**Executive Summary**
The Ministry of Railways launched the Amrit Bharat Station Scheme to redevelop railway stations with a long-term approach. The scheme involves phased master planning, focusing on improvements and amenities. As of October 2025, ₹7,253 crore has been spent out of the ₹12,118 crore allocated for financial year 2025-26. No specific timeline is indicated for the project completion.
**Key Points / Main Content**
* **Amrit Bharat Station Scheme:**
* Launched by the Ministry of Railways for station redevelopment.
* Focuses on long-term improvement with phased implementation.
* Includes preparation of master plans.
* **Master Planning Components:**
* Improvement of station access and circulation.
* Station integration with both sides of the city.
* Improvement of station buildings, waiting halls, toilets, and water booths.
* Provision of wider foot over bridges/air concourses.
* Provision of lifts/escalators/ramps.
* Platform surface improvement and cover.
* Kiosks for local products ('One Station One Product' scheme).
* Parking areas and multimodal integration.
* Amenities for differently-abled individuals (Divyangjans).
* Improved passenger information systems.
* Executive lounges, business meeting spaces, and landscaping.
* Sustainable and environment-friendly solutions.
* Ballastless tracks where necessary.
* Creation of city centres at stations.
* **Scheme Progress:**
* 1337 stations identified for development.
* Works completed at 155 stations (names provided).
* Structural and finishing works in progress at Tirupati, Nellore, Yesvantpur, Bangalore Cantt, Rameswaram and Safdarjung stations.
* **Funding and Implementation:**
* Funded under Plan Head-53 ('Customer Amenities').
* ₹12,118 crore allocated for financial year 2025-26.
* ₹7,253 crore spent up to October 2025.
* 15 stations identified for potential Public Private Partnership (PPP) development.
* Selection based on proposals from Zonal Railways, major cities, and tourist/pilgrimage sites.
* **Heritage and Technology:**
* Commitment to preserving heritage items during modernization.
* Site-specific measures based on structure condition.
* Continuous technological improvement in Indian Railways.
* **Project Complexities:**
* Requires various statutory clearances (fire, heritage, tree cutting, airport).
* Challenges due to utility shifting, operation of trains, and safety requirements.
* No fixed completion timeframe due to complexities.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact**: Improved amenities, better accessibility, enhanced information systems, and a more comfortable station environment.
* **Action Required**: Utilize new facilities and provide feedback on improvements.
**Stakeholder: Railway Authorities (Ministry of Railways, Zonal Railways)**
* **Impact**: Responsible for planning, funding, and implementing the modernization scheme.
* **Action Required**: Submit proposals for station development, allocate resources effectively, and oversee project execution.
**Stakeholder: Local Communities**
* **Impact**: Creation of city centres at stations, provision of local product kiosks, and improved connectivity.
* **Action Required**: Engage with railway authorities and provide input on local needs and preferences.
**Stakeholder: Contractors and Private Investors**
* **Impact**: Potential business opportunities through PPP arrangements and construction projects.
* **Action Required**: Participate in bidding processes and adhere to project guidelines and timelines.
**Stakeholder: Differently-abled individuals (Divyangjans)**
* **Impact**: Enhanced accessibility and amenities designed specifically for their needs.
* **Action Required**: Utilize the provided amenities and give feedback.
Key Entities Referenced
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the redevelopment of railway stations across the country with a long-term approach, focusing on infrastructure upgrades and enhanced amenities.
Ministry of Railways: The government ministry responsible for the development and modernization of railway stations, including the implementation of the Amrit Bharat Station Scheme.
Lok Sabha: The lower house of the Parliament of India, where the starred question regarding the modernization of railway stations was raised.
Public Private Partnership (PPP): A model being considered for development of 15 railway stations to encourage private investments.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 157
TO BE ANSWERED ON 10.12.2025
MODERNISATION OF RAILWAY STATIONS ACROSS THE COUNTRY
*157. SHRI MALAIYARASAN D:
Will the Minister of RAILWAYS be pleased to state:
(a) the current status of the modernisation projects for railway stations
across the country;
(b) the number of railway stations identified for modernisation and the
criteria for selection of stations;
(c) the details of the total budget allocated for the modernisation of
railway stations and the manner in which this funding is distributed
among different States;
(d) whether any Public Private Partnership (PPP) models are involved in
the modernization projects and if so, the details thereof and percentage
of funding expected from private investments;
(e) the details of the facilities/amenities planned to be included as part
of the modernisation of railway stations;
(f) the role of technology in modernisation process of railway stations
particularly in terms of passenger information and safety systems;
(g) the manner in which the Government plans to modernise historic
railway stations while preserving their heritage architecture and cultural
significance; and
(h) the details of the specific guidelines for modernisation projects at
heritage railway stations?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (h) A Statement is laid on the Table of the House.
*****STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (h) OF LOK
SABHA STARRED QUESTION NO. 157 TO BE ANSWERED ON 10.12.2025
(a) to (h) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate
with passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over
platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
stationThe scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing
and feasibility and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under this
scheme. Development works at railway stations under Amrit Bharat
Station Scheme have been taken up at a good pace. Till now, works of
155 stations has been completed. Names of these stations are as
following:
Alnavar, Amb Andaura, Ambikapur, Amgaon, Anandpur Sahib, Anara,
Ayodhya Dham, Badami, Bagalkot, Baijnath Paprola, Balrampur,
Bantawala, Barabhum, Baramati, Bareilly City, Baripada, Barpali,
Begumpet, Beohari, Bhanupratappur, Bhilai, Bijnor, Bimalgarh, Bommidi,
Bundi, Chanda Fort, Changanassery, Chidambaram, Chinchpokli,
Chirayinkeezh, Cuttack, Dakor, Derol, Deshnoke, Devlali, Dharwad,
Dhule, Dongargarh, Fatehabad, Fatehpur, Fatehpur Shekhawati, Gadag,
Godda, Gogameri, Gokak Road, Gola Gokarnath, Gomti Nagar,
Govardhan, Govind Garh, Govindpuri, Govindpur Road, Haibargaon,
Haldia, Hapa, Harpalpur, Hathras City, Hodal, Idgah Agra Jn., Izzatnagar,
Jaisalmer, Jam Jodhpur, Jam Wanthali, Joychandi Pahar, Kakinada
Town, Kalyani Ghoshpara, Kamakhyaguri, Kanalus Jn., Karaikkudi Jn.,
Karamsad, Karimnagar, Katni South, Kedgaon, Khairthal, Koppal,
Kosamba Jn., Kulitturai, Kuttipuram, Lasalgaon, Limbdi, Lohardaga,
Lonand Jn., Mahe, Mahuva, Mailani, Mandal Garh, Mandawar Mahwa
Road, Madhupur, Manaparai, Mandi Dabwali, Mangalagiri, Mannargudi,
Matunga, Mithapur, Morappur, Morbi, Muktsar, Munirabad, Murtizapur
Jn., Nainpur Jn., Nandura, Narmadapuram (Hoshangabad), Netaji
Subhash Chandra Bose Itwari Junction, Okha, Orchha, Palitana,Panagarh, Panki Dham, Parel, Parlakhemundi, Pirpainti, Piska,
Pokhrayan, Pollachi Jn., Polur, Porbandar, Rajgarh, Rajmahal, Rajula Jn.,
Ramghat Halt, Rayanpadu, Saharanpur Jn., Sahibzada Ajit Singh Mohali,
Sahebgunj, Samakhiyali, Samalpatti, Sankarpur, Savda, Seoni, Shahad,
Shajapur, Sholavandan, Shoranur Jn., Shridham, Siddharth Nagar, Sihor
Jn., Siuri, Sri Bala Brahmeswara Jogulamba, Srirangam, Srivilliputtur,
St.Thomas Mount, Sullurpeta, Suraimanpur, Swaminarayan Chappia,
Tamluk, Thawe, Thiruvarur Jn., Tiruvannamalai, Tuni, Ujhani, Urkura,
Utran, Vadakara, Vadala Road, Vriddhachalam Jn., Warangal.
The works at other stations have also been taken up at good pace and
progress of some of the stations is as given below:
• Tirupati station: The structural framework of new main entry
station building on South side and 2 nos. air concourses have been
completed. The finishing works of new main entry station building on
South side and air concourses, structural work of station building on
North side, platform shelter works, lift, escalators etc. have been taken
up.
• Nellore station: The structural frameworks, brickwork and
plastering of station buildings on both East and West sides and
structural work of air concourse have been completed. The finishing
works of station building on both East and West side and air concourse,
extension work of subway, water tanks and sewage treatment plant
have been taken up.
• Yesvantpur station: The structural works of East side station
building, civil works of East side sub-station, East side elevated road andMulti Level Car parking have been completed. The finishing works of
East side station building, East side elevated road and Multi Level Car
parking, sewage treatment plant, structural work of West side station
building and air concourse have been taken up.
• Bangalore Cantt. station: The works of 24m wide diversion road on
the South side, training centre,hostel on North side and structural work
of South side station building have been completed. The finishing work
South side station building, structural work of North side station building
and Foot Over Bridge have been taken up.
• Rameswaram station: The structural works of East/North terminal
building, departure forecourt, arrival forecourt, residential tower, sub-
station building, desalination plant and sewage treatment plant have
been completed. The masonry works of East terminal building, finishing
works of North terminal building, departure forecourt, arrival forecourt,
residential tower, platform upgradation including platform shelter and
revamping of existing waiting hall have been taken up.
• Safdarjung station: The work of signal building, station building,
plumbing and firefighting, structural work of operational building up to
terrace floor slab, air concourse foundation and pedestals have been
completed. The station building electrical and low voltage work,
platform refurbishing work, finishing work of operational building,
overhead tank and air concourse have been taken up.
Stations are selected based on the proposals received from Zonal
Railways, stations located in major cities and places of tourist and
pilgrimage importance.Development / Upgradation / Modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head-53 are maintained Zonal Railway-wise and not work-wise or
station wise or state-wise. The fund allocation of ₹ 12,118 crore has
been made for the financial year 2025-26 under Plan Head–53 and
expenditure (up to October, 2025) of ₹ 7,253 crore has been incurred so
far.
The station development projects under Amrit Bharat Station Scheme
are primarily conceptualized with budgetary support. However, 15
stations have been identified to be explored for development under
Public Private Partnership (PPP) mode also and based on the experience
gained from the same, further evolution of the scheme is envisaged.
Ministry of Railways is committed to preservation of items of heritage
value while planning and execution of redevelopment/modernization of
stations. Site specific measures are taken based on the context and
condition of the structure/artifact.
Technological improvement in Indian Railways including stations is a
continuous process and aspires to democratize the use of technology. It
aims to address India centric challenges, create economic and
employment opportunities for all Indians.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and
works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. The priority for development /
redevelopment / upgradation / modernisation of stations is accorded to
higher category of station over lower category of station while
sanctioning and executing the works.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close
proximity of tracks and high voltage power lines, etc. and these factors
affect the completion time. Therefore, no time frame can be indicated at
this stage.
*****