
Conversion
Doubling/Multi- 26 2,382 465 14,509
tracking
Total 59 5,067 1,050 29,860
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Bihar are as under:-
Page 21 of 32SN. Project Cost (Rs. in Cr.)
1 Patna bridge (28 Km) 3,310
2 Munger rail cum road Bridge (15 Km) 3,040
3 Kosi Bridge (22 Km) 863
4 Daniawan-Biharsharif new line (38 Km) 354
5 Chandan-Banka new line (40 Km) 496
6 Rampurhat-Mandarhill new line (130 Km) 908
7 Maharajganj-Masrakh new line (35 Km) 412
8 Rajgir-Tilaiya & Natesar-lslampur new line 726
(67 Km)
9 Jaynagar-Narkatiaganj gauge conversion 967
(260 Km)
10 Kaptanganj-Chhapra gauge conversion (234 819
Km)
11 Sakri-Nirmali, Saharasa-Forbesganj gauge 2,113
conversion (206 Km)
12 Mansi-Saharsa, Saharsa-Purnia, Banmakhi- 752
Bihariganj gauge conversion (169 Km)
13 Sahibganj-Pirpainti doubling (23 Km) 129
14 Maheshkunt-Thanabihpur doubling (32 Km) 115
15 Hajipur-Ramdayalu Nagar doubling (48 Km) 367
16 Pirpainti-Bhagalpur doubling (51 Km) 493
17 Kiul-Gaya doubling (124 Km) 2,462
18 Hajipur-Bachwara doubling (72 Km) 930
19 Araria-Galgalia (Thakurganj) new line (110 2,132
Km)
20 Samastipur-Darbhanga Doubling (38 Km) 874
Page 22 of 32Ongoing projects:
Some of the projects falling fully/partly in the State of Bihar which have
been taken up are as under:
SN. Project Cost
(Rs. in
Cr.)
1 Sakri-Hasanpur new line (76 Km) 802
2 Fatuha-lslampur new line (167 Km) 3,158
3 Koderma-Tilaiya new line (65 Km) 2,287
4 Hajipur-Sagauli new line (151 Km) 2,820
5 Araria-Supaul new line (96 Km) 2,170
6 Kursela-Bihariganj new line (58 Km) 194
7 Pirpainti-Jassidih new line (97 Km) 2,700
8 Chhitauni-Tumkuhi Road new line (59 Km) 1,881
9 Jalalgarh-Kishanganj new line (51 Km) 407
10 Sitamarhi-Nirmali new line (189 Km) 2,833
11 Bihta-Aurangabad new line (120 Km) 3,606
12 Gaya-Chatra and Gaya-Natesar new line (135 Km) 4,543
13 Sultanganj-Katuria new line (77 Km) 291
14 Jaynagar-Bijalpura Gauge conversion (69 Km) 900
15 Dhanbad-Sonnagar 3rd line (291 Km) 7,906
16 Sagauli-Valmikinagar Doubling (110 Km) 1,456
17 Muzaffarpur-Sugauli Doubling (101 Km) 1,745
18 Barauni-Bachwara 3rd & 4th line (32 Km) 486
19 Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur doubling 4,080
(256 Km)
Page 23 of 32SN. Project Cost
(Rs. in
Cr.)
20 Chhapra-Ballia Patch Doubling (65 Km) 1,046
21 Katihar-Kumedpur and Katihar-Mukuria Doubling 943
(65 Km)
22 Son Nagar-Andal Multitracking (749 Km) 12,334
23 Punarakh- Bhaktiyarpur New 4th line & balance 3rd line 422
(28 Km)
24 Aluabari Road-Thakurganj Doubling (20 Km) 327
25 Bhagalpur-Jamalpur 3rd line (53 Km) 1,156
26 Bhagalpur-Dumka-Rampurhat doubling (177 Km) 3,169
27 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192
28 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931
29 Punarakh-Kiul 3rd and 4th line (50 Km) 2,668
30 Kiul-Jhajha 3rd Line (54 Km) 962
31 Mansi-Saharsa doubling (44 Km) 499
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Jharkhand
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects falling fully/partly in the State of
Jharkhand is as under:-
Page 24 of 32Period Outlay
2009-14 ₹457 Cr./Yr
2026-27 ₹7,536 Cr. (approx. 16 times)
Track Construction:
The details of constructing new tracks falling fully/partly in the State of
Jharkhand is as under:-
Period New Track Commissioned Average Commissioning of new
tracks
2009-14 287 Km 57 Km/year
2014-26 1,371 Km 114 Km/year (2 times)
Projects Sanctioned:
As on 01.04.2026, 36 projects (10 New Lines and 26 doubling), covering a
total length of 2,887 Km, costing ₹60,064 crore falling fully/partly in
Jharkhand are sanctioned. The summary is as under:-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2026
(in Km) till March, 2026 (Rs. in Cr.)
(in Km)
New Lines 10 753 156 4,853
Doubling/Multi- 26 2,133 458 13,558
tracking
Total 36 2,887 615 18,411
Page 25 of 32Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
State of Jharkhand are as under:
S. Name of Project Cost (Rs. in Cr.)
No.
1 Mandarhill- Rampurhat new line (130 Km) 908
2 Giridih-Koderma new line (111 Km) 404
3 Koderma – Ranchi new line (202 Km) 3,800
4 Ranchi-Lohardaga Gauge Conversion (111 Km) 665
5 Sahibganj-Pirpainti Doubling (23 km) 129
6 Tinpahar-Sahebganj Doubling (38 Km) 246
7 Sini-Adityapur Doubling (23 Km) 215
8 Goeilkera-Manoharpur Doubling (28 Km) 425
9 Dongaposi-Rajkharswan 3rd line (75 Km) 629
10 Danea-Ranchi Road Doubling (25 Km) 324
11 Chakardharpur-Goilkera 3rd line (34 Km) 383
12 Garhwa Road-Ramna doubling (32 Km) 427
13 Manoharpur-Bondamanda 3rd line (30 Km) 359
14 Jarangdih-Danea Patch Doubling (29 km) 500
15 Ranchi Road- Patratu doubling (31 Km) 348
16 Talgaria-Bokaro doubling (38 Km) 514
17 Ramna-Singrauli doubling (160 Km) 2,436
Ongoing Projects:
Details of some of the projects falling fully/partly in the State of Jharkhand
which have been taken up are as under:
Page 26 of 32S.No Project Cost (Rs. in Cr.)
1 Koderma-Tilaiya new line (62 Km) 2,287
2 Buramara-Chakulia new line (60 Km) 1,459
3 Dhanbad-Sonnagar 3rd line (291 Km) 7,906
4 Bondamunda-Ranchi doubling (159 Km) 3,029
5 Kharagpur-Adityapur 3rd line (132 Km) 3,450
6 Chandil- Burnpur - 3rd line (121 Km) 1,932
7 Koderma-Barkakhana doubling (133 Km) 2,887
8 Bhagalpur-Rampurhat doubling (177 Km) 3,169
9 Gamharia-Chandil 3rd and 4th line (26 Km) 1,168
10 Barbenda-Damrughutu Doubling (52 Km) 815
11 Dangoaposi-Jaroli 3rd & 4th Line (43 Km) 1,638
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
CHHATTISGARH
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Chhattisgarh is as under:
Period Outlay
2009-2014 ₹311 Cr./year
2026-2027 ₹7,470 Cr. (approx. 24 times)
Page 27 of 32Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Chhattisgarh is as under:
Period New Track Average Commissioning of new tracks
Commissioned
2009-14 32 Km 6.4 Km per year
2014-26 1,311 Km 109.29 Km per year (17 times)
Projects Sanctioned:
As on 01.04.2026, 36 projects (8 New Lines and 28 Doubling), of total
length of 2,398 Km, costing ₹48,202 crore falling fully/partly in the State of
Chhattisgarh are Sanctioned. The summary is as under:-
Category No. of Total Length Total Exp upto
projects Length Commissioned till March 2026
(in km) March, 2026 (in (Rs. in cr.)
Km)
NL 8 887 262 7,535
DL 28 1,512 889 11,298
TOTAL 36 2,398 1,151 18,833
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
state of Chhattisgarh are as under:
Page 28 of 32S.No. Name of Project Cost (Rs. in
Cr.)
1 Kharsia-Korichhapar New Line (43 Km) 851
2 Bilaspur-Urkura 3rd line (110 Km) 365
3 Salka Road-Khongsara doubling (26 Km) 181
4 Durg-Rajnandgaon Doubling (31 Km) 250
5 Khodri Anuppur Doubling with flyover at Bilaspur 792
(72 Km)
6 Champa-Jharsuguda 3rd Line (152 Km) 1,227
7 Pendra Road –Annupur 3rd Line (50 Km) 394
8 Raipur - Titlagarh Doubling (203 Km) 1,171
9 Dallirajahra-Rowghat (95 Km) 1,628
Ongoing Projects:
Some of the major projects falling fully/partly in the State of Chhattisgarh
which have been taken up are as under:
S.N Name of Project Cost (Rs.
in Cr.)
1 Kharsia-Dharamjaygarh New Line (122 Km) 3,407
2 Gevra Road-Pendra Road New Line (135 Km) 3,724
3 Dharamjaigarh-Korba New Line (63 Km) 1,686
4 Chirimiri-Nagpur Halt New Line (17 Km) 670
5 Sardega-Bhalumunda New Line (37 Km) 1,282
6 Kharsia - Parmalkasa 5th and 6th line (278 Km) 7,854
7 Rowghat-Jagdalpur New Line (140 Km) 3,513
8 Kirandul-Jadgalpur Doubling (150 km) 1,780
Page 29 of 32S.N Name of Project Cost (Rs.
in Cr.)
9 Jagdalpur-Koraput Doubling (107 Km) 1,547
10 Jharsuguda-Bilaspur -4th line (206 Km) 2,596
11 Gevra Rd-Pendra Rd Doubling (135 Km) 3,475
12 Rajnandgaon-Nagpur 3rd line (228 Km) 3,545
13 Raipur-Dhamtari & Abhanpur-Rajim gauge conversion 3,250
(67.20 km)
14 Boridand- Ambikapur Doubling (80 Km) 1,577
15 4th line between of Durg-Rajnandgaon (31 Km) 464
16 Gondia-Dongargarh 4th line (84 Km) 2,223
17 Baikunth- Urkura 4th line (26 Km) 426
18 Champa-Korba 3rd Line (42 Km) 755
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
DELHI
Railway Budget:
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the UT of Delhi is as under:
Period Outlay
2009-14 ₹96 crore/year
2026-27 ₹ 2,711 Cr. (More than 28 times)
Page 30 of 32Projects Sanctioned:
As on 01.04.2026, 04 projects (doubling) of total length 224 Km, costing
Rs.7,219 crore, falling fully/partly in the UT of Delhi are sanctioned. The
summary is as under:-
Category No. of Total Length Expenditure upto
projects Length Commissioned March 2026
(Rs.in Crore)
Doubling 04 224 Km 04 Km 481
/multitracking
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
UT of Delhi are as under:
S. No. Project Cost
(Rs. in Cr.)
1 New Delhi to Tilak Bridge Doubling (7 Km) 137
2 Tughlakabad-Palwal 4th line (34 Km) 366
Ongoing Projects:
Some of the projects falling fully/partly in the UT of Delhi which have been
taken up are as under:
Page 31 of 32S. No. Project Cost
(Rs. in Cr.)
1 Delhi - Ambala Cantt 3rd & 4th line (194 Km) 5983
2 Delhi Kishanganj-Shakurbasti 3rd Line (07 Km) 156
3 Anand Vihar-Tilak Bridge 3rd & 4th line (20 km) 667
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Completion of Railway projects/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****