GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 651
TO BE ANSWERED ON 22.07.2026
NEW RAILWAY LINE FOR ARAKALAGUDU IN HASSAN DISTRICT
651. SHRI SHREYAS M PATEL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has received any proposal or representation
for construction of a new railway line connecting Arakalagudu in
Hassan district with the existing railway network and if so, the details
thereof;
(b) whether any survey, reconnaissance, feasibility study or Detailed
Project Report (DPR) has been conducted or is proposed for a new
railway line to Arakalagudu and if so, the details and present status
thereof;
(c) whether the Government proposes to consider a new railway line on
the Shravanabelagola – Holenarasipura – Arakalagudu – Somwarpet –
Madikeri - Mangaluru corridor to improve connectivity in the region;
(d) if so, the details of the proposal, including the estimated cost, funding
pattern and expected timeline for approval and implementation; and
(e) if not, the reasons therefor and the criteria adopted by the Ministry for
sanctioning new railway line projects in the region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Arakalagudu is about 22 Km away from Hole Narsipur Railway
station which serves as the transportation hub for the nearby regions.
§ Page 1 of 6Shravanabelagola and Mangaluru are already connected through existing
railway network via Hassan. Subsequently, to provide connectivity to
Madikeri, a feasibility study of Shravanabelagola to Madikeri via
Holenarsipura-Arkalgud-Konanur-Khushalnagar new line (117 Km) has been
carried out. The project has low traffic projections.
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Karnataka is as under:
Period Outlay
2009-14 ₹835 crore/year
2026-27 ₹7,748 crore (more than 9 times)
Track Construction:
The details of constructing new track falling fully/partly in the State of
Karnataka is as under:
Period New track Commissioned Average commissioning of new
tracks
2009-14 565 Km 113 Km/year
2014-26 1,769 Km 147.4 Km/year
Projects sanctioned:-
As on 01.04.2026, 25 projects (15 new lines and 10 doubling) of 2,935 km
length, costing ₹49,272 crore falling fully/partly in Karnataka are
sanctioned. The summary is as under:-
Page 2 of 6Category No of Total Length Exp
sanctioned Length Commissioned upto Mar'26
Projects (in Km) Upto Mar'26 (₹ in cr.)
(Km)
New Line 15 2,034 445 8,836
Doubling/ 10 901 301 4,562
Multitracking
Total 25 2,935 746 13,398
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Karnataka are as under:
S. Project Cost
No. (₹ in Crores)
1 Kottur-Harihar new line (65 km) 468
2 Hassan-Bangalore new line (167 km) 1,290
3 Bidar-Gulbarga new line (110 km) 1,543
4 Shivani - Hosadurga Road doubling (10 km) 50
5 Shivani-Birur doubling (29 km) 143
6 Hosadurga-Chikjajur doubling (29 km) 260
7 Ramanagram - Mysore patch doubling (94 km) 998
8 Yelahanka – Chennasadra doubling (13 km) 108
9 Yeshwantpur - Yelahanka doubling(12 km) 95
10 Netrawati - Mangalore Central doubling (2 km) 28
11 Kankanadi - Panambur doubling (19 km) 350
12 Arsikere-Tumkur doubling (96 km) 758
13 Yelahanka - Penukonda doubling (123 km) 1,104
14 Daund-Gulbarga doubling (225 km) 3,182
15 Hubli-Chikjajur doubling (190 km) 1,850
16 Hotgi-Gadag doubling (284 km) 2,459
17 Pune-Miraj-Londa doubling (466 km) 6,464
18 Jokkate-Thokur doubling (2 km) 102
Ongoing Projects:-
Details of some of the projects falling fully/partly in Karnataka which have
been taken up are as under:
Page 3 of 6Cost
S No. Project (₹ in
Crores)
1. Munirabad-Mahabubnagar new line (247 km) 3,978
2. Kadur - Sakleshpur new line (68 km) 908
3. Rayadurg - Tumkur new line (207 km) 4,565
4. Bagalkot - Kudachi new line (142 km) 1,694
5. Tumkur - Devangere new line (182 km) 2,142
6. Marikuppam - Kuppam new line (24 km) 518
7. Gadag - Wadi new line (257 km) 3,668
8. Shimoga - Ranebennur new line (96 km) 994
9. Hassan - Belur new line (32 km) 749
10. Dharwad -Belgaum new line (73 km) 927
Hospet - Hubli - Londa - Tinaighat - Vasco - de - Gama 4,730
11.
doubling (312 km)
12. Baiyyapanahalli - Hosur doubling (48 km) 1,160
13. Yeshwanthpur- Channasandra doubling (22 km) 684
14. Ballari-Chikjajur doubling (185 km) 3,342
15. Secunderabad - Wadi 3rd & 4th line (173 km) 5,012
16. Bellary - Hosapete 3rd & 4th line (65 km) 2,372
17. Guntakal-Wadi 3rd & 4th line (230 km) 4,758
Details of some major projects which are delayed due to land acquisition
are as under:-
Total Land Balance
S Land acquired Land to be
Project
No. required (in ha) acquired
(in ha) (in ha)
1 Shimoga–Rannebennur new line
559 283 276
(96 km)
2 Belgaum–Dharwad new line (73
581 0 581
km)
3 Shimoga– Harihar new line (79 km) 488 0 488
4 Whitefield-Kolar new line (53 km) 337 0 337
5 Hassan-Belur new line (32 km) 206 0 206
Page 4 of 6Summary of the status of land acquisition in Karnataka is as under:-
Total Land required for Projects in Karnataka 10,123 ha
Land Acquired 6,134 ha (61%)
Balance Land to be acquired 3,989 ha (39%)
Government of India is geared up to execute projects, however success
depends upon the support of Government of Karnataka.
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Page 5 of 6 Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 6 of 6