See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4124
TO BE ANSWERED ON 12.08.2026
NEW RAILWAY LINES IN UTTAR PRADESH
4124. SHRI ANAND BHADAURIA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Government proposes for laying of new railway lines from
Hardoi-Lakhimpur, Farrukhabad-Gola and Jharekhapur-Bahraich
(Uttar Pradesh) in view of the problems being faced by residents of
these areas in absence of railway connectivity;
(b) if so, the details thereof;
(c) whether the Government is likely to ensure survey for above
mentioned new railway lines on priority basis and start laying of
these lines during the current year; and
(d) if so, the details thereof and if not, the reasons therefor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Hardoi and Lakhimpur are already connected through existing
railway network via Balamau, Sitapur. Farrukhabad and Gola Gokarannath
are already connected through existing railway network via Kasganj and
Bareilly. Jharekapur and Bahraich are already connected through existing
railway network via Burhwal and Gonda.
To improve connectivity in the surrounding area, Bahraich-Khalilabad New
Line project (240 Km) has been sanctioned at a cost of ₹4,940 crore. An
expenditure of ₹1,525 crore has been incurred upto March 2026 and an
§ Page 1 of 6outlay of ₹686 crore has been provided for this project for the year
2026-27.
The project has been notified as “Special Railway Project” for acquisition
of land through State Government. Major section-wise progress is as
under:
Section Status
Khalilabad-Bansi (54 Km) 246.81 Ha. out of 254.44 Ha. land has
been acquired.
37.03L Cum. out of 61.71L Cum.
earth work has been completed.
Section involves construction of 26
major bridges and 7 station buildings.
27 out of 56 RUBs have been
completed.
4 ROBs have been planned.
Bansi-Ikauna (120 Km) 48.02 Ha. out of 568.22 Ha. land has
been acquired.
Ikauna-Bahraich (66 Km) 274.17 Ha. out of 329.60 Ha. land has
been acquired.
To provide direct connectivity, survey for Farrukhabad-Shahjahanpur-Gola
Gokarannath New Line (151 Km) was carried out. However, the project has
low traffic projections.
Also, to provide direct connectivity from Sitapur (approx. 20 Km from
Jharekapur) to Bahraich, Final Location Survey (FLS) for Sitapur City-
Bahraich New Line (99 Km) has been sanctioned for preparation of Detailed
Project Report (DPR).
Page 2 of 6After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
sanctioning of projects is a continuous and dynamic process, exact
timelines depend upon appraisals and approvals by various stakeholders.
Uttar Pradesh
Railway Budget:
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Uttar Pradesh is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2026-27 ₹20,012 crore (More than 18 times)
Track construction:
The details of constructing new tracks falling fully/partly in the State of
Uttar Pradesh are as under:
Period New Track Average Commissioning of new
Commissioned tracks
2009-14 996 Km 199 Km per year
2014-26 5,499 Km 458 Km per year (More than 2 times)
Projects sanctioned:
As on 01.04.2026, 49 projects (09 New Line, 01 Gauge Conversion and 39
Doubling) of 3,691 Km length, costing ₹62,417 crore falling fully/partly in
the State of Uttar Pradesh are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto Mar'26
(Km) (Km) (₹ in Cr.)
New Line 09 1,200 365 11,885
Gauge Conversion 01 11 0 27
Doubling/ 39 2,480 985 21,631
Multitracking
Total 49 3,691 1,350 33,543
Page 3 of 6Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Uttar Pradesh are as under:
SN Project Cost
(₹ in Cr.)
1 Meerut-Muzaffarnagar Doubling (55 Km) 430
2 Bahraich-Nepal Ganj Gauge Conversion (56 Km) 342
3 Ballia-Ghazipur City Doubling (65 Km) 650
4 Ghazipur City-Tarighat New Line (17 Km) 1,766
5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863
6 Gonda-Bahraich Gauge Conversion (60 Km) 318
7 Barabanki-Akbarpur Doubling (161 Km) 1,700
8 Kaptanganj-Chhapra Gauge Conversion (234 Km) 819
9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589
10 Indara-Dohrighat Gauge Conversion (34 Km) 213
11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1,634
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Lahota-Bhadoi Doubling (39 Km) 184
14 Etawah-Mainpuri New Line (58 Km) 313
15 Phaphamau-Prayagraj Doubling (14 Km) 212
16 Muzaffarnagar-Tapri Doubling (52 Km) 525
17 Utretia-Raibareilly Doubling (66 Km) 662
18 Raibareilly-Amethi Doubling (60 Km) 668
19 Alamnagar-Utretia Doubling (20 Km) 358
20 Bhimsen-Jhansi Doubling (206 Km) 2,620
21 Domingarh-Kusumhi 3rd Line and Gorakhpur-Nakaha 508
Jungle Doubling (21 Km)
22 Malhaur-Daliganj Doubling (13 Km) 183
23 Ruma Chakeri-Chandari 3rd Line (13 Km) 177
24 Bareilly-Tanakpur Gauge Conversion (102 Km) 313
25 Rosa- Burhwal Doubling (181 Km) 2,094
26 Jaunpur-Akbarpur Doubling (77 Km) 676
27 Ramna-Singrauli Doubling (160 Km) 2,436
28 Janghai-Phaphamau Doubling (47 Km) 414
29 Varanasi-Prayagraj Doubling (120 Km) 2,018
30 Karaila Road-Shaktinagar Doubling (32 Km) 763
Page 4 of 631 Deoband-Roorkee New Line (27 Km) 1,289
32 Agra-Etawah New Line(110 Km) 427
33 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1,778
34 Janghai-Pratapgarh-Amethi Doubling (87 km) 1,429
35 Burhwal-Gonda 3rd Line (62 Km) 1,308
Ongoing projects:
Some of the projects falling fully/partly in the State of Uttar Pradesh which
have been taken up are as under:
SN Project Cost
(₹ in Cr.)
1 Barabanki-Burhwal 3rd Line (27 Km) 426
2 Burhwal-Gonda Kacheri 4th Line (56 Km) 796
3 Bahraich-Khalilabad New Line (240 Km) 4,940
4 Katra-Ayodhya Dham Doubling (10 Km) 466
5 Pt. Deen Dayal Upadhyaya-Prayagraj 3rd Line (150 Km) 2,649
6 Billi-Chunar Doubling (102 Km) 1,424
7 Chhapra-Ballia Doubling (65 Km) 1,046
8 Etah-Kasganj New Line ( 29 Km) 389
9 Gorakhpur-Valmikinagar Doubling (96 Km) 1,121
10 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th Line 2,464
(15 Km)
11 Jhansi- Manikpur & Khairar-Bhimsen Doubling (431 Km) 4,330
12 Sahjanwa-Dohrighat New Line (81 Km) 1,320
13 Prayagraj (Iradatganj)-Manikpur 3rd Line (84 Km) 1,508
14 Bhatni-Aunrihar Doubling (117 Km) 2,529
15 Mathura-Jhansi 3rd line (274 Km) 5,961
16 Agra Fort-Bandikui Doubling (150 Km) 988
17 Barabanki-Malhaur 3rd & 4th Line (33 Km) 450
18 Phaphamau-Unchahar Doubling (72 Km) 899
19 Aunrihar-Varanasi City 3rd Line (31 Km) 497
20 Ghaziabad-Sitapur 3rd & 4th Line (403 Km) 14,926
21 Nagda-Mathura 3rd & 4th Line (568 Km) 16,403
22 Burhwal-Sitapur City 3rd & 4th Line (103 Km) 2,276
Page 5 of 6In last three years 2023-24, 2024-25, 2025-26 and current financial year
2026-27, 78 surveys (13 New Line, 02 Gauge Conversion and 63 Doubling)
covering a total length of 3,860 Km has been sanctioned falling fully/partly
in the State of Uttar Pradesh.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
*****
Page 6 of 6