GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1883
ANSWERED ON 30th JULY, 2026
NATIONAL HIGHWAY PROJECTS IN KARNATAKA
1883. SHRI E TUKARAM:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the total number of National Highway projects sanctioned in
Karnataka from 2014 till date along with their total sanctioned
length (in kms);
(b) the total length (in kms) of National Highways completed and
opened to traffic in Karnataka during the said period and the total
length still under construction or yet to be completed;
(c) the reasons for the delay in completion of the pending National
Highway projects in Karnataka; and
(d) the timeline including expected date for completion of the
remaining National Highway projects in Karnataka, project-wise?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) Since 2014, a total of 372 National Highway projects having an
aggregate length of 6077 km have been sanctioned in the State of
Karnataka.
(b) A total length of 4405 km have been completed and opened to
traffic during the said period. The length of 2194 km is at various
stages of implementation including construction & bidding.
(c) The progress of National Highway projects depends upon
timely availability of encumbrance-free land, statutory and
forest/environment clearances, utility shifting, law and order issues,
contractual matters, availability of construction materials, weather
conditions and other unforeseen site-specific factors. Delays,
wherever encountered, are attributable to one or more of these
factors. The Government and implementing agencies continuously
monitor the progress of projects and take appropriate measures forexpeditious execution by taking up the matter with State
Government of Karnataka.
(d) The project-wise status and expected date of completion of the
ongoing National Highway projects in Karnataka are at Annexure.Annexure
ANNEXURE REFERRED TO IN REPLY TO PART (d) OF LOK SABHA
UNSTARRED QUESTION NO. 1883 ANSWERED ON 30TH JULY, 2026
ASKED BY SHRI E TUKARAM REGARDING NATIONAL HIGHWAY
PROJECTS IN KARNATAKA
Scheduled
completion
date/
Sl. NH Length Present
Name of Project Revised
No. No. (km) Status
Scheduled
completion
date
Widening to 2L+PS from
Km 67 to Km 115 on Under
1 173 48.00 30-04-2027
Kadur-Hosadurga section Construction
NH 173
Widening to Four Lane
from Km 0+000 to Km
2+480 on NH-169 (Old Under
2 169 2.50 30-09-2026
NH-13 from km 530+700 Construction
to 533.180 ) of Shimoga -
Mangalore Section
Construction of Yadgiri
Bypass from Km. 70.900 Under
3 150 8.80 11-05-2027
to Km. 79.650 (Design Construction
chainages) of NH-150
Construction of
Srinivasapura Bypass
from existing Km
Under
4 453.890 Design Ch. 69 10.08 11-01-2027
Construction
0+000 to existing Km
461.450 Design Ch
10+080 on NH-69
Widening to 2L+PS from
Km 71.00 to 104.00
(Existing chainages)
Under
5 (Sarjapur to Pattadkallu) 367 26.00 31-12-2026
Construction
on Bhanapur to
Gaddanakeri section NH-
367
Widening to 2 Lane Under
6 150A 13.00 31-10-2026
Paved Shoulders from ConstructionKm 184.70 to Km 198.92
(Venkateshwara Camp to
Dadesugur Camp
Section) on NH-150A
Construction of 2 Lane
with paved shoulder from
km 55.6 to km 90.7
(existing chainages) of
Under
7 NH-766C (complete 766C 13.00 21-12-2027
Construction
Realignment of 13.76 km)
with 2 major Bridges
across Sharavathi
Backwaters
Construction of
Chintamani Bypass from
Design Ch.0+000
Under
8 (Existing Ch.428+880) to 69 15.40 18-07-2027
Construction
Design Ch.15+400
(Existing Ch.444+010) on
NH-69
Widening to Two Lane
with Paved Shoulders
From Km 235.000 To Under
9 150A 19.80 14-09-2026
254.800 of Sindigeri- Construction
Bellary Section on NH-
150A
Widening to 4L+PS of NH-
548B from Km 80.000
(Near Murgundi) to Km
Under
10 140.200 (Near Chikkodi) 548B 50.20 23-04-2028
Construction
excluding length from
Km 118.450 to Km
128.450
Construction of Bypass
at Kuknoor, Yelburga,
Under
11 Gajendragada of 367 17.30 25-06-2027
Construction
Bhanapur Gaddanakeri
section of NH-367
Widening to Two Lane
with Paved Shoulders
from KB Cross to Under
12 150A 42.26 13-01-2027
Chunchanahalli ie., Construction
Design Ch. 485+240
Km Existing Km494.000 to Design Ch.
523+393 Km Existing
km 533.152 & From
Design Ch.
530+393 Existing Km
540.175 to Design Ch.
534+476 Existing Km
544.200 at Nelligere of
NH-150A
Widening to 2L+PS from
Km 0.000 to 37.850
(Except Ex. Km 24.45 to Under
13 766C 35.10 06-08-2027
27.20) of NH-766C Construction
Byndoor-Ranebennur
Section
Widening to 2 Lane with
Paved Shoulders from
design Km 103.200
(Existing Km 103.200) to Under
14 544E 13.53 31-08-2026
design Km 116.700 Construction
(Existing Km 118.470) on
AP/KNT Border to Sira
Section of NH-544E
Widening to two lane
with paved shoulders
from Km 0.00 to 102.310 Under
15 548B 102.31 15-01-2027
(Design Chainage) of NH- Construction
548B (Murrum-
Maharashtra Border)
Widening of existing road
to 2 lane with paved
Shoulders from Km Under
16 169 8.80 30-11-2026
115.00 to Km 123.80 of Construction
NH-169 on Shivamogga -
Mangalore Section
Realignment of road from
Km 35.935 to 39.255
(Chowdapur village) Km
58.220 to Km 62.290 Under
17 150E 7.73 31-12-2026
(Afzalpur town) and Km Construction
70.125 to Km 72.920
(Ballurgi village) of NH-
150E
18 One time improvements 69 6.55 Under 31-08-2026of Gauribidanur town Construction
bypassed stretch of NH-
69
Construction of Bypass
to Naragund Town NH-52
(Old NH-218) (existing CH
Under
19 from Km.133.040 to 52 7.30 31-12-2026
Construction
140.843) Design CH. 0.0
to 7.30 Bijapur-Hubli
Section
Construction of
Shikaripura bypass from
existing Km. 146.150 to
Under
20 existing Km. 154.0 766C 6.58 30-12-2026
Construction
(design chainage from
Km. 0.00 to Km. 6.576) of
NH-766C
Widening to two lane
with paved Shoulders
from Km 40.00 to Km
Under
21 75.00 Existing 73 33.10 31-12-2026
Construction
chainages of Mangalore
- Tumkur section of NH-
73
Widening to 4 lane from
Km 51.60 to 76.20 (Hebri
to Parkala) and from Km
Under
22 85.20 to 88.90 (Karavali 169A 28.30 30-11-2026
Construction
junction to Malpe) of
Thirthahalli-Udupi-Malpe
Section of NH-169A
Widening to existing 2
lane with paved Shoulder
to 4 Lane with paved
shoulder from design Km Under
23 169 15.27 30-11-2026
153.00 to 168.27 (Mala Construction
Gate to Karkala) of NH -
169 on Shimoga -
Mangalore section
Widening Two lane with
Paved shoulder from Km
Under
24 494.450 to Km 505.500 of 234 11.09 31-08-2026
Construction
NH-234 (Mulbagal to AP
Border)Widening to existing 2
lane with paved Shoulder
from Km 15.980
Under
25 (Megaravalli) to Km 169A 14.77 30-12-2026
Construction
30.750 (Agumbe) of NH-
169A on Thirthahalli -
Malpe section
Widening to 2-Lane with
Paved Shoulders from
Km 116.800 to Under
26 173 31.72 31-07-2026
149.070(Design Changes) Construction
on Hosadurga - Holalkere
Section of NH-173
Widening to
intermediate/two lane to
2 lane with paved
shoulder from Existing
chanages Km 112.750 to
Under
27 142.00 (Liingasur to 150A 30.94 31-08-2026
Construction
Mudabal cross) & from
Km. 147.070 to Km.
149.070 (Maski city limit)
of Jewargi Chamrajnagar
setion of NH-150A
Widening to 4 lane from
Km. 133.00 to 158.04
(design Chainage Km. Under
28 367 24.27 31-03-2027
130.88 to 155.145) Construction
(Shirur Cross to
Gaddankeri) of NH-367
Construction of 6 lane
with service road RUB at
Km. 5.46, Km. 7.06, Km Under
29 275K 1.10 15-09-2026
7.86 and Km. 28.585 of Construction
NH- 275K (Mysore Ring
Road)
Balance work of
Construction of Two/Four
lane with paved shoulder Under
30 13 101.60 30-08-2026
from Km 422.000 to Construction
523.600 ( Chitradurga to
Shivamogga ) of NH-13
Widening to Four Lane Under
31 69 8.40 30-12-2026
Divided Carriageway Constructionfrom Km 278.00 to Km
286.40 in Sagar Town
limits on Tumkur-
Honnavara Section of
NH-206 (new NH-69)
Widining from Existing
intermidiate lane to Four
lane in Sringeri Town
limits from ch 110.00 to Under
32 169 5.00 31-07-2026
ch 115.00 (old ch 640.00 Construction
to 645.00) of NH-169 (old
NH-13) of shimoga-
Mangalore section
Widening of Major Bridge
at Ch 171.601 (Existing
Under
33 chainage 172.310) on NH- 150A 0.50 31-07-2026
Construction
150A (Jewaragi -
Chamarajnagar Section)
Widening to 2 lane with
paved shoulders from
design Km. 199.200 to
design Km. 214.880 of Under
34 150A 15.68 30-04-2027
(Ibrampura to Construction
Tekkalkote) of NH-150A
Jewargi-Chamrajnagar
section
Construction of Elevated
corridor from Km.
135.650 to 136.300 on
63, from Km. 249 to Km.
250.050 on old NH-4 and 63 & Under
35 3.60 30-11-2026
from Km. 192.910 to Km. 218 Construction
193.350 on NH-218 from
decongestion of traffic in
Ranichennamma circle in
Hubli city
Construction of Major
Bridge at Km.180.865
Under
36 across river Krishna on 167 2.12 30-04-2027
Construction
NH 167 Hagari Jadcherla
section
Construction of 4 lane
Under
37 ROB and its approaches 218 1.51 31-08-2026
Construction
in lieu of existing levelcrossing 75 at Km.15 on
NH 218
Construction of 4 lane
ROB and its approaches
in lieu of existing 56T-C-2 Under
38 367 0.01 31-12-2026
at Km. 0.517 on NH-367 Construction
(Bhanapura and Koppal
satations)
Widening of existing 2
lane to 4 lane with paved
shoulder from Designed
km 25.15 to km 56.70
(Except Km 52.70 to Under
39 169 30.75 24-02-2028
53.50) of NH-169 ( Construction
Nellisara Camp to
Thirthahalli ) of NH-169
on Shimoga-Mangalore
section
Construction of 2-Lane
ROB in lieu of LC -110E at
existing Km 340+640
(Sudha Cross in Ballari Under
40 67 1.50 31-03-2027
City Limits) on Old NH-63 Construction
(New NH-67) on
Hosapete to Ballari
Section
Widening to two lane
with paved shoulder of
Under
41 NH-73(New) spur road 73 28.49 04-11-2027
Construction
Ujire - Dharmasthala -
Periyashanthi
Improvement to Black
Spot at Devalapura Cross
Under
42 ring road (KA-(05)-19) on 275K 0.01 17-01-2027
Construction
NH-275K Mysuru Ring
Road section
Construction of 4 lane
ROB at Km 40.134 on NH-
150 including balance
approach work from Km Under
43 150 2.00 23-09-2027
39.560 to Km 40.065 and Construction
from Km 40.203 to
40.612 of NH-150 of
Kalaburagi districtImprovement to 2lane
with Paved Shoulder from
Km 597.560
(Pandavapura Town Under
44 150A 11.38 31-08-2026
Limit) to 606.670 Construction
(Kiranguru) on NH-150A
(Jewargi-Chamarajnagar
Section)
Construction of 4 lane
ROB in lieu of LC No. 47
at Km 49/600-700 (NH
Design Ch: 673+000)
between Nanjangud
Under
45 Town (NTW) and 150A 1.73 13-08-2027
Construction
Chamarajanagar (CMNR)
Stations near Pandya
Hundi on Mysore-
Chamarajanagar Section
of NH-150A
Providing One Time
Improvement from Km.
0.000 to Km. 1.527 of old
Under
46 NH 373 and Km. 91.468 373 2.13 31-08-2026
Construction
to Km. 92.080 of NH 373
in Holenarasipura Town
Limit
Reconstruction of 7
Minor Bridges on NH-
150A from Km 142.00 to
171.00 on EPC Mode in Under
47 150A 2.91 31-08-2026
the state of Karnataka on Construction
EPC Mode under NH(O)
Annual Plan 2023-24 (NH-
150A-KNT-2023-24-998)
Remedial Measures and
Improvement of
Blackspot ID KA 03 110
at Mayagondanahalli Under
48 73 0.50 31-07-2026
Village of chainage Km Construction
166 175 NH 73 old NH
234 Mangalore Tumkur
section
Reconstruction of 4 lane Under
49 275 5.10 19-01-2027
major bridge at Km Construction173.600 across
Lakshmanathirtha River
along with approaches
from Km 171.300 to
176.400 in the Hunsur
town limits on NH-275
(Bantwal-Mysore Section)
Widening to Two Lane
with Paved Shoulders
from Km 0.00 (Design
Chainage 0.00) to Km
Under
50 23.338 (Design Chainage 166E 23.31 31-03-2027
Construction
23+310) of NH-166E
(MH/KNT Border-
Kanamadi- Bijjargi-
Tikota section)
Re construction of
Existing Major Bridge at
Under
51 near Maniknagar at Km 50 0.01 27-11-2027
Construction
99.225 on NH-50 Bidar
Humnabad Section
Widening to 4L+PS of NH-
548B from Km 118.450 Under
52 548B 10.00 29.05.2029
(Near Shirguppi) to Km Construction
128.450 (Near Ankali)
Construction of Retaining
wall from Km 78.000 to
125.000 (Selected
Under
53 Reaches) of NH - 275 275 1.91 17-02-2027
Construction
(Bantwal-Bangalore
section) selected
reaches
Strengthening of the road
stretch from Km 132.324
to Km 213.00 (excluding
km 137.200 to 144.400,
KM 163.800 to 165.200,
Under
54 KM 168.115 to 168.390, 275 65.60 26-10-2026
Construction
KM 171.300 to 176.400 &
Km 181.120 to 182.220)
(Kushalnagar- Hinkal-
Mysore Section) of NH-
275
55 6-laning of Davangere - 48 78.92 Partially 30-09-2026Haveri section of NH-48 Completed
4 lane of Tumkur -
Shimoga section of NH- Partially
56 206 52.89 31-08-2026
69 (Old NH-206) (Package Completed
- I)
4 lane of Tumkur -
Shimoga section of NH- Partially
57 206 56.71 31-12-2026
69 (Old NH-206) Package Completed
- II)
4-laning of Belgaum-
Partially
58 Khanapur Section of NH 748 30 31-03-2027
Completed
748.
Belkere - Sirsi - Kumta of Under
59 766E 58.92 31-08-2026
NH766E construction
4 laning of Tumkur -
Under
60 Shivmoga section of NH- 206 56.34 31-03-2027
construction
206 (Pkg-IV)
Four laning of Banavara
to Bettadahalli Section of Partially
61 206 48.52 31-12-2026
NH-69 (Old NH-206) Completed
Package III)
Widening to 4 lane of
Channarayapatna &
Under
62 Hassan bypass with 75 39.01 31-10-2026
construction
other project facilities of
NH-75
Construction of 6 lane
new bridge across Under
63 66 0.774 28-06-2027
Phalguni river near Kulur construction
on NH-66
4L of Addahole (Near
Gundya) to Bantwal Under
64 75 48.485 30-04-2027
Cross section (Pkg-02) of construction
NH-75 (Old NH-48)
4L of Sannur to
Bikarnakatte section of Under
65 169 45 30-04-2027
NH-169 Karkala - construction
Mangalore (Package-III)
Haveri – Yakumbi – Sirsi Under
66 766E 74.98 31-01-2028
Road 766E construction
6 laning of Nelamangala - Under
67 48 44.73 31-03-2027
Tumkur of NH-48 construction
68 6-laning from 48 37.83 Under 31-05-2027Sankeshwar Bypass - construction
MH/KNT Border of NH-48
Road connectivity to
Under
69 Honnavar Port from 66 4.58 31-05-2028
construction
Kasarkod on NH-66
Development of 6-lane
Access Controlled
Greenfiled highway Partially
70 150C 40.6 31-08-2026
from Baswantpur to Completed
Singnodi section of NH-
150C (Pkg IV)
Development of 6-lane
Access Controlled
Greenfiled hihgway from
Under
71 MH/KNT Border (Badadal) 150C 71 31-11-2026
construction
to Maradgi S Ankola
section of NH-150C (Pkg
II)
Construction of 4-lane
Under
72 greenf field highway from 648 20.9 30-11-2026
construction
TN/KA Border of NH-648
Construction of balance
work of 2 laning with PS
from Khanapur to Under
73 748 53.32 31-03-2027
Karnataka / Goa Border construction
section of NH-748 (Old
NH-4A)
6 laning of Hubli-Dharwad Under
74 48 30.35 31-05-2027
bypass of NH-48 construction
Development of 6-lane
Access Controlled
Highway from Maradgi S
Under
75 Andola to Baswantpur 150C 65.5 31-11-2026
construction
section of NH-150C (Pkg
III) of Akkalkot - KNT /TS
Border)
Mysore - madikere Under
76 275 22.7 08-04-2028
Package-2 of NH-275 construction
Mysore - madikere Under
77 275 24.1 19-01-2028
Package-3 of NH-275 construction
Mysore - madikere Under
78 275 26.55 06-03-2028
Package-4 of NH-275 construction
79 Mysore - madikere 275 18.98 Under 18-03-2028Package-5 of NH-275 construction
Belgaum Hungund
Raichur Under
80 748A 44.9 30-06-2027
Section (Package 6) of construction
NH-748A
Belgaum Hungund
Raichur Under
81 748A 46.2 31-08-2027
Section (Package 5) of construction
NH-748A
4L of Left-Over Works of
Hospet-Bellary - Under
82 67 95.37 10-04-2028
Karnataka/AP border of construction
NH-67
Belgaum Hungund
Raichur Under
83 748A 43.8 08-10-2027
Section (Package 1) of construction
NH-748A
Belgaum Hungund
Raichur Under
84 748A 46.1 02-07-2027
Section (Package 2) of construction
NH-748A
Belgaum Hungund
Raichur Under
85 748A 46.2 08-02-2028
Section (Package 3) of construction
NH-748A
Belgaum Hungund
Under
86 Raichur Section 748A 46.2 18-04-2028
construction
(Package 4) of NH-748A
Access Controlled
Highway of 4 lane with Under
87 150A 13.087 14-10-2027
paved shoulder of Bellary construction
Bypass of NH 150A
Additional works in 6L of
Bengaluru – Mysuru Under
88 275 2 19-01-2028
Access control with construction
close toll of NH-275
*****