GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1751
TO BE ANSWERED ON 29.07.2026
MUMBAI AHMEDABAD HIGH SPEED RAIL (MAHSR) PROJECT
1751. SHRI GURMEET SINGH MEET HAYER:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the date of commencement, the initial sanctioned budget
and the original target completion timeline of the Mumbai-Ahmedabad
High-Speed Rail (MAHSR) project;
(b) the details of the current physical and financial progress of the project,
along with the revised operational timeline for its full completion;
(c) the details of the total quantum of cost overruns incurred on this
project till date and the specific reasons for the escalation;
(d) the details of the specific administrative, technical or land acquisition
challenges responsible for the delays encountered during project
execution; and
(e) the details of the route, estimated project costs and current planning
status of the other high-speed rail corridors proposed across the
country?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Presently, the Mumbai-Amdavad High Speed Rail (MAHSR) Project
(508 km) is under execution. The Project is passing through the States of
Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12
stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat,
Bharuch, Vadodara, Anand, Amdavad and Sabarmati.
Entire land (1389.5 Ha.) for MAHSR project has been acquired. All Statutory
Clearances have been obtained. All 1651 utilities have been shifted. The
delay in land acquisition in the State of Maharashtra has impacted the
project till 2021. The land acquisition picked up in 2022 in Maharashtra.
Page 1 of 4
§The progress of various major items so far is as under:
Item Progress
Piers 452 kms.
Girder 356 kms.
Track Bed 209 kms.
OHE Masts 190 kms.
The progress of stations is given below:-
Station Status
S.No.
1 Sabarmati Foundation & structural works completed.
Finishing work have been taken up.
2 Amdavad Structural works completed. Finishing works
and track works have been taken up.
3 Anand/Nadiad
4 Vadodara Foundation & structural works completed.
Finishing work have been taken up.
5 Bharuch
Structural works completed and finishing
6 Surat
works have been taken up. At Surat, Bilimora
7 Bilimora and Bharuch Track works have also been
taken up.
8 Vapi
9 Boisar Foundation works have been taken up and in
advanced stage. Structural works have been
10 Virar
taken up.
11 Thane
12 BKC (Mumbai) This is an underground station. Foundation
works almost completed and Base Slab has
been taken up.
The progress on the River Bridges is as under:-
S.No. River Name Status
1 Sabarmati River (480m) Sub-Structure work completed,
Superstructure work has been taken up.
Page 2 of 42 Meshwa River (120m) Bridge construction completed. Track
works completed and OHE works have
3 Vatrak River (280m)
been taken up at Mohar River. Track
4 Mohar (Shedhi) River
works in progress at Vatrak River.
(160m)
5 Mahi River (720m) Foundation completed. Pier works and
Girder launching have been taken up.
6 Vishwamitri River (80m) Bridge construction completed.
7 Dhadhar River (120m)
8 Narmada River (1366m) 21 out of 25 wells completed; 6 out of 24
spans launched
9 Kim River (120m) Bridge construction completed.
10 Tapi River (720m) 09 out of 13 Pier Cap completed.
11 Mindhola River (240m)
12 Purna River (360m)
13 Ambika River (200m)
14 Venganiya River (200m)
15 Kaveri River (120m)
16 Kharera River (120m) Bridge construction completed. Track
17 Auranga River (320m) and Electrical works have been taken up.
18 Par River (320m)
19 Kolak River (160m)
20 Daman Ganga River
(360m)
21 Darotha River (80m)
22 Jagani River (360m) Substructure works have been
completed.
23 Vaitarna River (2320m) 17 Pile Cap and 15 Pier (out of 58)
completed.
24 Ulhas River Branch Temporary Access Bridge (TAB)
(120m) completed to start the foundation work.
25 Desai Khadi River Geo-technical Investigation (GTI) has
Bridge (400m) been completed and Design work has
been taken up.
The work of the under-sea tunnel (approximately 21 km) has commenced,
out of which 4.8 km of tunnel between Ghansoli and Shilphata in
Maharashtra has been completed.
On the Surat–Vapi section (97 km) entire civil works including river bridge
construction, have been completed and 86% of the track bed has been laid.
Page 3 of 4Bullet train project is a very complex and technology intensive Project.
Exact timelines for the completion of the project and final cost can be
reasonably ascertained after the completion of all associated works of
Civil Structures, Track, Electrical, Signaling & Telecommunication and
supply of Trainsets.
To strengthen national transport infrastructure, provide a fillip to regional
connectivity, economic growth, tourism, investment and employment
generation, and encourage modal shift from road and air transport to rail,
the Government has announced the development of the following seven
new High-Speed Rail (HSR) corridors in the Union Budget 2026-27:-
(i) Mumbai–Pune
(ii) Pune–Hyderabad
(iii) Hyderabad–Bengaluru
(iv) Hyderabad–Chennai
(v) Chennai–Bengaluru
(vi) Delhi–Varanasi
(vii) Varanasi–Siliguri
Post Budget announcement, the cost updation, alignment finalization etc.
have been taken up in DPR. Based on the experience gained from MAHSR
project, National High Speed Rail Corporation Limited (NHSRCL) has taken
up activities for a standardised set of designs and technical specifications
for the Infrastructure of future corridors, such as viaducts, bridges, tunnels
and stations, train control systems etc.
Being highly capital intensive, the decision to sanction any HSR
Corridor/Project depends on many factors such as outcome of DPR, techno
economic feasibility studies and availability of resources such as financing
options etc.
*****
Page 4 of 4