GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 666
TO BE ANSWERED ON 03.12.2025
NEW RAILWAY PROJECTS FOR MAHARASHTRA AND MADHYA PRADESH
666. DR. SHRIKANT EKNATH SHINDE:
SHRI NARESH GANPAT MHASKE:
SMT. BHARTI PARDHI:
SHRI RAVINDRA DATTARAM WAIKAR:
SHRI SHRIRANG APPA CHANDU BARNE:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has assessed the current status of passenger
safety, punctuality and cleanliness and if so, the details thereof;
(b) the steps taken/being taken by the Government during the last three years
to modernise stations, introduce digital ticketing and improve passenger
amenities, State/UT-wise;
(c) whether plans exist to expand connectivity to remote, hilly and border
regions to promote regional development and if so, the details thereof;
(d) the measures implemented/being implemented to reduce fright delays and
promote cost-effective transport for farmers and small businesses;
(e) the funds allocated for new projects to Maharashtra and Madhya Pradesh
including Balaghat Lok Sabha Constituency during the last three years and the
current year in Mumbai suburban network, Project-wise; and
(f) whether a long-term roadmap exists for sustainable operations including
100 per cent electrification and carbon footprint reduction and if so, the details
thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there has been asteep decline in the number of accidents. Consequential Train Accidents have
reduced from 135 in 2014-15 to 31 in 2024-25 as shown in the graph below.
It may be noted that the Consequential Train Accidents during the period
2004-14 was 1711 (average 171 per annum), which has declined to 31 in 2024-25
and further to 11 in 2025-26 (upto November, 2025).
Another important index showing improved safety in train operations is
Accidents Per Million Train Kilometer (APMTKM) which has reduced from 0.11 in
2014-15 to 0.03 in 2024-25, indicating an improvement of approx. 73% during the
said period.
234
s
tn
e
d
ic
c
A 165
n
ia
rT
la 135
itn
e
u
q
e
s
n
o
C
fo
.o 55 48
N 40
31
35
22
11
Safety Measures:-
The various safety measures taken to enhance safety in train operations are as
under:-
1. On Indian Railways, the expenditure on Safety related activities has
increased over the years as under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
(Act.) (Act.) (Act.)
39,463 87,327 1,01,651 1,14,022 1,16,4702. Electrical/Electronic Interlocking Systems with centralized operation of points
and signals have been provided at 6,656 stations up to 31.10.2025 to reduce
accident due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,098 Level
Crossing Gates up to 31.10.2025 for enhancing safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by verification of
track occupancy by electrical means has been provided at 6,661 stations up to
31.10.2025.
5. Kavach is a highly technology intensive system, which requires safety
certification of highest order. Kavach was adopted as a National ATP system
in July 2020. Kavach is provided progressively in phased manner. Initially,
Kavach Version 3.2 was deployed on 1465 RKm of South Central Railway and
80 RKm of North Central Railway. Kavach specification Version 4.0 was
approved by RDSO on 16.07.2024.After extensive and elaborate trials, Kavach
Version 4.0 has been successfully commissioned on Palwal-Mathura-Kota-
Nagda section (633Rkm) on Delhi-Mumbai route and on Howrah-Bardhaman
section (105RKm)on Delhi-Howrah route. Kavach implementation has been
taken up in balance sections of Delhi-Mumbai and Delhi-Howrah route. Further,
Kavach implementation has been taken up on 15,512 RKm covering all GQ, GD,
HDN and identified sections of Indian Railways.
6. Detailed instructions on issues related with safety of Signalling, e.g.
mandatory correspondence check, alteration work protocol, preparation of
completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per protocol
has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to improve
alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is located two
OHE masts prior to the signals in electrified territories to alert the crew about
the signal ahead when visibility is low due to foggy weather.10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog affected
areas which enables loco pilots to know the distance of the approaching
landmarks like signals, level crossing gates, etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS)
rails, Prestressed Concrete Sleeper (PSC) Normal/Wide base sleepers with
elastic fastening, fan shaped layout turnout on PSC sleepers, Steel Channel/H-
beam Sleepers on girder bridges is used while carrying out primary track
renewals.
12. Mechanisation of track laying activity through use of track machines like
PQRS, TRT, T-28 etc. to reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing progress of
rail renewal and avoiding welding of joints, thereby improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and timely
removal of defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic Welding and
adoption of better welding technology for rails i.e., Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System) and TRC
(Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout renewal
works.
19. Inspections at regular intervals are carried out to monitor and educate staff
for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track database and
decision support system has been adopted to decide rationalized maintenance
requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g. integrated
block, corridor block, worksite safety, monsoon precautions, etc. have been
issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is undertaken
to ensure safe train operations.23. Replacement of conventional ICF design coaches with LHB design coaches is
being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been
eliminated by January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of Bridges.
The requirement of repair/rehabilitation of Bridges is taken up based upon the
conditions assessed during these inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for widespread
passenger information in all coaches. Fire posters are provided in every coach
so as to educate and alert passengers regarding various Do‟s and Don‟ts to
prevent fire. These include messages regarding not carrying any inflammable
material, explosives, prohibition of smoking inside the coaches, penalties etc.
27. Production Units are providing Fire detection and suppression system in newly
manufactured Power Cars and Pantry Cars, Fire and Smoke detection system
in newly manufactured coaches. Progressive fitment of the same in existing
coaches is also underway by Zonal Railways in a phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open Lines) General
Rules vide Gazette notification dated 30.11.2023, wherein work of integrated
maintenance/repair/replacement of assets is planned up to 52 weeks in
advance on rolling basis and executed as per plan.
The details of the Safety related works related to better maintenance
practices, Technological improvements, better infrastructure and rolling stock
etc. undertaken by Railways are tabulated below:-
2004-05 2014-15 2014-25
S.N. Item to to Vs.
2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality rails 57,450 Km 1.43 Lakh Km More than 2
(60 Kg) (Km) times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)3. Electronic Interlocking 837 Stations 3,691 Stations More than 4
(Stations) times
4. Fog Pass Safety Devices As on 31.03.14: As on 31.03.25: 288 times
(Nos.) 90 Nos. 25,939 Nos.
5. Thick Web Switches Nil 28,301 Nos.
(Nos.)
Better Maintenance Practices
1. Primary Rail Renewal 32,260 Km 49,941 Km 1.5 times
(Track Km)
2. USFD (Ultra Sonic Flaw 79.43 Lakh 2 Cr. More than 2
detection) Testing of times
Welds (Nos.)
3. Weld failures (Nos.) In 2013-14: In 2024-25: 90 %
3699 Nos. 370 Nos. reduction
4. Rail fractures (Nos.) In 2013-14: In 2024-25: More than
2548 Nos. 289 Nos. 88% reduction
Better Infrastructure and Rolling Stock
1. New Track KM added 14,985 Km 34,428 Km More than 2
(Track Km) times
2. Flyovers (RoBs)/ 4,148 Nos. 13,808 Nos. More than 3
Underpasses (RUBs) times
(Nos.)
3. Unmanned Level As on 31.03.14: As on 31.03.24: Removed
crossings 8,948 Nil
(Nos.) on BG (All eliminated
by 31.01.19)
4. Manufacture of LHB 2,337 Nos. 42,677 More than 18
Coaches (Nos.) times
Punctuality:-
Indian Railways makes all possible efforts to run trains on time. Several
factors affect punctual running of trains which include foggy weather, path
constraints, asset maintenance, alarm chain pulling, agitations, cattle run over
and other unforeseen circumstances.
Based on assessments of factors affecting the punctual running of trains,
remedial measures, both short term and long term, are taken which include
capacity augmentation of rail network, upgradation of track and signaling system,
removing operational bottlenecks, yard remodeling etc. Due to the above
measures, the overall punctuality of trains during 2025-26 (upto October, 2025)
has been about 80%.Cleanliness:-
I. Cleanliness and housekeeping of trains & stations is a continuous process
and Indian Railways make every endeavor to keep trains & stations in
properly maintainedandcleancondition.
II. To ensure cleanliness, regular checks/surprise checks/surprise checks are
conducted by supervisors/senior officials at Divisional, Zonal & Headquarter
level with special focus on general class.
III. Special Cleanliness Campaigns under Swatch Bharat Abhiyan and
cleanliness drives/campaigns are organized regularly over Indian Railways
with the objective to achieve significant and sustainable improvements in
cleanliness standards.
IV. Regular monitoring is also ensured through Rail Madad portal which has
been developed to enable passengers to highlight their needs and seek
assistance on passenger amenities, cleanliness, etc.
Station Modernisation and Passenger Amenities:-
Modernization/upgradation of Railway Stations is undertaken under various
modernization schemes. At present, stations are developed under „Amrit Bharat
Station Scheme‟ which envisages development of stations on a continuous basis
with a long term approach. Ministry of Railways has launched „Amrit Bharat
Station Scheme‟ for redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:-
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water booths
Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
Provision of lift/escalators/ramp Improvement/Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like „One Station
One Product‟
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing and
feasibility and creation of city centre at the station in the long term.
So far, 1,337 stations have been identified for development under „Amrit
Bharat Station Scheme‟, out of which 132 stations are located in the State of
Maharashtra and 80 stations are located in the State of Madhya Pradesh. The
names of stations identified for development under „Amrit Bharat Station
Scheme‟ in the State of Maharashtra and Madhya Pradesh are as following:-
No. of Amrit
State Names of Amrit Stations
Stations
Ahmednagar, Ajni (Nagpur), Akalkot Road, Akola,
Akurdi, Amalner, Amgaon, Amravati, Andheri,
Badnera, Balharshah, Bandra Terminus, Baramati,
Belapur, Bhandara Road, Bhokar, Bhusawal,
Borivali, Byculla, Chalisgaon, Chanda Fort,
Maharashtra 132
Chandrapur, Charni Road, Chhatrapati Sambhaji
Nagar, Chhatrapati Shivaji Maharaj Terminus,
Chinchpokli, Chinchwad, Dadar (CR), Dadar (WR),
Dahisar, Daund, Dehu Road, Devlali, Dhamangaon,
Dharangaon, Dharashiv, Dharmabad , Dhule, Diva,No. of Amrit
State Names of Amrit Stations
Stations
Dudhani, Gangakher, Godhani, Gondia, Grant Road,
Hadapsar, Hatkanangale, Hazur Sahib Nanded,
Himayatnagar, Hinganghat, Hingoli Deccan,
Igatpuri, Jalgaon, Jalna, Jeur, Jogeshwari, Kalyan
Jn, Kamptee, Kandivali, Kanjur Marg, Karad, Katol,
Kedgaon, Kinwat, Kopargaon, Kurduwadi Jn, Kurla
Jn, Lasalgaon, Latur, Lokmanya Tilak Terminus,
Lonand Jn, Lonavla, Lower Parel, Malad, Malkapur,
Manmad Jn, Manwath Road , Marine Lines,
Matunga, Miraj Jn, Mudkhed Jn, Mumbai Central,
Mumbra, Murtizapur Jn, Nagarsol, Nagpur Jn,
Nandgaon, Nandura, Nandurbar, Narkher Jn,
Nashik Road, Netaji Subhash Chandra Bose Itwari
Junction, Pachora Jn, Palghar, Pandharpur, Panvel
Jn, Parbhani Jn, Parel, Parli Vaijnath, Partur ,
Phaltan, Prabhadevi, Pulgaon Jn, Pune Jn, Purna
Jn, Raver, Rotegaon , Sainagar Shirdi, Sandhurst
Road, Sangli, Satara, Savda, Selu, Sewagram,
Shahad, Shegaon, Shivaji Nagar Pune, Shri
Chhatrapati Shahu Maharaj Terminus Kolhapur,
Solapur, Talegaon, Thakurli, Thane, Titvala,
Tumsar Road, Umri, Uruli, Vadala Road,
Vidyavihar, Vikhroli, Wadsa, Wardha, Washim,
Wathar
Akodia, Amla, Anuppur, Ashoknagar, Balaghat,
Madhya
Banapura, Bargawan, Beohari, Berchha, Betul,
80
Pradesh
Bhind, Bhopal, Bijuri, Bina, BiyavraRajgarh,
Chhindwara, Dabra, Damoh, Datia, Dewas,No. of Amrit
State Names of Amrit Stations
Stations
Gadarwara, Ganjbasoda, Ghoradongri, Guna,
Gwalior, Harda, Harpalpur, Indore Jn, Itarsi Jn,
Jabalpur, Junnor Deo, Kareli, Katni Jn,
KatniMurwara, Katni South, Khachrod, Khajuraho
Jn, Khandwa, Khirkiya, Laxmi Bai Nagar, Maihar,
Maksi Jn, Mandla Fort, Mandsor, MCS Chhatarpur,
Meghnagar, Morena, Multai, Nagda Jn, Nainpur Jn,
Narmadapuram (Hoshangabad), Narsinghpur,
Nepanagar, Nimuch, Orchha, Pandhurna, Pipariya,
Ratlam, Rewa, Ruthiyai, Sanchi, Sant Hirdaram
Nagar, Satna, Saugor, Sehore, Seoni, Shahdol,
Shajapur, Shamgarh, Sheopur Kalan, Shivpuri,
Shridham, Shujalpur, Sihora Road, Singrauli,
Tikamgarh, Ujjain, Umaria, Vidisha, Vikramgarh
Alot
Development works at railway stations under Amrit Bharat Station Scheme
in the state of Maharashtra and Madhya Pradesh have been taken up at a good
pace. Details of works completed in the states are as under:-
No. of Stations Name of Stations
State
completed
Amgaon, Chanda Fort, Chinchpokli, Devlali,
Dhule, Kedgaon, Lasalgaon, Lonand Jn, Matunga,
Maharashtra 15 Murtizapur Jn, Netaji Subhash Chandra Bose
Itwari Junction, Parel, Savda, Shahad, Vadala
Road
Madhya Katni South, Narmadapuram (Hoshangabad),
06
Pradesh Orchha, Seoni, Shajapur, ShridhamThe works at other stations have also been taken up at good pace and
progress of some of the above stations is as given below:-
Maharashtra:-
Wathar Station: The works of new portico, improvement of station building,
water booth, new main entry gate, parking area, circulating area,
improvement of entrance lobby, compound wall of parking area, platform
shelter at platform no. 1, platform surfacing, improvement of waiting room,
signages and station illumination have been completed. The finishing works
have been taken up.
Nandgaon Station: The works of entrance and exit gate, platform surfacing,
platform shelter, improvement of station building, booking office, Foot Over
Bridge, boundary wall, circulating area, parking area, signage and lighting
have been completed. The finishing works have been taken up.
Nandura Station: The works of platform surfacing, platform shelter, booking
office, entrance gate, improvement of waiting hall, toilet, station building,
circulating area, parking area, signages, coach indication board, station
illumination and boundary wall have been completed. The finishing works
have been taken up.
Hadapsar Station: The works of new station building, waiting hall, 12 m Foot
Over Bridge, underground tank, platform shelter, improvement of platform
surfacing, circulating area, station illumination, signages, lifts, escalators and
landscaping have been completed. The finishing works have been taken up.
Baramati Station: The works of platform shelter, septic tank, toilet, compound
wall, water booth, improvement of booking office, platform surfacing, waiting
room, portico, circulating area, signages and station illumination have been
completed. The finishing works have been taken up.Madhya Pradesh:-
Nainpur Station: The works of improvement of station building, waiting hall,
circulating area, toilet, platform shelters, platform surfacing, coach indication
board, train indication board and 12 m Foot Over Bridge have been completed.
The finishing works have been taken up.
Umaria Station: The works of improvement of station building, waiting hall,
Passenger Reservation System (PRS), parking area, approach roads, toilet,
signages, coach indication board, train indication board and 12 m Foot Over
Bridge have been completed. The finishing works have been taken up.
MCS Chhatarpur Station: The works of improvement of station building,
waiting hall, platform shelter, platform surfacing, toilet, circulating area,
parking area and 12 m Foot Over Bridge have been completed. The finishing
works have been taken up.
Mandla Fort Station: The works of improvement of station building, waiting
hall, parking area, platform shelters, platform surfacing, signages, Passenger
Announcement System, lifts and 12 m Foot Over Bridge have been completed.
The finishing works have been taken up.
Junnor Deo Station: The works of booking office, waiting hall, porch, platform
shelter, improvement of station building, circulating area, parking area, lifts,
signages and 12 m Foot Over Bridge have been completed. The finishing
works have been taken up.
Further, development/redevelopment/upgradation/modernization of stations on
Indian Railways is a continuous and ongoing process and works in this regard are
undertaken as per requirement, subject to inter-se priority and availability of
funds. The priority for development/redevelopment/upgradation/modernisation of
stations is accorded to higher category of station over lower category of station
while sanctioning and executing the works.
Development/upgradation/modernisation of stations including under „Amrit
Bharat Station Scheme‟ is generally funded under Plan Head-53 „CustomerAmenities‟. The details of allocation and expenditure under Plan Head-53 are
maintained Zonal Railway-wise and not work-wise, or station-wise or state-wise.
The state of Maharashtra is covered under the jurisdiction of four railway
zones, namely, Central Railway, South Central Railway, South East Central
Railway and Western Railway. For the last three years and the current year, ₹
11,190 Cr. has been allocated while an expenditure of ₹ 9,198 Cr. has been
incurred during the last three years and current year (up to October, 2025).
The state of Madhya Pradesh is covered under the jurisdiction of seven
railway zones, namely, Central Railway, East Central Railway, North Central
Railway, South Central Railway, South East Central, Western Railway and West
Central Railway. For the last three years and the current year, ₹ 17,294 Cr. has
been allocated while an expenditure of ₹ 14,008 Cr. has been incurred during the
last three years and current year (up to October, 2025).
Development/Upgradation of railway stations is complex in nature involving
safety of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, air-port clearance etc. The progress also
gets affected due to brownfield related challenges such as shifting of utilities
(involving water/sewage lines, optical fiber cables, gas pipe lines, power/signal
cables, etc.), infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close proximity of
tracks and high voltage power lines, etc. and these factors affect the completion
time. Therefore, no time frame can be indicated at this stage.
Improvement in passenger amenities at Railway Station is a continuous and
ongoing process and works in this regard are undertaken as per requirement
feasibility, inter-se priority and availability of funds.
Digital Ticketing:-
Indian Railways has launched RailOne App on 01.07.2025, which combines
all the public facing services of Indian Railways eliminating the need of
downloading multiple apps of Indian Railways for different purposes. The appprovides single sign-on facility meaning that user need not remember multiple
login credentials for availing different services of Indian Railways. The app has its
own e-wallet (R-wallet) which can be used for purchase of reserved, unreserved
and platform tickets. Special security measures have been built to safeguard the
app against vulnerabilities and potential attacks. RailOne App provides a smooth
payment facility at par with the leading travel apps.
Expansion of Rail Connectivity:-
Railway projects are surveyed/ sanctioned/executed Zonal Railway wise
and not State-wise/Area wise/Parliamentary constituency-wise as the Railway‟
projects may span across State boundaries. Railway projects are sanctioned on
the basis of remunerativeness, traffic projections, last mile connectivity including
hilly and border regions, missing links and alternate routes, augmentation of
congested/saturated lines, demands raised by State Governments, Central
Ministries, Members of Parliament, other public representatives, Railway‟s own
operational requirement, socio-economic considerations etc. depending upon
throwforward of ongoing projects and overall availability of funds.
During the last three years i.e. FY 2022-23, 2023-24, 2024-25 and the
current FY 2025-26, 284 New Line surveys of a total length of 27,492 km have
been sanctioned throughout the country including hilly and border regions.
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure
projects (154 New Line, 33 Gauge Conversion and 244 Doubling) of total length
35,966 Km, costing approx. `6.75 lakh crore are sanctioned including hilly and
border regions, out of which, 12,769 Km length has been commissioned and an
expenditure of approx. `2.91 lakh crore has been incurred upto March, 2025. The
summary is as under:-
Total Length Length Commissioned Total Exp
No of
Category NL/GC/DL till Mar'25 upto Mar'25
Projects
(Km) (Km) (in Crore)
New Lines 154 16,142 3,036 1,45,318Gauge
33 4,180 2,997 22,753
Conversion
Doubling/
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway‟s website.
The details of commissioning/laying of new track across Indian Railways
are given below:-
New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.57 Km/day ( more than 2 times)
In 2024-25, 3248 km sections have been commissioned across Indian
Railways and in current FY 2025-26, 895 km sections have been commissioned.
Madhya Pradesh
Jabalpur-Gondia Gauge Conversion Project (300 km), passing through
Balaghat parliamentary constituency has been recently commissioned. To further
improve connectivity in Balaghat Lok Sabha constituency, survey for doubling of
Jabalpur-Gondia line (231 km) has been completed. Detailed project report has
been prepared with the project having an estimated cost of Rs. 4,671 crore.
Budget allocation in the recent years has increased significantly. Budget
allocation for Infrastructure projects and safety works, falling fully/partly in the
State of Madhya Pradesh is as under:-
Period Outlay
2009-14 ₹632 crore/year
2025-26 ₹14,745 crore (More than 23 times)The details of commissioning/laying of new track falling fully/partly in the
State of Madhya Pradesh during 2009-14 and 2014-25 is as under:-
New Track
Period Average Commissioning of new tracks
Commissioned
2009-14 145 Km 29 Km/year
2014-25 2651 Km 241 Km/year (More than 8 times)
As on 01.04.2025, 24 Railway projects (08 New Lines, 02 Gauge Conversion
and 14 Doubling), of total length of 4,740 Km costing ₹89,543 crore falling
fully/partly in the State of Madhya Pradesh, are sanctioned, out of which 2,092 Km
length has been commissioned and an expenditure of ₹41,401 crore has been
incurred upto March 2025. The status of work is summarized as under:
Plan Head No. of Total Length Expenditure upto
projects Length Commissione March 2025
(in Km) d (in Km) (₹in Cr.)
New Lines 8 1914 544 15,069
Gauge Conversion 2 809 430 6,766
Doubling/Multitrac
14 2017 1118 19,566
king
Total 24 4,740 2,092 41,401
Details of some of the recently completed projects falling fully/partly in the
State of Madhya Pradesh are as under:-
S.No. Name of Project Latest Cost
(₹in Crores)
1. Guna- Etawah New Line (348 Km) 683
2. Jabalpur-Gondia Gauge Conversion (300 Km) 2005
3. Chhindwara-Nagpur Gauge Conversion (150 Km) 1512
4. Chhindwara-Mandla Fort Gauge Conversion (182 Km) 1268S.No. Name of Project Latest Cost
(₹in Crores)
5. Ghat Pindari-Balkheda Doubling (6 Km) 29
6. Guna-Ruthiyai Doubling (20 Km) 175
7. Khodri – Anuppur Doubling (62 Km) 489
8. Jukhei Chord line, Bye Passing the Katni Yard (2 Km) 12
9. Sontalai-Bagratawa Doubling (7 Km) 110
10. Itarsi-Budhni 3rd line (25 Km) 286
11. Teegaon-Chichonda Ghat Section 3rd line (17 Km) 176
12. Bhopal-Bina 3rd line (145 km) 1075
13. Barkhera-Bhopal 3rd line (41 km) 473
14. Nagda-Ujjain Doubling of Gambhir Bridge (2 Km) 28
15. Pendra Road-Anuppur 3rd line (50 Km) 394
16. Bina-Kota Doubling (283 km) 2477
17. Nimach-Chittaurgarh Doubling (56 Km) 560
18. Khodri-Anuppur Doubling with flyover at Bilaspur (72 Km) 792
19. Budhni-Barkhera 3rd line (27 Km) 1703
20. Indore-Dewas-Ujjain Doubling (79 Km) 757
21. Powerkheda-JujharpurRail flyover (16 Km) 443
22. Anuppur-Katni 3rd line (165 Km) 2311
23. Ramna-Singrauli doubling (160 Km) 2436
24. Karaila Road- Shaktinagar Doubling(32 Km) 763
25. Malkhedi-Mahadeokhedi Doubling (12 Km) 59Some of major projects falling fully/partly in the State of Madhya Pradesh
which have been taken up are as under:-
S. No Project Cost
(₹in Crores)
1. Manmad - Indore New Line (360 Km)
18529
2. Ramganjmandi-Bhopal New Line (277 Km)
5073
3. Indore-Budni New Line (198 Km)
7474
4. Lalitpur-Satna, Rewa-Singrauli&Mahoba-Khajuraho
8914
New Line (541 Km)
5. Nimach-Badi Sadri New Line (48 Km)
495
6. Gwalior-Sheopurkalan Gauge Conversion with
2913
extension to Kota (284 Km)
7. Itarsi- Nagpur 3rd line (280 Km)
2450
8. Jhansi-Bina 3rd line (153 Km) 2002
9. Mathura-Gwalior-Jhansi 3rd line (274 Km) 5924
10. Katni - Bina 3rd line (260 Km)
3138
11. Katni- Grade separator / Bypass (35 Km)
2300
12. Katni- Singrauli Doubling (257 Km)
4377
13. Satna-Rewa Doubling (50 Km)
590
14. Shahdol-Singhpur4th Line (6 Km)
54
15. Bhusawal-Khandwa 3rd & 4th Line (131 Km)
3285
In last three years, 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 61 surveys (18 New Line & 43 Doubling) covering a total length of 5,901
Km has been sanctioned falling fully/partly in the State of Madhya Pradesh.
Maharashtra:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in the
State of Maharashtra is as under:-Period Outlay
2009-14 ₹ 1,171 crore/year
2025-26 ₹ 23,778 crore (More than 20 times)
Commissioning of sections (New Line, Gauge Conversion and Doubling)
falling fully/partly in the State of Maharashtra during 2009-14 and 2014-2025 is as
under:-
New track
Period Average commissioning of new tracks
Commissioned
2009-14 292 Km 58.4 Km/year
2014-25 2,292 Km 208.36 Km/year (more than 3 times)
As on 01.04.2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25
Doubling), of a total length of 5,098 km, costing ₹ 89,780 crore, falling fully/partly
in Maharashtra, are sanctioned, out of which 2,360 km length has been
commissioned and an expenditure of₹39,407 crore has been incurred upto March‟
2025. The summary is as under:-
No. of Total Length Length Commissioned Total Exp
Category sanctioned NL/GC/DL till Mar'25 upto Mar'25
Projects (in Km) (in Km) (₹ in Cr.)
New Lines 11 1,355 234 10,504
Gauge
02 609 334 4,286
Conversion
Doubling /
25 3,134 1,792 24,617
Multitracking
Total 38 5,098 2,360 39,407Details of some of the recently completed projects falling fully/partly in
Maharashtra are as under:-
Cost
S.No. Project
(₹ in crore)
1. Jabalpur-Gondia Gauge Conversion (300 Km) 2,005
2. Chhindwara-Nagpur Gauge Conversion (150 Km) 1512
3. Panvel-Pen Doubling (35 Km) 263
4. Panvel-Roha Doubling (75 Km) 31
5. Pen-Roha Doubling (40 Km) 330
6. Udhna-Jalgaon Doubling (307 Km) 2,448
7. Mudkhed-Parbhani Doubling (81 Km) 673
8. Bhusawal – Jalgaon 3rd Line (24 Km) 325
9. Jalgaon-Bhusawal 4th line (24 Km) 261
10. Daund-Gulbarga Doubling (225 Km) 3,182
11. Pune-Miraj-Londa Doubling (466 Km) 6,463
12. Manmad- Jalgaon 3rd line (160 Km) 1,677
Some of the main projects falling fully/partly in the Maharashtra which have
been taken up are as under:-
Cost
S.No. Name of the project
(₹ in crore)
1. Ahalyanagar-Beed-Parle Vaijnath New Line (261 Km.) 4,957
2. Baramati-Lonand New Line (64 Km.) 1,844
3. Wardha-Nanded New Line (284 Km.) 3,445
4. Manmad-Indore New Line (360 Km.) 18,529
5. Wadsa-Gadchiroli New Line (52 Km) 1,886
6. Jalna -Jalgaon New Line (174 Km.) 5,804
7. Daund-Manmad Doubling (236 Km.) 30,376
8. Kalyan-Kasara - 3rd line (68 Km.) 1,433Cost
S.No. Name of the project
(₹ in crore)
9. Wardha -Nagpur 3rd line (76 Km.) 698
10. Wardha-Ballarshah 3rd line (132 Km.) 1,385
11. Itarsi- Nagpur 3rd line (280 Km.) 2,450
12. Rajnandgaon-Nagpur 3rd line (228 Km.) 3,545
13. Wardha-Nagpur 4th line (79 Km.) 1,137
14. Jalgaon-Manmad 4th Line (160 Km) 2,574
During the last three years i.e. FY 2022-23, 2023-24, 2024-25 and the
current FY, 98 Surveys (29 New Line , 2 Gauge Conversion and 67 Doubling) of
total length 8603 Km falling fully/ partly in the State of Maharashtra, have been
sanctioned.
To improve the connectivity in Mumbai suburban area and to meet the
future demands of passengers, Mumbai Urban Transport Project (MUTP)-II costing
₹8,087 crore, MUTP-III costing ₹10,947 crore and MUTP-IIIA costing ₹33,690 crore
have been sanctioned. These projects include following works in Mumbai
Suburban Area:-
Cost
S. No. Name of project
(₹ in crore)
1. 6th Line Mumbai Central-Borivali (30 km) 919
2. Extension of Harbour Line Goregaon-Borivali (7 km) 826
3. Virar-Dahanu Road 3rd & 4th Line (64 km) 3,587
4. 5th & 6th Line CSTM-Kurla (17.5 km) 891
5. Panvel-Karjat Suburban Corridor (29.6 km) 2,782
6. Airoli-Kalwa (elevated) Suburban Corridor link (3.3 km) 476
7. 5th & 6th line Borivali-Virar (26 km) 2,184
8. 4th line between Kalyan-Asangaon (32 km) 1,759
9. 3rd & 4th line between Kalyan-Badlapur (14.05 km) 1,510
10. Kalyan Yard-Segregation of Main Line & Suburban 866Vasai bye pass line (Double line) between Naigaon and
11. 176
Juchandra (5.73 Km)
12. Trespass Control Measures such as FOBs etc. (34 551
locations)
To enhance sub-urban rail capacity, a total of 238 rakes of 12 car have also
been sanctioned under MUTP-III & IIIA at a cost of ₹19,293 crore. The process for
procurement of these rakes has been taken up.
Measures to reduce Freight Delays:-
In order to ensure smoother and quicker transit of freight trains and faster
turnaround times, Indian Railways have taken measures to increase network
capacity including infrastructure projects such as Eastern Dedicated Freight
Corridor (EDFC) and Western Dedicated Freight Corridor (WDFC) to create
dedicated freight path to give exclusive access to freight trains.
Further, the capacity enhancement works and rolling stock programs are
planned and being executed, which upon completion, will reduce transit time of
freight trains and lead to better speed. The details are as under:-
a. Doubling/Multi-Tracking on critical sections and high-density network.
b. Provision of Rail flyover and Bypass lines at junction stations.
c. Induction of higher horsepower locomotives.
d. Induction of higher capacity and high speed wagons.
e. Improvement to terminals and their connectivity to trunk routes.
Cost Effective Transport:-
The following measures have been taken to promote cost effective
transport:-
I. Joint Parcel Product-Rapid Cargo Service (JPP-RCS) Scheme:- This scheme
offer tailor-made logistics to meet specific needs of the customer and
provide door-to-door parcel services. Under the scheme, provision has been
made for online booking of parcel space in these services throughAggregators (in addition to India Post) on „Virtual Aggregation Platform
(VAP)‟.
II. Short term leasing of leased SLR and lease VPs has been permitted through
e-auction.
III. Utilization of BCN/BCNA stock lying idle as deemed VPU (where parcel vans
are not available) for carriage of parcel traffic has been permitted.
Power has been delegated to Zonal Railways to reduce the composition of
Parcel Rakes for transportation of mixed perishables goods traffic including fruits
and vegetables upto 15 Parcel vans plus 1 SLRs instead of standard composition
of 20 Parcel vans plus 1 SLRs. Orange, Mango and Banana traffic when moved in
BCN/BCNA/BCX/BCXN Rakes are charged at scale-P minus 50%.
Electrification and Carbon Footprint Reduction:-
Electrification of railway network on Indian Railways has been taken up in
mission mode. So far, about 99.1% of Broad Gauge (BG) network has been
electrified. The electrification in remaining network has been taken up.
Electrification carried out during 2014-25 and before 2014 is as under:-
Period Route Kilometer
Before 2014 (about 60 years) 21,801
2014-25 46,900
In Maharashtra and Madhya Pradesh, entire existing BG network has been
electrified. Further, all new line/multitracking projects are being sanctioned and
constructed with electrification.
Indian Railways is committed to sustainable operation through near total
Railway Electrification combined with use of renewable energy sources, a
combination of solar, wind and other renewable sources based on strategic power
procurement planning, thus contributing to carbon footprint reduction.
*****