Parliament Question: Mumbai-Ahmedabad Section of NH-48

Issued by Ministry of Road Transport and Highways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Executive Summary: This document addresses concerns raised in Lok Sabha Starred Question No. 268 regarding the condition of the Mumbai-Ahmedabad section of National Highway NH48. It details the reasons for the highway's poor condition, particularly during monsoon season, and outlines steps taken to rectify the issues. The document also specifies actions taken against defaulting agencies responsible for maintenance lapses, with work targeted for completion by November 2025. Key Points / Main Content: Reasons for Poor Condition of NH48: * The Vadodara to Maharashtra border section experiences high rainfall and heavy commercial traffic (1.5 Lakhs PCU). * Heavy commercial traffic increases susceptibility to surface defects during the monsoon season. * Prior to 2021, the Achhad to Dahisar section's bituminous pavement experienced distress due to high traffic and rainfall. Remedial Actions: * Potholes are regularly addressed by the maintenance agency. * White topping work on a 121 km stretch from Achhad to Dahisar was sanctioned as a long-term solution and is targeted for completion by November 2025. * Damaged white topping panels are being replaced by the contractor, with repairs also being done using mastic asphalt during the monsoon. * The Central Road Research Institute (CRRI) and the Indian Institute of Technology (IIT), Bombay, were consulted during construction, and IIT Bombay reviewed repair methodologies. * The Delhi-Mumbai Expressway is under construction to reduce traffic load on NH48. * Additional works, including widening of bridges, construction of underpasses/flyovers, and service roads, have been sanctioned and are in progress. Accountability and Penalties: * Lapses in highway maintenance are addressed with penal provisions in the contract. * Ahmedabad-Vadodara Section: A penalty of Rs. 27.67 Crore was imposed on the contractor/concessionaire. * Vadodara-Bharuch Section: A penalty of Rs. 0.35 crore was imposed on the contractor. * Surat to Vapi Section: The Performance Bank Guarantee of Rs. 2.90 Crore was encashed, a penalty of Rs. 9.02 crore was imposed, and a recovery of Rs. 13.84 crore is being counterclaimed through arbitration. * Achhad to Dahisar Section: The contractor has been debarred by NHAI from 22.04.2025 to 23.11.2025, and rectification work is being taken up at the contractor's risk cost. Impact Analysis: Contractors/Concessionaires: * Impact: Financial penalties, debarment, and responsibility for rectification costs due to maintenance lapses. * Action Required: Improve maintenance practices to avoid penalties and ensure adherence to contract terms; rectify defects at their own cost. National Highways Authority of India (NHAI): * Impact: Responsible for ensuring highway maintenance and imposing penalties on defaulting contractors. * Action Required: Oversee maintenance work, enforce contract provisions, and manage rectification work at the contractor's risk cost. Highway Users: * Impact: Affected by traffic congestion due to construction and potential safety hazards from potholes. * Action Required: Exercise caution while driving on the affected sections of NH48 and be aware of potential delays due to ongoing construction and maintenance. Central Road Research Institute (CRRI) and Indian Institute of Technology (IIT), Bombay: * Impact: Consulted to give expert advice on repairs. * Action Required: Provide expert guidance on methodologies and onsite work of repair and replacement of damaged panels.

Key Entities Referenced

NH48: National Highway 48, a major highway discussed in the context of its condition and maintenance. Mumbai-Ahmedabad: A section of NH48 specifically mentioned due to issues with potholes and road quality. Maharashtra: A state in India where a section of NH48 (Achhad to Dahisar) experiences pavement distress. Gujarat: A state in India where a section of NH48 (Vadodara to Maharashtra border) experiences high rainfall and heavy traffic. Vadodara: A city in Gujarat, part of the Vadodara-Bharuch-Surat-Vapi stretch of NH48. Delhi-Mumbai Expressway: A parallel corridor under construction to reduce traffic load on NH48. Central Road Research Institute CRRI: An organization consulted for domain expertise on road construction and repair methodology. Indian Institute of Technology IIT, Bombay: An organization consulted for domain expertise on road construction and repair methodology; reviewed repair work.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA STARRED QUESTION NO. 268 ANSWERED ON 7TH AUGUST, 2025 MUMBAI-AHMEDABAD SECTION OF NH-48 †*268. SHRI PATEL UMESHBHAI BABUBHAI: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार् ग मंत्री be pleased to state: (a) whether large potholes are formed on the Mumbai–Ahmedabad stretch of National Highway (NH)-48 (Delhi–Chennai) every year and it fails to/is not able to withstand even the first spell of monsoon rains; (b) whether any investigation has been carried out/undertaken to ascertain the reasons behind the consistently poor condition of this highway during monsoon, if so, the details thereof and the steps taken to rectify the same; (c) the reasons for the failure to maintain the road quality to satisfactory/required standards despite multiple toll hikes implemented on this route in recent years; and (d) whether there is any mechanism to ensure accountability for the maintenance of highways and if so, the details thereof along with the action taken against the defaulting agencies during the last five years? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) to (d) A statement is laid on the Table of the House.STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA STARRED QUESTION NO. 268 ANSWERED ON 7TH AUGUST, 2025 ASKED BY SHRI PATEL UMESHBHAI BABUBHAI REGARDING ‘MUMBAI-AHMEDABAD SECTION OF NH-48’. (a) to (c) The section of NH-48 from Vadodara to Maharashtra border in State of Gujarat lies in a high rainfall region and carries nearly 1.5 Lakhs Passenger Car Unit (PCU) traffic. Since this stretch carries very heavy commercial traffic, it is more susceptible to surface defect especially during monsoon season. The damages and pothole formations have been observed at some locations on the Vadodara-Bharuch-Surat -Vapi stretch of NH-48 in Gujarat State, due to continuous heavy rain complemented with heavy commercial traffic on the highway stretch. However, the potholes are regularly being attended by Maintenance agency to keep the stretch in motorable conditions. Prior to 2021, on account of very high commercial traffic & huge rainfall and pavement distress was noticed on bituminous pavement of Achhad to Dahisar section of NH-48 in state of Maharashtra. Therefore, as a long term solution, the work of white topping of entire section of 121 Km stretch was sanctioned. This white topping work is under progress and targeted for its completion by November 2025. The lane by lane work, issue of traffic congestion, pre-mature running of vehicle over fresh/under curing concrete etc led to localised failures in white topping. The potholes in the white topping are being attended by the white topping Contractor by replacing the damaged panels. In addition to this during on-going monsoon, the potholes are also repaired by mastic asphalt. During construction, the domain experts from Central Road Research Institute (CRRI) and Indian Institute of Technology (IIT), Bombay have been consulted. The methodology and on-site work of repair and replacement of damaged panels has also been reviewed by IIT Bombay. To reduce traffic load on NH-48, a parallel corridor—the Delhi–Mumbai Expressway—is also under construction. Upon its completion, a significant portion of the traffic is expected to be diverted from NH - 48. In addition tothis, based on site requirements, additional works such as widening of bridges, construction of new Vehicular Underpasses/Light Vehicular Underpasses (VUPs/LVUPs)/flyovers, and provision of service roads have already been sanctioned on existing NH-48, and execution of these works is in progress. (d) The lapses in maintenance of highway are being dealt with applicable penal provisions in the Contract including taking up the works on the Risks & Cost of non-performing contractors. The details of action taken against the defaulting agencies during the last five years are as under: Sl Section of NH-48 Details of Action taken against the defaulting agencies No during the last five years 1 Ahmedabad- Damages/penalty of Rs. 27.67 Crore imposed on Vadodara Section Contractor/concessionaire. 2 Vadodara- Damages/penalty of Rs. 0.35 crore is imposed on Bharuch Section Contractor 3 Surat to Vapi The Performance Bank Guarantee amounting to Rs. Section 2.90 Crore has been encashed. A penalty of Rs. 9.02 crore has been imposed, and a recovery of Rs. 13.84 crore has been counterclaimed through arbitration proceedings. 4 Achhad to The Contractor has been debarred by NHAI from Dahisar section 22.04.2025 to 23.11.2025 for default in the contract. NHAI is also taking up rectification on risk & cost of defaulting contractor. *****