GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1731
TO BE ANSWERED ON 29.07.2026
MODERNISATION OF THIRTEEN RAILWAY STATIONS IN DELHI UNDER ABSS
†1731. SHRI RAMVIR SINGH BIDHURI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the thirteen (13) railway stations in Delhi are being modernised
under the Amrit Bharat Station Scheme (ABSS) and if so, the details
thereof;
(b) the details of the percentage of the work completed at the said
stations;
(c) the time-line set for completion of the modernisation work of the said
stations; and
(d) the details of expenditure being incurred at the said station along with
the cost incurred on redevelopment of each of the said stations?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 13 stations are located in Delhi. The
names of stations identified for development under Amrit Bharat Station
Scheme in Delhi are as following:
State No. of Names of Stations
Stations
Delhi 13 Adarshnagar Delhi, Anand Vihar, Bijwasan, Delhi,
Delhi Cantt., Delhi Safdarjung, Delhi Sarai Rohilla,
§ Page 1 of 4State No. of Names of Stations
Stations
Delhi Shahadra, Hazrat Nizamuddin, Narela, New
Delhi, Sabzi Mandi, Tilak Bridge
The activities for development at the stations have been taken up at good
pace and progress of some of the stations is as given below:
Bijwasan station: The structural work of station building, air
concourse, electrical substation and water treatment plant have been
completed. The works of finishing of station-building, new platform
shelters, sewage treatment plant, rainwater harvesting, lifts,
escalator, waiting lounge and flooring & finishing of air-concourse
have been taken up.
Safdarjung Station: The structural works of station building and
operational building have been completed. The work of station
building electrical work, air concourse, foot over bridge, improvement
of circulating area, finishing of station building and operational-
building have been taken up.
Delhi Cantt. station: The works of east side station building, elevated
road all around the station, multi-level car parking, departure
concourse, north and south side arrival blocks, platform refurbishing
and overhead water storage tank have been taken up.
New Delhi station: The works of holding area on Ajmeri Gate side for
rush management and shifting of passenger facilities have been
completed. The works of elevated-road network along Asaf Ali Road
and Basant Road, double basement on Paharganj side and diversion of
the sewer barrel at Chelmsford Road have been taken up.
Sabzi Mandi station: The works of a new station building, 12m wide
foot over bridge, platform shelter, improvement of platform surface,
Page 2 of 4toilets, improvement of amenities for Divyangjan and improvement of
circulating area have been taken up.
Tilak Bridge station: The works of new station building, foot over
bridge walkway, lift, staircase and escalator have been taken up.
Narela station: The work of widening of platform no. 2 has been
completed.
Other stations have been taken up for master planning and are at various
stages. Master planning is an iterative process requiring optimization and
the time frame for such optimization cannot be indicated at this stage.
Amrit Bharat Station Scheme involves preparation of master plans and their
implementation in phases to improve the stations of Indian Railways. The
master planning, keeping in view the necessity of each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
Page 3 of 4The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brown field work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise. Delhi is covered under the jurisdiction of Northern Railway. For the
zone, an allocation of ₹ 2,078 crore has been made for the financial year
2026-27, out of which an expenditure of ₹ 452 crore (up to June, 2026) has
been incurred so far.
*****