GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1979
ANSWERED ON 30th JULY, 2026
NATIONAL HIGHWAY PROJECTS IN ANDHRA PRADESH
1979. SHRI P V MIDHUN REDDY:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the total funds sanctioned by the Government for National
Highway (NH) projects in Andhra Pradesh from Financial Year 2019-
20 to Financial Year 2025-26, year-wise;
(b) the actual capital expenditure incurred by the Ministry on these
NH projects in Andhra Pradesh during the same period, year-wise;
and
(c) the current status of National Highway projects under
implementation in Andhra Pradesh including the number of projects
facing delays due to land acquisition, forest clearance or other
approvals and the steps taken by the Government to expedite their
completion?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) Government in Ministry of Road Transport & Highways
allocates funds State wise. The year-wise details of funds allocated
for National Highway (NH) projects in the State of Andhra Pradesh
from Financial Year 2019-20 to Financial Year 2025-26 are as under:
Financial Year Funds allocated (Rs in Crore)
2019-20 6,170
2020-21 4,296
2021-22 5,913
2022-23 6,957
2023-24 11,780
2024-25 11,554
2025-26 11,962
Total 58,632(b) The year-wise capital expenditure incurred on National
Highway projects in the State of Andhra Pradesh during the above
period is as under:
Financial Year Capital Expenditure (Rs in Crore)
2019-20 6,170
2020-21 4,296
2021-22 5,913
2022-23 6,957
2023-24 11,780
2024-25 11,554
2025-26 11,962
Total 58,632
(c) At present, 106 National Highway projects are under
implementation in the State of Andhra Pradesh. The current status
is summarized as below:
Particulars Number of
Projects
Total ongoing projects 106
Facing delay primarily due to land acquisition 26
Facing delay primarily due to forest/ environment
12
clearances
Facing delay due to utility shifting/ statutory
11
approvals
Facing delay due to contractor/other project-
21
specific issues
The progress of National Highway projects depends upon timely
availability of encumbrance-free land, statutory and forest/
environment clearances, utility shifting, law and order conditions,
availability of construction materials, contractual obligations and
other project-specific factors.
The Government and implementing agencies monitor the progress
of projects regularly at various levels and take appropriate
measures, including close coordination with the State Government
and other stakeholders, for expeditious land acquisition and
handing over of encumbrance-free stretches, obtaining statutory
and forest/environment clearances, shifting of utilities in
coordination with the concerned agencies, resolution of contractual
and technical issues and regular review and monitoring to facilitate
timely implementation of the projects.
*****