Executive Summary:
This document details the ongoing National Highway (NH) projects in West Bengal as of July 24, 2025, including project lengths, allocated funds, and project status. It identifies projects behind schedule and notes project cost escalations. The information was provided in response to Lok Sabha Unstarred Question No. 779.
Key Points / Main Content:
Project Overview:
* A total of 34 National Highway (NH) projects are currently ongoing in West Bengal.
Project Status:
* 13 out of the 34 ongoing NH projects are behind schedule.
Project Details:
* The document includes an annexure with details of specific NH projects, including:
* NH number and name
* Project length in kilometers
* Sanctioned date
* Scheduled completion date
* Total Project Cost (TPC) in Crores of Rupees
* Physical progress
* Cost escalation, if any, in Crores of Rupees
Impact Analysis:
Ministry of Road Transport and Highways:
* Impact: Required to provide details on NH projects in West Bengal, monitor project progress, and address project delays and cost escalations.
* Action Required: Continue oversight of projects and address delays.
West Bengal State Government:
* Impact: Affected by the progress of NH projects within the state, which impact connectivity and infrastructure development.
* Action Required: Coordinate with the Ministry of Road Transport and Highways to facilitate project completion.
Citizens of West Bengal:
* Impact: Benefit from improved road infrastructure, reduced travel times, and enhanced connectivity upon project completion.
* Action Required: None.
Contractors and Construction Companies:
* Impact: Responsible for executing the NH projects within the specified timelines and budget.
* Action Required: Expedite project progress to meet deadlines and manage costs effectively.
Key Entities Referenced
Ministry of Road Transport and Highways: The Indian government ministry responsible for the development and maintenance of national highways.
West Bengal: A state in eastern India where the mentioned National Highway projects are located.
National Highways (NHs): A network of highways that are maintained by the central government of India.
SHRI KHALILUR RAHAMAN: A member of Lok Sabha who raised the question about NH projects in West Bengal.
SHRI NITIN JAIRAM GADKARI: The Minister of Road Transport and Highways who answered the question in Lok Sabha.
NH81: A specific National Highway in West Bengal where construction of a new road is planned.
Darjeeling, West Bengal: A district in West Bengal where road works are being undertaken on NH110
NH10: A specific National Highway in West Bengal where slope protection work is planned.
GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 779
ANSWERED ON 24TH JULY 2025
NHs PROJECTS IN WEST BENGAL
779. SHRI KHALILUR RAHAMAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the details regarding the ongoing National Highways (NHs)
projects in West Bengal including their total length and funds
allocated thereof;
(b) the number of these projects that are behind schedule; and
(c) the details of project cost escalation, if any, project-wise?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) and (c) Details are Annexed.
(b) Presently, 13 out of 34 ongoing National Highways (NHs)
projects in West Bengal are behind schedule.ANNEXURE
ANNEXURE REFERRED TO IN REPLY OF PARTS (a) AND (c) OF LOK
SABHA UNSTARRED QUESTION NO. 779 FOR ANSWER ON 24.07.2025
ASKED BY SHRI KHALILUR RAHAMAN REGARDING NHs PROJECTS IN
WEST BENGAL
Sanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
Construction of new road at
the missing link portion of N
H-81 along the approved alig
02-11-20 01-11-20
1 nment between Harishchand 81 13.15 271.17 82.56% 20.03
16 18
rapur & Easter approach of
Kalindri-Bridge, in the distric
t of Malda.
Construction of 4-lane ROB (
Twins 2-lanes) and its appro
aches in replacement of leve 24-02-20 23-02-20
2 2B ROB 145.89 22.67% 54.44
l crossing at km 3.950 of NH- 24 26
2B (Railway km 226/0) at Tal
it.
Construction of twins 2-lane
ROB and its approaches in r
eplacement of existing level
crossing Gate No. -38 (Rly k 16-01-20 14-01-20
3 60 ROB 101.76 69.47% -4.22
m 165/21-165/23) between C 23 25
hondrakona Road & Garbeta
Stations in Kadamadiha at k
m 159.448 of NH-60.
Construction of ROB and its
approaches in lieu of Level C 07-08-20 06-08-20
4 60 ROB 155.87 10.61% -17.30
rossing No. 10/B/T at km 307 23 25
.050 of NH-60 (Bhimgarh).
Construction of ROB and its
appraoches in lieu of level cr 10-07-20 09-07-20
5 60 ROB 127.21 75.45% -10.07
ossing No. 21/SPL/E at km 33 21 23
8.600 of NH-60 (Suri).
Construction of proposed RO
B & its approaches on NH-60
at 193+800 in lieu of LC Gate 13-11-20 12-11-20
6 60 ROB 62.09 35.31% -0.69
No. 39/A/3E in the state of W 21 23
est Bengal.Sanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
Development to 4/6-lanning o
f NH-31 (New NH-10) with bo
th side service roads from k
m 569.258 to km 581.030 (en
d of AH-02 project on NH- 31 22-03-20 19-09-20
7 10 11.77 995.04 51.21% 64.16
near Shivmandir to Sevoke A 23 25
rmy Cantonment) in districts
of Darjeeling and Jalpaiguri i
n the state of West Bengal o
n EPC Mode
Reconstruction and Widenin
g of 8 nos. narrow culvert at
km 22.445, km 22.450, km 2
2.840, km 27.565 , km 29.00
0 (half portion) , km 29.500,
km 30.650, km 38.290 & spo
t improvement from km 22.3
97 to km 22.442, km 22.445 t
o km 22.450, km 22.453 to k
m 22.493, km 26.855 to km 2
6.935, km 27.125 to km 27.1
75 , km 27.492 to km 27.562,
km 27.565 to km 27.710 , km
29.487 to km 29.502, km 29. 01-03-20 01-03-20
8 110 Culvert 13.49 76.27% 0.15
506 to km 29.513, km 32.710 24 25
to km 32.750 km, km 32.885
to km 32.910, km 38.185 to k
m 38.285, km 38.290 to km 3
8.330 & repair of old parapet
s, construction of new parap
ets, road signage such as M
edian Marker, Road Marking
etc in selected stretches fro
m km 20.00 to km 40.00 of N
H-110 (Old NH-55) in the Dist
rict of Darjeeling under Annu
al Plan 2022-23 sanction -reg
.Sanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
(i) Reconstruction of a box c
ulvert at km 3.780 in connec
tion with the Widening of NH
-35 (New NH-112) under NH
Division No.-V, P.W. (Roads)
Directorate, (ii) Reconstructi
on of minor bridge at km 13.
872 of NH-35 (New NH-112)
under NH Division No. V, P.W
07-11-20 06-11-20
9 . (Roads) Directorate (iii) Re 112 Culvert 40.13 70.00% NIL
23 25
construction of bow string gi
rder type minor bridge at km
16.567 of NH35 (New NH-112
) under NH Division No.- V, P.
w. (Roads) Directorate, in th
e district of North 24-Pargan
as, West Bengal during the y
ear 2022-23 in EPC mode - re
g.
Construction or 4 lane Ranig
anj Bypass of length 5.261 k
m on NH-60 (new NH-14) fro
08-03-20 08-03-20
10 m km 273.00 of NH to km 47 60 5.26 410.83 37.50% 4.58
24 26
8.18 of NH-2 (New NH 16) in
paschim Bardhaman, West B
engal in EPC Mode- reg.
Slope Stabilization Scheme
at location of landslide at k
m 52.240 km of NH-110 (Old
NH55) at Tindharia, West Be
ngal & Permanent Restoratio Slope S
06-09-20 06-03-20
11 n of damaged Road bench at 110 tabiliza 24.52 52.02% NIL
24 26
km 42.80 of NH -110 (Old NH tion
-55) under NH Division-IX in t
he district of Darjeeling Wes
t Bengal during the year 202
2-2023.
Widening Carriageway width
along with construction of fo
otpath from km 69.00 to km
71.40, Permanent Restoratio
n of depressed road bench a
t km 60.480 and Restoration
of Valley side protection wal
10-01-20 10-07-20
12 l at km 60.950 in between k 110 2.40 18.45 99.03% NIL
24 25
m 60 to km 61 & Repair & Re
habilitation of Panchanai bri
dge at km 75.030 of NH-110 (
Old NH- 55) in the district of
Darjeeling West Bengal durin
g the year 2022-2023 -Sancti
on -Reg.Sanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
Improvement of Spots from 2
1.710 km to 21.838 km (inclu
ding reconstruction & culver
t widening), 21.921 km to 22.
000 km (including drop & gui
des), 23.7600 km to 23.800 k
m, 26.597 km to 26.705 km (i
ncluding drop & guides), 28.
270 km to 28.340 km, 35.878 11-09-20 11-09-20
13 110 0.79 14.48 47.00% NIL
km to 35.980 km, 36.025 km 24 25
to 36.135 km , 36.245 km to
36.400 km (includ+F55:F59in
g reconstruction & culvert w
idening) on NH-110 (Old NH-
55) in between km 20.00 to k
m 40.00 of NH-110 (Old NH-5
5) under NH Division-IX, in th
e district of Darjeeling.
Construction of 3 (three) nos
. newsingle cell type box cul
vert (2.0 m X 3.0m) at chaina
ges 54+150 km, 54+750 km,
& 55+150 km of NH-12(old N
H-117) including improveme 16-04-20 13-10-20
14 12 Culvert 1.64 0% NIL
nt offlaring portion on either 25 25
side of each culvert during t
he year 2024-2025under N.H.
Division No. 1, in the district
of South 24 parganas, WestB
engal.
Re- senctioning from Km 0.0
0 to Km 0.500, strengthening
from km 0.00 to km 8.20 and
km 15.00 to km 15.50 and Wi
dening and strenghening fro 11-04-20 10-04-20
15 327 15.50 49.96 32% NIL
m km 8.20 to km 15.00 of NH 25 26
-327 (old NH-31C) in the distr
ict of Darjeeling under NH Di
vision No. IX P.W.(Roads) Dir
ectorate, West Bengal
Repair and Rehabilitation wo
rks for 13 nos. distressed bri
dhes in the Birbhum district
as a part of Detailed project
Report for 4- Lanning of NH-6
0 (New NH- 14) from km 115. 07-05-20 07-05-20
16 14 Bridge 31.61 0% NIL
000 (Kharagpur) to km 422.4 25 27
50 (Moregram) in the State o
f West Bengal (Package III-
Bakreswar Bridge at 322.550
km, Bramhani Bridge at 398.
450 km amd Gambhira BridgSanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
e at 418.918 km).
Repair and Rehabilitation wo
rks for 13 nos. distressed bri
dhes in the Birbhum district
as a part of Detailed project
Report for 4- Lanning of NH-6
0 (New NH- 14) from km 115.
000 (Kharagpur) to km 422.4
50 (Moregram) in the State o
28-04-20 27-04-20
17 f West Bengal (Package IV- T 14 Bridge 37.58 15% NIL
25 27
ilpara Right Canal Bridge at
342.660 km, Tilpara Bridge a
t 343.950 km,Khairakuri Brid
ge at 344.880 km, Dwarka C
anal Bridge at 358.740 km, D
eucha Barrage Bridge at 359
.050 km).
Repair and Rehabilitation wo
rk for 13 nos. distressed brid
ges in the Birbhum district a
s a part of Detailed Project R
eport for 4- Lanning of NH-60
(New NH-14) from km 115.00
07-05-20 06-05-20
18 0 (Kharagpur) to km 422.450 14 Bridge 7.86 12% NIL
25 26
(Moregram) in the State of W
est Bengal (Package I). Sinju
ri-Bridge at km 308.660, Sinj
uri-2 at km 309.020 Chandra
bhaga bridge at km 333.400
Repair and Rehabilitation wo
rk for 13 nos. distressed brid
ges in the Birbhum district a
s a part of Detailed Project R
eport for 4- Lanning of NH-60
28-04-20 28-07-20
19 (New NH-14) from km 115.00 14 Bridge 8.74 30% NIL
25 26
0 (Kharagpur) to km 422.450
(Moregram) in the State of W
est Bengal (Package II) MD
Bazar Mini Bridge at km 350.
530 & Kargil bridge at km 35Sanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
3.040
Improvements of spots inclu
ding reconstruction & wideni
ng of culverts in between Ch
.40.000 to 65.000 of NH 55 (n 23-04-20 22-04-20
20 110 2.85 32.35 10.06% NIL
ew NH 110) under N.H. Divisi 25 26
on-IX(I), in the district of Dar
jeeling, West Bengal in the F
Y 2024-25
Improvement of spots (inclu
ding widening of culvert, dro
ps & guide) from km 4.390 to
km 4.585, km 5.328 to km 5.
430, km 8.520 to km 9.075 (a
t 02 nos. of locations), km 9.
17-03-20 16-03-20
21 335 to km 9.520 and km 12.0 110 1.121 15.02 1.14% NIL
25 26
60 to km 12.235 on NH110 (
Old NH-55) in between km 0.
00 to km 20.00 of NH- 110 un
der NH Division-IX in the Dist
rict of Darjeeling, West Beng
al.
Bagrakot-Kafer (Package - I 04-10-20 03-04-20
22 717A 15.24 402.94 98.54% 32.81
VA) 19 22
05-10-20 05-04-20
23 Bagrakot-Kafer ( Pkg IV-B) 717A 12.6 295.97 95.71% 32.18
20 23
05-10-20 05-04-20
24 Kafer- Lava More (Pkg-VA) 717A 21.1 273.78 95.12% 31.36
20 23
Lava More Pedong bypass to 20-10-20 17-04-20
25 717A 16.55 395.59 91.24% 39.61
Reshi Border (Pkg-VB) 20 22
Slope Protection and landsli
de mitigation at 4 Vulnerable
LocationsSlope protection a
nd landslide mitigation at 4 v
ulnerable locations (km 1.95
0 to Km 2.100, km 11.100 to
26-06-20 26-06-20
26 11.450, km 22.435 to km 22. NH-10 0.62 152.27 0% NIL
25 27
485 and km 22.610 to km 22.
680) within Sevoke-Rangpo s
ection of NH-10 (old NH-31A)
in Kalimpong district in the
State of West Bengal on EPC
mode
Slope Protection and Landsli
de Mitigation at 2 Vulnerable
Locations [km 23.20 to km 2
3.960 and 26.530 to km 26.5
06-09-20 08-03-20
27 80] within Sevoke-Rangpo S NH-10 0.81 68.49 2% NIL
24 26
ection of NH-10(old NH-31A)
in the district of Kalimpong i
n West Bengal during FY 202
3-24 on EPC modeSanctio Project c
Appoint Schedul
ned Cos Physica ost escal
Sl. NH N Length ed date/ ed Comp
Project Name t/TPC (R l progre ation, if a
No o (in km) Date of letion D
s. in Cro ss (%) ny (Rs. in
start ate
re) Crore)
4 lane bridge over River Gan
ga at downstream of Farakk 20-12-20 18-12-20
28 12 5.468 622.04 92.47% NIL
a Barrage of NH-12 (Old NH- 18 21
34)(4L NHDP-III,5 Km, EPC)
Up-gradation to 2L+PS confi
12-12-20 09-06- 2
29 guration of Purulia-Chandil S 18 73.281 1612.1 96.19% NIL
19 2
ection of NH-18 (Old NH-32)
Construction of 4-laning road
for Purulia Bypass Section fr
om Km 84.030 to Km 94.345
05-02-20
30 of NH-18 (Old NH-32) (Length 18 10.315 557.6 09-08-23 91.41% 14.23
22
10.315 km) in the state of W
est Bengal under NHDP-IV-B
on EPC Mode
6L Elevated Kona Expressw
06-06-20
31 ay from Km. 0.145 to Km. 7.3 117 7.192 1212.56 03-12-26 19.25% NIL
24
37 of NH-117
4-laning of the de-scoped str
etches from Km. 115.342 to
Km. 191.700 of NH-12 (Old N
H-34) in Nadia district (3.962 16-07-20
32 12 10.554 201.1 11-01-26 30.7% NIL
) & Murshidabad district (5.5 24
38) in the State of West Ben
gal on EPC Mode under NH(O
))
4-laning of Barasat-Barajagul
i Section of NH-12 (Old NH-3
4) from Km. 31.000 to Km. 4
12-08-20
33 8.679 in the district of North 12 17.679 352 13-02-26 6% NIL
24
24-Parganas in the State of
West Bengal on EPC Mode u
nder NH(O)
4 laning of Falakata to Salsa
04-12-20
34 labari of NH-27 (Old NH-31D) 27 41.654 2154.96 01-06-27 27.03% NIL
24
(Pck-2A)
10867.0
Total 285.90
9
*****