Parliament Question: National Highway Projects in Karnataka

Issued by Ministry of Road Transport and Highways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 1883 ANSWERED ON 30th JULY, 2026 NATIONAL HIGHWAY PROJECTS IN KARNATAKA 1883. SHRI E TUKARAM: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) the total number of National Highway projects sanctioned in Karnataka from 2014 till date along with their total sanctioned length (in kms); (b) the total length (in kms) of National Highways completed and opened to traffic in Karnataka during the said period and the total length still under construction or yet to be completed; (c) the reasons for the delay in completion of the pending National Highway projects in Karnataka; and (d) the timeline including expected date for completion of the remaining National Highway projects in Karnataka, project-wise? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) Since 2014, a total of 372 National Highway projects having an aggregate length of 6077 km have been sanctioned in the State of Karnataka. (b) A total length of 4405 km have been completed and opened to traffic during the said period. The length of 2194 km is at various stages of implementation including construction & bidding. (c) The progress of National Highway projects depends upon timely availability of encumbrance-free land, statutory and forest/environment clearances, utility shifting, law and order issues, contractual matters, availability of construction materials, weather conditions and other unforeseen site-specific factors. Delays, wherever encountered, are attributable to one or more of these factors. The Government and implementing agencies continuously monitor the progress of projects and take appropriate measures forexpeditious execution by taking up the matter with State Government of Karnataka. (d) The project-wise status and expected date of completion of the ongoing National Highway projects in Karnataka are at Annexure.Annexure ANNEXURE REFERRED TO IN REPLY TO PART (d) OF LOK SABHA UNSTARRED QUESTION NO. 1883 ANSWERED ON 30TH JULY, 2026 ASKED BY SHRI E TUKARAM REGARDING NATIONAL HIGHWAY PROJECTS IN KARNATAKA Scheduled completion date/ Sl. NH Length Present Name of Project Revised No. No. (km) Status Scheduled completion date Widening to 2L+PS from Km 67 to Km 115 on Under 1 173 48.00 30-04-2027 Kadur-Hosadurga section Construction NH 173 Widening to Four Lane from Km 0+000 to Km 2+480 on NH-169 (Old Under 2 169 2.50 30-09-2026 NH-13 from km 530+700 Construction to 533.180 ) of Shimoga - Mangalore Section Construction of Yadgiri Bypass from Km. 70.900 Under 3 150 8.80 11-05-2027 to Km. 79.650 (Design Construction chainages) of NH-150 Construction of Srinivasapura Bypass from existing Km Under 4 453.890 Design Ch. 69 10.08 11-01-2027 Construction 0+000 to existing Km 461.450 Design Ch 10+080 on NH-69 Widening to 2L+PS from Km 71.00 to 104.00 (Existing chainages) Under 5 (Sarjapur to Pattadkallu) 367 26.00 31-12-2026 Construction on Bhanapur to Gaddanakeri section NH- 367 Widening to 2 Lane Under 6 150A 13.00 31-10-2026 Paved Shoulders from ConstructionKm 184.70 to Km 198.92 (Venkateshwara Camp to Dadesugur Camp Section) on NH-150A Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 (existing chainages) of Under 7 NH-766C (complete 766C 13.00 21-12-2027 Construction Realignment of 13.76 km) with 2 major Bridges across Sharavathi Backwaters Construction of Chintamani Bypass from Design Ch.0+000 Under 8 (Existing Ch.428+880) to 69 15.40 18-07-2027 Construction Design Ch.15+400 (Existing Ch.444+010) on NH-69 Widening to Two Lane with Paved Shoulders From Km 235.000 To Under 9 150A 19.80 14-09-2026 254.800 of Sindigeri- Construction Bellary Section on NH- 150A Widening to 4L+PS of NH- 548B from Km 80.000 (Near Murgundi) to Km Under 10 140.200 (Near Chikkodi) 548B 50.20 23-04-2028 Construction excluding length from Km 118.450 to Km 128.450 Construction of Bypass at Kuknoor, Yelburga, Under 11 Gajendragada of 367 17.30 25-06-2027 Construction Bhanapur Gaddanakeri section of NH-367 Widening to Two Lane with Paved Shoulders from KB Cross to Under 12 150A 42.26 13-01-2027 Chunchanahalli ie., Construction Design Ch. 485+240 Km Existing Km494.000 to Design Ch. 523+393 Km Existing km 533.152 & From Design Ch. 530+393 Existing Km 540.175 to Design Ch. 534+476 Existing Km 544.200 at Nelligere of NH-150A Widening to 2L+PS from Km 0.000 to 37.850 (Except Ex. Km 24.45 to Under 13 766C 35.10 06-08-2027 27.20) of NH-766C Construction Byndoor-Ranebennur Section Widening to 2 Lane with Paved Shoulders from design Km 103.200 (Existing Km 103.200) to Under 14 544E 13.53 31-08-2026 design Km 116.700 Construction (Existing Km 118.470) on AP/KNT Border to Sira Section of NH-544E Widening to two lane with paved shoulders from Km 0.00 to 102.310 Under 15 548B 102.31 15-01-2027 (Design Chainage) of NH- Construction 548B (Murrum- Maharashtra Border) Widening of existing road to 2 lane with paved Shoulders from Km Under 16 169 8.80 30-11-2026 115.00 to Km 123.80 of Construction NH-169 on Shivamogga - Mangalore Section Realignment of road from Km 35.935 to 39.255 (Chowdapur village) Km 58.220 to Km 62.290 Under 17 150E 7.73 31-12-2026 (Afzalpur town) and Km Construction 70.125 to Km 72.920 (Ballurgi village) of NH- 150E 18 One time improvements 69 6.55 Under 31-08-2026of Gauribidanur town Construction bypassed stretch of NH- 69 Construction of Bypass to Naragund Town NH-52 (Old NH-218) (existing CH Under 19 from Km.133.040 to 52 7.30 31-12-2026 Construction 140.843) Design CH. 0.0 to 7.30 Bijapur-Hubli Section Construction of Shikaripura bypass from existing Km. 146.150 to Under 20 existing Km. 154.0 766C 6.58 30-12-2026 Construction (design chainage from Km. 0.00 to Km. 6.576) of NH-766C Widening to two lane with paved Shoulders from Km 40.00 to Km Under 21 75.00 Existing 73 33.10 31-12-2026 Construction chainages of Mangalore - Tumkur section of NH- 73 Widening to 4 lane from Km 51.60 to 76.20 (Hebri to Parkala) and from Km Under 22 85.20 to 88.90 (Karavali 169A 28.30 30-11-2026 Construction junction to Malpe) of Thirthahalli-Udupi-Malpe Section of NH-169A Widening to existing 2 lane with paved Shoulder to 4 Lane with paved shoulder from design Km Under 23 169 15.27 30-11-2026 153.00 to 168.27 (Mala Construction Gate to Karkala) of NH - 169 on Shimoga - Mangalore section Widening Two lane with Paved shoulder from Km Under 24 494.450 to Km 505.500 of 234 11.09 31-08-2026 Construction NH-234 (Mulbagal to AP Border)Widening to existing 2 lane with paved Shoulder from Km 15.980 Under 25 (Megaravalli) to Km 169A 14.77 30-12-2026 Construction 30.750 (Agumbe) of NH- 169A on Thirthahalli - Malpe section Widening to 2-Lane with Paved Shoulders from Km 116.800 to Under 26 173 31.72 31-07-2026 149.070(Design Changes) Construction on Hosadurga - Holalkere Section of NH-173 Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to Under 27 142.00 (Liingasur to 150A 30.94 31-08-2026 Construction Mudabal cross) & from Km. 147.070 to Km. 149.070 (Maski city limit) of Jewargi Chamrajnagar setion of NH-150A Widening to 4 lane from Km. 133.00 to 158.04 (design Chainage Km. Under 28 367 24.27 31-03-2027 130.88 to 155.145) Construction (Shirur Cross to Gaddankeri) of NH-367 Construction of 6 lane with service road RUB at Km. 5.46, Km. 7.06, Km Under 29 275K 1.10 15-09-2026 7.86 and Km. 28.585 of Construction NH- 275K (Mysore Ring Road) Balance work of Construction of Two/Four lane with paved shoulder Under 30 13 101.60 30-08-2026 from Km 422.000 to Construction 523.600 ( Chitradurga to Shivamogga ) of NH-13 Widening to Four Lane Under 31 69 8.40 30-12-2026 Divided Carriageway Constructionfrom Km 278.00 to Km 286.40 in Sagar Town limits on Tumkur- Honnavara Section of NH-206 (new NH-69) Widining from Existing intermidiate lane to Four lane in Sringeri Town limits from ch 110.00 to Under 32 169 5.00 31-07-2026 ch 115.00 (old ch 640.00 Construction to 645.00) of NH-169 (old NH-13) of shimoga- Mangalore section Widening of Major Bridge at Ch 171.601 (Existing Under 33 chainage 172.310) on NH- 150A 0.50 31-07-2026 Construction 150A (Jewaragi - Chamarajnagar Section) Widening to 2 lane with paved shoulders from design Km. 199.200 to design Km. 214.880 of Under 34 150A 15.68 30-04-2027 (Ibrampura to Construction Tekkalkote) of NH-150A Jewargi-Chamrajnagar section Construction of Elevated corridor from Km. 135.650 to 136.300 on 63, from Km. 249 to Km. 250.050 on old NH-4 and 63 & Under 35 3.60 30-11-2026 from Km. 192.910 to Km. 218 Construction 193.350 on NH-218 from decongestion of traffic in Ranichennamma circle in Hubli city Construction of Major Bridge at Km.180.865 Under 36 across river Krishna on 167 2.12 30-04-2027 Construction NH 167 Hagari Jadcherla section Construction of 4 lane Under 37 ROB and its approaches 218 1.51 31-08-2026 Construction in lieu of existing levelcrossing 75 at Km.15 on NH 218 Construction of 4 lane ROB and its approaches in lieu of existing 56T-C-2 Under 38 367 0.01 31-12-2026 at Km. 0.517 on NH-367 Construction (Bhanapura and Koppal satations) Widening of existing 2 lane to 4 lane with paved shoulder from Designed km 25.15 to km 56.70 (Except Km 52.70 to Under 39 169 30.75 24-02-2028 53.50) of NH-169 ( Construction Nellisara Camp to Thirthahalli ) of NH-169 on Shimoga-Mangalore section Construction of 2-Lane ROB in lieu of LC -110E at existing Km 340+640 (Sudha Cross in Ballari Under 40 67 1.50 31-03-2027 City Limits) on Old NH-63 Construction (New NH-67) on Hosapete to Ballari Section Widening to two lane with paved shoulder of Under 41 NH-73(New) spur road 73 28.49 04-11-2027 Construction Ujire - Dharmasthala - Periyashanthi Improvement to Black Spot at Devalapura Cross Under 42 ring road (KA-(05)-19) on 275K 0.01 17-01-2027 Construction NH-275K Mysuru Ring Road section Construction of 4 lane ROB at Km 40.134 on NH- 150 including balance approach work from Km Under 43 150 2.00 23-09-2027 39.560 to Km 40.065 and Construction from Km 40.203 to 40.612 of NH-150 of Kalaburagi districtImprovement to 2lane with Paved Shoulder from Km 597.560 (Pandavapura Town Under 44 150A 11.38 31-08-2026 Limit) to 606.670 Construction (Kiranguru) on NH-150A (Jewargi-Chamarajnagar Section) Construction of 4 lane ROB in lieu of LC No. 47 at Km 49/600-700 (NH Design Ch: 673+000) between Nanjangud Under 45 Town (NTW) and 150A 1.73 13-08-2027 Construction Chamarajanagar (CMNR) Stations near Pandya Hundi on Mysore- Chamarajanagar Section of NH-150A Providing One Time Improvement from Km. 0.000 to Km. 1.527 of old Under 46 NH 373 and Km. 91.468 373 2.13 31-08-2026 Construction to Km. 92.080 of NH 373 in Holenarasipura Town Limit Reconstruction of 7 Minor Bridges on NH- 150A from Km 142.00 to 171.00 on EPC Mode in Under 47 150A 2.91 31-08-2026 the state of Karnataka on Construction EPC Mode under NH(O) Annual Plan 2023-24 (NH- 150A-KNT-2023-24-998) Remedial Measures and Improvement of Blackspot ID KA 03 110 at Mayagondanahalli Under 48 73 0.50 31-07-2026 Village of chainage Km Construction 166 175 NH 73 old NH 234 Mangalore Tumkur section Reconstruction of 4 lane Under 49 275 5.10 19-01-2027 major bridge at Km Construction173.600 across Lakshmanathirtha River along with approaches from Km 171.300 to 176.400 in the Hunsur town limits on NH-275 (Bantwal-Mysore Section) Widening to Two Lane with Paved Shoulders from Km 0.00 (Design Chainage 0.00) to Km Under 50 23.338 (Design Chainage 166E 23.31 31-03-2027 Construction 23+310) of NH-166E (MH/KNT Border- Kanamadi- Bijjargi- Tikota section) Re construction of Existing Major Bridge at Under 51 near Maniknagar at Km 50 0.01 27-11-2027 Construction 99.225 on NH-50 Bidar Humnabad Section Widening to 4L+PS of NH- 548B from Km 118.450 Under 52 548B 10.00 29.05.2029 (Near Shirguppi) to Km Construction 128.450 (Near Ankali) Construction of Retaining wall from Km 78.000 to 125.000 (Selected Under 53 Reaches) of NH - 275 275 1.91 17-02-2027 Construction (Bantwal-Bangalore section) selected reaches Strengthening of the road stretch from Km 132.324 to Km 213.00 (excluding km 137.200 to 144.400, KM 163.800 to 165.200, Under 54 KM 168.115 to 168.390, 275 65.60 26-10-2026 Construction KM 171.300 to 176.400 & Km 181.120 to 182.220) (Kushalnagar- Hinkal- Mysore Section) of NH- 275 55 6-laning of Davangere - 48 78.92 Partially 30-09-2026Haveri section of NH-48 Completed 4 lane of Tumkur - Shimoga section of NH- Partially 56 206 52.89 31-08-2026 69 (Old NH-206) (Package Completed - I) 4 lane of Tumkur - Shimoga section of NH- Partially 57 206 56.71 31-12-2026 69 (Old NH-206) Package Completed - II) 4-laning of Belgaum- Partially 58 Khanapur Section of NH 748 30 31-03-2027 Completed 748. Belkere - Sirsi - Kumta of Under 59 766E 58.92 31-08-2026 NH766E construction 4 laning of Tumkur - Under 60 Shivmoga section of NH- 206 56.34 31-03-2027 construction 206 (Pkg-IV) Four laning of Banavara to Bettadahalli Section of Partially 61 206 48.52 31-12-2026 NH-69 (Old NH-206) Completed Package III) Widening to 4 lane of Channarayapatna & Under 62 Hassan bypass with 75 39.01 31-10-2026 construction other project facilities of NH-75 Construction of 6 lane new bridge across Under 63 66 0.774 28-06-2027 Phalguni river near Kulur construction on NH-66 4L of Addahole (Near Gundya) to Bantwal Under 64 75 48.485 30-04-2027 Cross section (Pkg-02) of construction NH-75 (Old NH-48) 4L of Sannur to Bikarnakatte section of Under 65 169 45 30-04-2027 NH-169 Karkala - construction Mangalore (Package-III) Haveri – Yakumbi – Sirsi Under 66 766E 74.98 31-01-2028 Road 766E construction 6 laning of Nelamangala - Under 67 48 44.73 31-03-2027 Tumkur of NH-48 construction 68 6-laning from 48 37.83 Under 31-05-2027Sankeshwar Bypass - construction MH/KNT Border of NH-48 Road connectivity to Under 69 Honnavar Port from 66 4.58 31-05-2028 construction Kasarkod on NH-66 Development of 6-lane Access Controlled Greenfiled highway Partially 70 150C 40.6 31-08-2026 from Baswantpur to Completed Singnodi section of NH- 150C (Pkg IV) Development of 6-lane Access Controlled Greenfiled hihgway from Under 71 MH/KNT Border (Badadal) 150C 71 31-11-2026 construction to Maradgi S Ankola section of NH-150C (Pkg II) Construction of 4-lane Under 72 greenf field highway from 648 20.9 30-11-2026 construction TN/KA Border of NH-648 Construction of balance work of 2 laning with PS from Khanapur to Under 73 748 53.32 31-03-2027 Karnataka / Goa Border construction section of NH-748 (Old NH-4A) 6 laning of Hubli-Dharwad Under 74 48 30.35 31-05-2027 bypass of NH-48 construction Development of 6-lane Access Controlled Highway from Maradgi S Under 75 Andola to Baswantpur 150C 65.5 31-11-2026 construction section of NH-150C (Pkg III) of Akkalkot - KNT /TS Border) Mysore - madikere Under 76 275 22.7 08-04-2028 Package-2 of NH-275 construction Mysore - madikere Under 77 275 24.1 19-01-2028 Package-3 of NH-275 construction Mysore - madikere Under 78 275 26.55 06-03-2028 Package-4 of NH-275 construction 79 Mysore - madikere 275 18.98 Under 18-03-2028Package-5 of NH-275 construction Belgaum Hungund Raichur Under 80 748A 44.9 30-06-2027 Section (Package 6) of construction NH-748A Belgaum Hungund Raichur Under 81 748A 46.2 31-08-2027 Section (Package 5) of construction NH-748A 4L of Left-Over Works of Hospet-Bellary - Under 82 67 95.37 10-04-2028 Karnataka/AP border of construction NH-67 Belgaum Hungund Raichur Under 83 748A 43.8 08-10-2027 Section (Package 1) of construction NH-748A Belgaum Hungund Raichur Under 84 748A 46.1 02-07-2027 Section (Package 2) of construction NH-748A Belgaum Hungund Raichur Under 85 748A 46.2 08-02-2028 Section (Package 3) of construction NH-748A Belgaum Hungund Under 86 Raichur Section 748A 46.2 18-04-2028 construction (Package 4) of NH-748A Access Controlled Highway of 4 lane with Under 87 150A 13.087 14-10-2027 paved shoulder of Bellary construction Bypass of NH 150A Additional works in 6L of Bengaluru – Mysuru Under 88 275 2 19-01-2028 Access control with construction close toll of NH-275 *****

Continue your research