GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 3931
ANSWERED ON 27.03.2026
MUMBAI- AHMEDABAD HIGH SPEED RAIL LINE
3931 SHRI NEERAJ SHEKHAR:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Mumbai- Ahmedabad High Speed rail line is likely to be made operational by August,
2027;
(b) if so, the details thereof;
(c) whether first section of the said project from Surat to Vapi will be fully operational by August 2027;
and
(d) if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Presently, the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is under
execution. The Project is passing through the States of Gujarat, Maharashtra and Union Territory of
Dadra & Nagar Haveli with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora,
Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
Entire land (1389.5 Ha.) for MAHSR project has been acquired. All Statutory Clearances have been
obtained. All 1651 utilities have been shifted. The delay in land acquisition in the State of Maharashtra
has impacted the project till 2021. The land acquisition picked up in 2022 in Maharashtra.
The progress of various major items so far is as under:
Item Progress
Piers 430 kms.
Girder 341 kms.
Track Bed 174 kms.
OHE Masts 153 kms.
The progress of stations is given below:-
S.No. Station Status
Foundation works completed, Platform slab & roof structural works
1 Sabarmati
and finishing works are in progress.
Page 1 of 3
§2 Ahmedabad
Structural works completed and finishing works have been taken up.
3 Anand/Nadiad
Foundation work completed, structural works and finishing works
4 Vadodara
have been taken up.
5 Bharuch
6 Surat
Structural works completed and finishing works have been taken up.
7 Bilimora
8 Vapi
9 Boisar
Foundation works have been taken up and in advanced stage.
10 Virar
Structural works have been taken up.
11 Thane
BKC This is an underground station. Foundation works almost completed
12
(Mumbai) and Base Slab has been taken up.
The progress on the River Bridges is as under:-
S. No. River Name Status
Sub-Structure work completed, Superstructure work
1 Sabarmati River (480m)
has been taken up.
2 Meshwa River (120m)
3 Vatrak River (280m) Bridge construction completed.
4 Mohar (Shedhi) River (160m)
5 Mahi River (720m) 11 out of 12 wells completed; 5 spans launched
6 Vishwamitri River (80m)
Bridge construction completed.
7 Dhadhar River (120m)
8 Narmada River (1366m) 21 out of 25 wells completed; 4 spans launched
9 Kim River (120m) Bridge construction completed.
Foundation work has been taken up, 10 out of 12
10 Tapi River (720m)
wells completed
11 Mindhola River (240m)
12 Purna River (360m)
13 Ambika River (200m)
14 Venganiya River (200m)
15 Kaveri River (120m)
16 Kharera River (120m) Bridge construction completed.
17 Auranga River (320m)
18 Par River (320m)
19 Kolak River (160m)
20 Daman Ganga River (360m)
21 Darotha River (80m)
22 Jagani River (360m) Foundation works have been completed
23 Vaitarna River (2320m) 12 Pile Cap and 11 Pier (out of 58) completed.
Temporary Access Bridge (TAB) completed to start
24 Ulhas River Branch (120m)
the foundation work.
Desai Khadi River Bridge Geo-technical Investigation (GTI) has been
25
(400m) completed and Design work has been taken up.
Page 2 of 3
§The work of the under-sea tunnel (approximately 21 km) has commenced, out of which 4.8 km of
tunnel between Ghansoli and Shilphata in Maharashtra has been completed.
On the Surat–Vapi section (97 km) entire civil works including river bridge construction, have been
completed and 80% of the track bed has been laid.
However, Bullet train project is a very complex and technology intensive Project. Exact timelines for
the completion of the entire project can be reasonably ascertained after the completion of all associated
works of Civil Structures, Track, Electrical, Signaling & Telecommunication and supply of Trainsets.
*****
Page 3 of 3
§